Project

Estimated Cost

$

(b) Port Works (Contd.)

Incineration and Composting Plant, Kowloon 28,600,000 Cheung Sha Wan Reclamation, Stage II 2,700,000 Cha Kwo Ling Seawall, Stage II 4,000,000 Tai Wan Seawall, Stage I 700,000 Yau Ma Tei Slipway Reprovisioning, Stage I (Pier and Slipway) 6,773,000 Kowloon Bay Seawall, Part II 2,000,000 Tai Wan Seawall, Stage II 800,000 Roof over Kwun Tong Public Pier 150,000 Shuen Wan Typhoon Shelter 5,500,000 Minor Ferry Service Piers at Yau Kom Tau on the Mainland and Tsing Yi Island 385,000 Demolition of Ngai Kap Pai Reef 30,000 Winch Hauled Trolley and Track, Waglan Island 110,000 Light Beacons at Pak Kok, Luk Keng and Kau Yi Chau 75,000 Removal of Silvermine Bay Rock 30,000 Beacon at Tai O Creek Breakwater 75,000 Light Beacons at Lau Fau Shan, Siu A Chau and Northwest Tsing Yi Island 120,000 H.M.S. Tamar Seawall 220,000 Cattle Pier at Cheung Sha Wan 800,000 Waterfront Road at Victoria Park (Seawall) 3,200,000 Seawall Foundation at Wan Chai Reclamation Stage II, Section 5-6 900,000 Seawall at Wan Chai Reclamation Stage II, Section (N)—(6A) 1,700,000 Pumphouse at Yau Ma Tei Typhoon Shelter 700,000 Site Formation and Seawall for Sewage Works at Pillar Island, Kwai Chung 800,000 Site Formation at Aberdeen Resettlement 2,040,300

(c) Development Works

Stormwater Culvert Extension at Cheung Sha Wan Reclamation 3,350,000 Construction of Railway Workshops and Ancillary Works 12,300,000 Resiting the Railway Terminus, Preliminary Works 2,000,000

133

Edit History

2026-05-12 00:55:55 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Estimated Cost$(b) Port Works (Contd.) Incineration and Composting Plant, Kowloon 28,600,000 Cheung Sha Wan Reclamation, Stage II 2,700,000 Cha Kwo Ling Seawall, Stage II 4,000,000 Tai Wan Seawall, Stage I 700,000 Yau Ma Tei Slipway Reprovisioning, Stage I (Pier and Slipway) 6,773,000 Kowloon Bay Seawall, Part II 2,000,000 Tai Wan Seawall, Stage II 800,000 Roof over Kwun Tong Public Pier 150,000 Shuen Wan Typhoon Shelter 5,500,000 Minor Ferry Service Piers at Yau Kom Tau on the Mainland and Tsing Yi Island 385,000 Demolition of Ngai Kap Pai Reef 30,000 Winch Hauled Trolley and Track, Waglan Island 110,000 Light Beacons at Pak Kok, Luk Keng and Kau Yi Chau 75,000 Removal of Silvermine Bay Rock 30,000 Beacon at Tai O Creek Breakwater 75,000 Light Beacons at Lau Fau Shan, Siu A Chau and Northwest Tsing Yi Island 120,000 H.M.S. Tamar Seawall 220,000 Cattle Pier at Cheung Sha Wan 800,000 Waterfront Road at Victoria Park (Seawall) 3,200,000 Seawall Foundation at Wan Chai Reclamation Stage II, Section 5-6 900,000 Seawall at Wan Chai Reclamation Stage II, Section (N)—(6A) 1,700,000 Pumphouse at Yau Ma Tei Typhoon Shelter 700,000 Site Formation and Seawall for Sewage Works at Pillar Island, Kwai Chung 800,000 Site Formation at Aberdeen Resettlement 2,040,300(c) Development Works Stormwater Culvert Extension at Cheung Sha Wan Reclamation 3,350,000 Construction of Railway Workshops and Ancillary Works 12,300,000 Resiting the Railway Terminus, Preliminary Works 2,000,000133
Baseline (Original)
Estimated Cost$(b) Port Works (Contd.) Incineration and Composting Plant, Kowloon 28,600,000 Cheung Sha Wan Reclamation, Stage II... 2,700,000 Cha Kwo Ling Seawall, Stage II 4,000,000 Tai Wan Seawall, Stage I 700,000 Yau Ma Tei Slipway Reprovisioning, Stage I (Pier and Slipway) 6,773,000 Kowloon Bay Seawall, Part II 2,000,000 Tai Wan Seawall, Stage II... 800,000 Roof over Kwun Tong Public Pier 150,000 Shuen Wan Typhoon Shelter 5,500,000 Minor Ferry Service Piers at Yau Kom Tau on the Mainland and Tsing Yi Island... 385,000 Demolition of Ngai Kap Pai Reef 30,000 Winch Hauled Trolley and Track, Waglan Island 110,000 Light Beacons at Pak Kok, Luk Keng and Kau Yi Chau+ 75,000 Removal of Silvermine Bay Rock 30,000 Beacon at Tai O Creek Breakwater 75,00024 Light Beacons at Lau Fau Shan, Siu A Chau and Northwest Tsing Yi Island 120,000 H.M.S. Tamar Seawall 220,000 Cattle Pier at Cheung Sha Wan 800,000 Waterfront Road at Victoria Park (Seawall) 3,200,000 Seawall Foundation at Wan Chai Reclamation Stage II, Section 5-6 900,000 Seawall at Wan Chai Reclamation Stage II, Section (N)—(6A) 1,700,000 Pumphouse at Yau Ma Tei Typhoon Shelter 700,000** Site Formation and Seawall for Sewage Works at Pillar Island, Kwai Chung 800,000 Site Formation at Aberdeen Resettlement+ 2,040,300(c) Development Works Stormwater Culvert Extension at Cheung Sha Wan Reclamation 3,350,000 Construction of Railway Workshops and Ancillary Works 12,300,000 Resiting the Railway Terminus, Preliminary Works 2,000,000133
2026-05-12 00:55:55 · Baseline
View content

