10.04. A new unit responsible for advising on the preparation of contracts and the vetting of claims from contractors was set up during the year and an examination, in conjunction with consulting engineers, of the safety of all impounding and service reservoirs with capacities of more than ten million gallons was initiated.

10.05. The office is represented on various committees including:

Committee Representative(s) Water Resources Development Committee Director of Water Supplies and a Government Water Engineer Plover Cove Progress Committee Director of Water Supplies and a Government Water Engineer Building Contractors' Association/P.W.D. Joint Meeting Director of Water Supplies Resettlement Programme Committee Chief Engineer (Distribution) A Senior Engineer Castle Peak and Sha Tin New Town Works Committee A Senior Engineer Castle Peak and Sha Tin New Town Management Committee

10.06. Details of rainfall, storage, consumption and other general statistics are given in Appendix CC.

General

DISTRIBUTION DIVISION

Chief Engineer:

J. S. DON, B.Sc. (Hons.), C.Eng., M.I.C.E.

J. C. PAYNE, B.Sc. (Eng.), C.Eng., M.I.C.E., A.M.I.W.E. (Acting)

10.07. The Division maintains and operates the various installations connected with the day-to-day supply of water.

Supply Section

10.08. At the end of the year 30,012 million gallons of water was held in storage including 23,879 million gallons in the Plover Cove Reservoir. Storage at the same time last year was 33,016 million gallons of which 25,393 million gallons was stored at Plover Cove. Yields from catchment areas were only 80% of last year's yield due to low rainfall in the last seven months of the year. Under the Agreement with the People's Council of Kwantung Province, 15,016 million gallons of water was received from China during the year. Heavy rainfall in July and

116

Edit History

2026-05-12 01:52:18 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
10.04. A new unit responsible for advising on the preparation of contracts and the vetting of claims from contractors was set up during the year and an examination, in conjunction with consulting engineers, of the safety of all impounding and service reservoirs with capacities of more than ten million gallons was initiated. 10.05. The office is represented on various committees including: Committee Representative(s) Water Resources Development Committee Director of Water Supplies and a Government Water Engineer Plover Cove Progress Committee Director of Water Supplies and a Government Water Engineer Building Contractors' Association/P.W.D. Joint Meeting Director of Water Supplies Resettlement Programme Committee Chief Engineer (Distribution) A Senior Engineer Castle Peak and Sha Tin New Town Works Committee A Senior Engineer Castle Peak and Sha Tin New Town Management Committee 10.06. Details of rainfall, storage, consumption and other general statistics are given in Appendix CC. General DISTRIBUTION DIVISION Chief Engineer: J. S. DON, B.Sc. (Hons.), C.Eng., M.I.C.E. J. C. PAYNE, B.Sc. (Eng.), C.Eng., M.I.C.E., A.M.I.W.E. (Acting) 10.07. The Division maintains and operates the various installations connected with the day-to-day supply of water. Supply Section 10.08. At the end of the year 30,012 million gallons of water was held in storage including 23,879 million gallons in the Plover Cove Reservoir. Storage at the same time last year was 33,016 million gallons of which 25,393 million gallons was stored at Plover Cove. Yields from catchment areas were only 80% of last year's yield due to low rainfall in the last seven months of the year. Under the Agreement with the People's Council of Kwantung Province, 15,016 million gallons of water was received from China during the year. Heavy rainfall in July and 116
Baseline (Original)
10.04. A new unit responsible for advising on the preparation of contracts and the vetting of claims from contractors was set up during the year and an examination, in conjunction with consulting engineers, of the safety of all impounding and service reservoirs with capacities of more than ten million gallons was initiated. 10.05. The office is represented on various committees including: Committee Water Resources Development Committee Plover Cove Progress Committee Building Contractors' Association/ P.W.D. Joint Meeting Resettlement Programme Committee Castle Peak and Sha Tin New Town Works Committee Castle Peak and Sha Tin New Town Management Committee Representative(s) Director of Water Supplies and a Government Water Engineer Director of Water Supplies and a Government Water Engineer Director of Water Supplies Chief Engineer (Distribution) A Senior Engineer A Senior Engineer 10.06. Details of rainfall, storage, consumption and other general statistics are given in Appendix CC. General DISTRIBUTION DIVISION Chief Engineer: J. S. DON, B.Sc. (Hons.), C.Eng., M.I.C.E. J. C. PAYNE, B.Sc. (Eng.), C.Eng., M.I.C.E., A.M.I.W.E. (Acting) 10.07. The Division maintains and operates the various installations connected with the day-to-day supply of water. Supply Section 10.08. At the end of the year 30,012 million gallons of water was held in storage including 23,879 million gallons in the Plover Cove Reservoir. Storage at the same time last year was 33,016 million gallons of which 25,393 million gallons was stored at Plover Cove. Yields from catchment areas were only 80% of last year's yield due to low rainfall in the last seven months of the year. Under the Agreement with the People's Council of Kwantung Province, 15,016 million gallons of water was received from China during the year. Heavy rainfall in July and 116
2026-05-12 01:52:18 · Baseline
View content

10.04. A new unit responsible for advising on the preparation of contracts and the vetting of claims from contractors was set up during the year and an examination, in conjunction with consulting engineers, of the safety of all impounding and service reservoirs with capacities of more than ten million gallons was initiated.

10.05. The office is represented on various committees including:

Committee

Water Resources Development

Committee

Plover Cove Progress Committee

Building Contractors' Association/

P.W.D. Joint Meeting

Resettlement Programme Committee

Castle Peak and Sha Tin New

Town Works Committee

Castle Peak and Sha Tin New

Town Management Committee

Representative(s)

Director of Water Supplies and a Government Water Engineer

Director of Water Supplies and a Government Water Engineer Director of Water Supplies

Chief Engineer (Distribution) A Senior Engineer

A Senior Engineer

10.06. Details of rainfall, storage, consumption and other general statistics are given in Appendix CC.

General

DISTRIBUTION DIVISION

Chief Engineer:

J. S. DON, B.Sc. (Hons.), C.Eng., M.I.C.E.

J. C. PAYNE, B.Sc. (Eng.), C.Eng., M.I.C.E., A.M.I.W.E. (Acting)

10.07. The Division maintains and operates the various installations connected with the day-to-day supply of water.

Supply Section

10.08. At the end of the year 30,012 million gallons of water was held in storage including 23,879 million gallons in the Plover Cove Reservoir. Storage at the same time last year was 33,016 million gallons of which 25,393 million gallons was stored at Plover Cove. Yields from catchment areas were only 80% of last year's yield due to low rainfall in the last seven months of the year. Under the Agreement with the People's Council of Kwantung Province, 15,016 million gallons of water was received from China during the year. Heavy rainfall in July and