Cheung Chau Praya Extension

6.47. A contract was let and work proceeded on the construction of a 250-foot extension northwards of the existing Cheung Chau Praya.

Shek Pik Pier

6.48. A contract was let and work started on the construction of a reinforced-concrete pier at Shek Pik. This pier will serve the Tong Fuk Prison, Shek Pik Training Centre and fishing craft in the southern Lantau area.

Tsing Yi Public Pier

6.49. A reinforced-concrete waiting shelter for ferry passengers was constructed adjacent to the public pier.

Sai Kung

6.50. A contract was let and work started on a small reclamation adjacent to Sai Kung cinema for the construction of a latrine and bath-house building.

Navigational Aids

6.51. As part of the overall plans for the continuing improvement of navigational aids in the Colony waters, light beacons were constructed at Po Toi Island, Lo Chau and Junk Island.

Refuse Disposal Incinerators

6.52. Planning work continued in connection with the second Kowloon incinerator to be sited adjacent to the first at Lai Chi Kok. The work is being carried out by Consulting Engineers and the Division is responsible for liaison work.

6.53. The Division completed the construction of a new reinforced-concrete ramp for loading barges at Kennedy Town and a pumphouse, refuse collection pier and turbo-alternator house at Lai Chi Kok.

Kwai Chung Container Terminal

6.54. The engineering report on the proposed container terminal to be sited at Kwai Chung was completed and published. This report


Page 65

Edit History

2026-05-12 01:44:16 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Cheung Chau Praya Extension 6.47. A contract was let and work proceeded on the construction of a 250-foot extension northwards of the existing Cheung Chau Praya. Shek Pik Pier 6.48. A contract was let and work started on the construction of a reinforced-concrete pier at Shek Pik. This pier will serve the Tong Fuk Prison, Shek Pik Training Centre and fishing craft in the southern Lantau area. Tsing Yi Public Pier 6.49. A reinforced-concrete waiting shelter for ferry passengers was constructed adjacent to the public pier. Sai Kung 6.50. A contract was let and work started on a small reclamation adjacent to Sai Kung cinema for the construction of a latrine and bath-house building. Navigational Aids 6.51. As part of the overall plans for the continuing improvement of navigational aids in the Colony waters, light beacons were constructed at Po Toi Island, Lo Chau and Junk Island. Refuse Disposal Incinerators 6.52. Planning work continued in connection with the second Kowloon incinerator to be sited adjacent to the first at Lai Chi Kok. The work is being carried out by Consulting Engineers and the Division is responsible for liaison work. 6.53. The Division completed the construction of a new reinforced-concrete ramp for loading barges at Kennedy Town and a pumphouse, refuse collection pier and turbo-alternator house at Lai Chi Kok. Kwai Chung Container Terminal 6.54. The engineering report on the proposed container terminal to be sited at Kwai Chung was completed and published. This report Page 65
Baseline (Original)
Cheung Chau Praya Extension 6.47. A contract was let and work proceeded on the construction of a 250-foot extension northwards of the existing Cheung Chau Praya. Shek Pik Pier 6.48. A contract was let and work started on the construction of a reinforced-concrete pier at Shek Pik. This pier will serve the Tong Fuk Prison, Shek Pik Training Centre and fishing craft in the southern Lantau area. Tsing Yi Public Pier 6.49. A reinforced-concrete waiting shelter for ferry passengers was constructed adjacent to the public pier. Sai Kung 6.50. A contract was let and work started on a small reclamation adjacent to Sai Kung cinema for the construction of a latrine and bath- house building. Navigational Aids 6.51. As part of the overall plans for the continuing improvement of navigational aids in the Colony waters, light beacons were con- structed at Po Toi Island, Lo Chau and Junk Island. Refuse Disposal Incinerators 6.52. Planning work continued in connection with the second Kowloon incinerator to be sited adjacent to the first at Lai Chi Kok. The work is being carried out by Consulting Engineers and the Division is responsible for liaison work. 6.53. The Division completed the construction of a new reinforced- concrete ramp for loading barges at Kennedy Town and a pumphouse, refuse collection pier and turbo-alternator house at Lai Chi Kok. Kwai Chung Container Terminal 6.54. The engineering report on the proposed container terminal to be sited at Kwai Chung was completed and published. This report 65
2026-05-12 01:44:16 · Baseline
View content

Cheung Chau Praya Extension

6.47. A contract was let and work proceeded on the construction of a 250-foot extension northwards of the existing Cheung Chau Praya.

Shek Pik Pier

6.48. A contract was let and work started on the construction of a reinforced-concrete pier at Shek Pik. This pier will serve the Tong Fuk Prison, Shek Pik Training Centre and fishing craft in the southern Lantau area.

Tsing Yi Public Pier

6.49. A reinforced-concrete waiting shelter for ferry passengers was constructed adjacent to the public pier.

Sai Kung

6.50. A contract was let and work started on a small reclamation adjacent to Sai Kung cinema for the construction of a latrine and bath- house building.

Navigational Aids

6.51. As part of the overall plans for the continuing improvement of navigational aids in the Colony waters, light beacons were con- structed at Po Toi Island, Lo Chau and Junk Island.

Refuse Disposal Incinerators

6.52. Planning work continued in connection with the second Kowloon incinerator to be sited adjacent to the first at Lai Chi Kok. The work is being carried out by Consulting Engineers and the Division is responsible for liaison work.

6.53. The Division completed the construction of a new reinforced- concrete ramp for loading barges at Kennedy Town and a pumphouse, refuse collection pier and turbo-alternator house at Lai Chi Kok.

Kwai Chung Container Terminal

6.54. The engineering report on the proposed container terminal to be sited at Kwai Chung was completed and published. This report

65

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.