New Works
10.59 Five new pumping stations were commissioned, of which those at Batty's Belvedere, Tsing Yi, Shek Pik Valve Tower and Tong Fuk are fully automatic electric stations and that at Tai Wan is a semi-automatic diesel station. In addition, the installation of electrical services was completed at eleven new stations. Installation of equipment was in hand at three pumping stations at Castle Peak, Hong Lok Yuen and Ting Kok; procurement of new plant for five pumping stations at Chai Wan, Eastern, Cheung Sha Wan, Peninsula and Tsuen Wan was in hand; and design work on three pumping stations at Chai Wan, Bowen Road and Albany was in progress. An automatic control board was installed at Central Water Front Salt Water Pumping Station and a similar set was purchased for Sau Mau Ping Salt Water Pumping Station.
10.60 Flow and level transmission equipment was installed at three service reservoirs at Mount Cameron, Shau Kei Wan and Ho Man Tin and installation of similar equipment for a further six locations was in hand on the Island. Procurement of level metering equipment for five locations on the Island and Mainland was in hand.
General
DESALTING DIVISION
Chief Engineer: Under recruitment
Senior Engineer:
Wu Yu-ngong, M.Eng., C.Eng., M.I.Mech.E.
10.61 This is a newly constituted Division, arising from the Department's entry into the desalting field, and comprises two sub-divisions, a Project Sub-Division for which staff recruitment commenced at the end of the year and which will supervise the manufacturing stage of the 40 million gallons per day desalter, and an Experimental Sub-Division which is operating and evaluating data from the experimental evaporator which has been installed on the site selected for the larger plant. Pending recruitment of the project team, the Experimental Sub-Division, in conjunction with the Mechanical, Electrical and Construction Divisions and the Contracts and Claims Unit, has been
145
New Works
10.59 Five new pumping stations were commissioned, of which those at Batty's Belvedere, Tsing Yi, Shek Pik Valve Tower and Tong Fuk are fully automatic electric stations and that at Tai Wan is a semi-automatic diesel station. In addition, the installation of electrical services was completed at eleven new stations. Installation of equip- ment was in hand at three pumping stations at Castle Peak, Hong Lok Yuen and Ting Kok; procurement of new plant for five pumping stations at Chai Wan, Eastern, Cheung Sha Wan, Peninsula and Tsuen Wan was in hand; and design work on three pumping stations at Chai Wan, Bowen Road and Albany was in progress. An automatic control board was installed at Central Water Front Salt Water Pumping Station and a similar set was purchased for Sau Mau Ping Salt Water Pumping Station.
10.60 Flow and level transmission equipment was installed at three service reservoirs at Mount Cameron, Shau Kei Wan and Ho Man Tin and installation of similar equipment for a further six locations was in hand on the Island. Procurement of level metering equipment for five locations on the Island and Mainland was in hand.
General
DESALTING DIVISION
Chief Engineer: Under recruitment
Senior Engineer:
Wu Yu-ngong, M.Eng., C.Eng., M.I.Mech.E.
10.61 This is a newly constituted Division, arising from the Depart- ment's entry into the desalting field, and comprises two sub-divisions, a Project Sub-Division for which staff recruitment commenced at the end of the year and which will supervise the manufacturing stage of the 40 million gallons per day desalter, and an Experimental Sub- Division which is operating and evaluating data from the experimental evaporator which has been installed on the site selected for the larger plant. Pending recruitment of the project team, the Experimental Sub-Division, in conjunction with the Mechanical, Electrical and Con- struction Divisions and the Contracts and Claims Unit, has been