Project Estimated Cost Development Works $ Resiting the Railway Terminus, Preliminary Works 1,950,000 Kowloon Bay Development Drainage Works-Stage I 5,260,000 Aircraft Long-Term Parking Areas, Kai Tak Airport 3,200,000 Extension of Aircraft Parking Aprons and Taxiways, Kai Tak Airport-Stage I 11,400,000 Maintenance Apron and Associated Drainage Works, Kai Tak Airport 2,565,000 Taxiway Modifications, Kai Tak Airport ... Runway Grooving Trials, Hong Kong Airport ... Kai Tak Runway Extension, Further Investigation 1,200,000 Drainage Works 240,000 Construction of Yen Chow Street Submarine Outfall ... Construction of Main Culvert in Kwai Chung West Wan Chai Sewerage District Development-Construction of Submarine Outfall (West) 500,000 ... 550,000 ... 1,838,000 ... 1,706,000 Remedial Works to Landslide Area in Ma Shan Village and Associated Roads and Drainage Works 897,000 Remedial Works in Tsin Shui Ma Tau Village ... ... 117,000 Stormwater Drain Diversion, Central Reclamation 980,000 Shau Kei Wan Sewerage District Development--Shau Kei Wan Road Sewer ... ... ... ... 514,000 Staunton Creek Nullah Fronting Aberdeen Sports Ground, Stage III, Part I ... ... 1,000,000 Construction of Lai Chi Kok Submarine outfall 1,874,000 Removal and Disposal of Sewage Sludge and Screenings in Kowloon 894,000 ... 156

Edit History

2026-05-12 02:01:38 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
APPENDIX P—Contd. Project Estimated Cost Development Works $ Resiting the Railway Terminus, Preliminary Works 1,950,000 Kowloon Bay Development Drainage Works-Stage I 5,260,000 Aircraft Long-Term Parking Areas, Kai Tak Airport 3,200,000 Extension of Aircraft Parking Aprons and Taxiways, Kai Tak Airport-Stage I 11,400,000 Maintenance Apron and Associated Drainage Works, Kai Tak Airport 2,565,000 Taxiway Modifications, Kai Tak Airport ... Runway Grooving Trials, Hong Kong Airport ... Kai Tak Runway Extension, Further Investigation 1,200,000 Drainage Works 240,000 Construction of Yen Chow Street Submarine Outfall ... Construction of Main Culvert in Kwai Chung West Wan Chai Sewerage District Development-Construction of Submarine Outfall (West) 500,000 ... 550,000 ... 1,838,000 ... 1,706,000 Remedial Works to Landslide Area in Ma Shan Village and Associated Roads and Drainage Works 897,000 Remedial Works in Tsin Shui Ma Tau Village ... ... 117,000 Stormwater Drain Diversion, Central Reclamation 980,000 Shau Kei Wan Sewerage District Development--Shau Kei Wan Road Sewer ... ... ... ... 514,000 Staunton Creek Nullah Fronting Aberdeen Sports Ground, Stage III, Part I ... ... 1,000,000 Construction of Lai Chi Kok Submarine outfall 1,874,000 Removal and Disposal of Sewage Sludge and Screenings in Kowloon 894,000 ... 156
Baseline (Original)
APPENDIX P—Contd. Project Estimated Cost$ Development Works Resiting the Railway Terminus, Preliminary Works 1,950,000 Kowloon Bay Development Drainage Works-Stage I Aircraft Long-Term Parking Areas, Kai Tak Airport...5,260,000... 3,200,000 Extension of Aircraft Parking Aprons and Taxiways, Kai Tak Airport-Stage I 11,400,000...... Maintenance Apron and Associated Drainage Works, Kai Tak Airport 2,565,000 Taxiway Modifications, Kai Tak Airport Runway Grooving Trials, Hong Kong Airport Kai Tak Runway Extension, Further Investigation Drainage Works Construction of Yen Chow Street Submarine Outfall Construction of Main Culvert in Kwai Chung West Wan Chai Sewerage District Development-Construction of Sub-marine Outfall (West).....1,200,000240,000...... 500,000 550,000 1,838,000 1,706,000 Remedial Works to Landslide Area in Ma Shan Village and Asso-ciated Roads and Drainage Works... 897,000 Remedial Works in Tsin Shui Ma Tau Village ... ... 117,000 Stormwater Drain Diversion, Central Reclamation 980,000 Shau Kei Wan Sewerage District Development--Shau Kei Wan Road Sewer ... ... ... 514,000 Staunton Creek Nullah Fronting Aberdeen Sports Ground, Stage III, Part I ... 1,000,000 Construction of Lai Chi Kok Submarine outfall 1,874,000 Removal and Disposal of Sewage Sludge and Screenings in Kowloon 894,000 156
2026-05-12 02:01:38 · Baseline
View content

APPENDIX P—Contd.

Project

Estimated Cost

$

Development Works

Resiting the Railway Terminus, Preliminary Works

1,950,000

Kowloon Bay Development Drainage Works-Stage I Aircraft Long-Term Parking Areas, Kai Tak Airport

...

5,260,000

...

3,200,000

Extension of Aircraft Parking Aprons and Taxiways, Kai Tak

Airport-Stage I

11,400,000

...

...

Maintenance Apron and Associated Drainage Works, Kai Tak

Airport

2,565,000

Taxiway Modifications, Kai Tak Airport

Runway Grooving Trials, Hong Kong Airport

Kai Tak Runway Extension, Further Investigation

Drainage Works

Construction of Yen Chow Street Submarine Outfall

Construction of Main Culvert in Kwai Chung West Wan Chai Sewerage District Development-Construction of Sub-

marine Outfall (West)..

...

1,200,000

240,000

...

...

500,000

550,000

1,838,000

1,706,000

Remedial Works to Landslide Area in Ma Shan Village and Asso-

ciated Roads and Drainage Works

...

897,000

Remedial Works in Tsin Shui Ma Tau Village

...

...

117,000

Stormwater Drain Diversion, Central Reclamation

980,000

Shau Kei Wan Sewerage District Development--Shau Kei Wan Road

Sewer

...

...

...

514,000

Staunton Creek Nullah Fronting Aberdeen Sports Ground, Stage

III, Part I

...

1,000,000

Construction of Lai Chi Kok Submarine outfall

1,874,000

Removal and Disposal of Sewage Sludge and Screenings in Kowloon

894,000