APPENDIX P-Contd.

Project

Estimated Cost

$

(b) Port Works (Contd.)

Incineration and Composting Plant, Kowloon

28,600,000

Cheung Sha Wan Reclamation, Stage II ...

2,700,000

Cha Kwo Ling Seawall, Stage II

4,000,000

Tai Wan Seawall, Stage I

700,000

Yau Ma Tei Slipway Reprovisioning, Stage I (Pier and Slipway)

6,773,000

Kowloon Bay Seawall, Part II

2,000,000

Tai Wan Seawall, Stage II ...

800,000

Roof over Kwun Tong Public Pier

150,000

Shuen Wan Typhoon Shelter

5,500,000

Minor Ferry Service Piers at Yau Kom Tau on the Mainland

and Tsing Yi Island

...

385,000

Demolition of Ngai Kap Pai Reef

30,000

Winch Hauled Trolley and Track, Waglan Island

110,000

Light Beacons at Pak Kok, Luk Keng and Kau Yi Chau

+

75,000

Removal of Silvermine Bay Rock

30,000

Beacon at Tai O Creek Breakwater

75,000

24

Light Beacons at Lau Fau Shan, Siu A Chau and Northwest

Tsing Yi Island

120,000

H.M.S. Tamar Seawall

220,000

Cattle Pier at Cheung Sha Wan

800,000

Waterfront Road at Victoria Park (Seawall)

3,200,000

Seawall Foundation at Wan Chai Reclamation Stage II,

Section 5-6

900,000

Seawall at Wan Chai Reclamation Stage II, Section (N)—(6A)

1,700,000

Pumphouse at Yau Ma Tei Typhoon Shelter

700,000

**

Site Formation and Seawall for Sewage Works at Pillar Island,

Kwai Chung

800,000

Site Formation at Aberdeen Resettlement

+

2,040,300

(c) Development Works

Stormwater Culvert Extension at Cheung Sha Wan Reclamation

3,350,000

Construction of Railway Workshops and Ancillary Works

12,300,000

Resiting the Railway Terminus, Preliminary Works