APPENDIX O-Contd.
(1) Hong Kong (Contd.)
Project Approximate Cost $ Factory Street Nullah Culverting and Road Reconstruction 248,000 Construction of Trunk Sewers in Yee Wo Street, Tung Lo Wan Road and Jardine's Bazaar 317,000 Construction of Trunk Sewer in Percival Street/Leighton Road 147,000 Construction of Roads and Drainage, Wong Chuk Hang Low Cost Housing, Stage I 450,000 Bowrington Canal Extension 2,800,000 Construction of Trunk Sewer in Tai Hang Road 274,000(ii) Kowloon:
Project Approximate Cost $ Ngau Tau Kok Bus Terminus 146,000 Tai Po Road Widening between Lung Cheung Road and Castle Peak Road Junction, Stage I (North Kowloon Magistracy to Castle Peak Road) 890,000 Canton Road Widening (from Peking Road to Ocean Terminal Entrance) 152,000 Construction of Lai Chi Kok Trunk Sewer (from east side of Water Boat Dock to junction of future roads opposite N.K.I.L. 5087) 360,000 Reconstruction of Heng Lam Street (Junction Road to Fung Mo Street) 115,000 Reconstruction of Mong Kok Road (Tong Mi Road to Reclamation Street) 211,000 Reconstruction of Mong Kok Road (Nathan Road to Tung Choi Street) and Knight Street 200,000 Reconstruction of Kai Tak Road and Ta Ku Ling Road (Nga Tsin Wai Road to Carpenter Road) 172,000 Reconstruction of Woh Chai Street (Nam Cheong Street South-east through Resettlement Estate) and Sai Yeung Choi Street (Boundary Street Northward to N.K.I.L. 4843) 240,000 Stormwater Drainage Improvements near Hok Lo Village, Kai Tak 143,000 Reconstruction of Mong Kok Road (Tung Choi Street to Sai Yee Street) 140,000 Extension of Aircraft Parking Apron, Kai Tak 3,540,000 Tsz Wan Shan Bus Terminus (South) 164,000 Tsz Wan Shan Bus Terminus (North) 185,000 Decking of Hing Wah Street Nullah (Po On Road to Fuk Wing Street) 154,000 Reconstruction of Waterloo Road (Boundary Street to approach ramp of Flyover at Nairn House Intersection) 437,000 133APPENDIX O-Contd.
(1) Hong Kong (Contd.)
Project
Factory Street Nullah Culverting and Road Reconstruction Construction of Trunk Sewers in Yee Wo Street, Tung Lo Wan
Road and Jardine's Bazaar
Approximate Cost
$
248,000
317,000
Construction of Trunk Sewer in Percival Street/Leighton Road... Construction of Roads and Drainage, Wong Chuk Hang Low
Cost Housing, Stage I
147,000
450,000
Bowrington Canal Extension
2,800,000
•
**
Construction of Trunk Sewer in Tai Hang Road
274,000
(ii) Kowloon:
Ngau Tau Kok Bus Terminus
146,000
Tai Po Road Widening between Lung Cheung Road and Castle Peak Road Junction, Stage I (North Kowloon Magistracy to Castle Peak Road)
890,000
Canton Road Widening (from Peking Road to Ocean Terminal
Entrance)
152,000
་་་
Construction of Lai Chi Kok Trunk Sewer (from east side of Water Boat Dock to junction of future roads opposite N.K.I.L. 5087)
360,000
***
Reconstruction of Heng Lam Street (Junction Road to Fung
Mo Street)
115,000
Reconstruction of Mong Kok Road (Tong Mi Road to
Reclamation Street)
211,000
Reconstruction of Mong Kok Road (Nathan Road to Tung
Choi Street) and Knight Street
200,000
•
..✰
Reconstruction of Kai Tak Road and Ta Ku Ling Road (Nga
Tsin Wai Road to Carpenter Road) Reconstruction of Woh Chai Street (Nam Cheong Street South-east through Resettlement Estate) and Sai Yeung Choi Street (Boundary Street Northward to N.K.I.L. 4843)... Stormwater Drainage Improvements near Hok Lo Village, Kai
Tak
172,000
240,000
143,000
Reconstruction of Mong Kok Road (Tung Choi Street to Sai
Yee Street)
140,000
Extension of Aircraft Parking Apron, Kai Tak Tsz Wan Shan Bus Terminus (South)
3,540,000
164,000
***
Tsz Wan Shan Bus Terminus (North)
185,000
Decking of Hing Wah Street Nullah (Po On Road to Fuk Wing
Street)
154,000
Reconstruction of Waterloo Road (Boundary Street to approach
ramp of Flyover at Nairn House Intersection)
437,000
133