1967-1968 — Page 110

Public Works Department Annual Report 工務司署年報 All AI Reviewed

WATERWORKS OFFICE

Director of Water Supplies:

E. P. WILMOT-MORGAN, O.B.E., J.P., B.Sc., M.I.C.E., M.I.W.E.

A. S. ROBERTSON, B.Sc. (Hons.), A.M.I.C.E., A.M.I.Struct.E., A.M.I.W.E. (Acting) Government Water Engineer:

A. S. ROBERTSON, B.Sc. (Hons.), A.M.I.C.E., A.M.I.Struct.E., A.M.I.W.E.

W. T. KNIGHT, A.M.I.C.E., A.M.I.Mun.E., M.Inst.Q. (Acting)

Assistant Government Water Engineers:

W. T. KNIGHT, A.M.I.C.E., A.M.I.Mun.E., M.Inst.Q.

J. M. PETTIGREW, A.M.I.Mech.E.

W. D. A. TUCKER, M.A. (Eng.), A.M.I.C.E. (Acting)

GENERAL

8.01. 1967 was another crisis year for the Waterworks office. A deteriorating supply situation which developed out of very low rainfall after August 1966, allied with failure to negotiate additional supplies from China for July, August and September 1967, finally led to the introduction of a four-hour supply every fourth day in mid-July. Fortunately, these extreme measures were only necessary for a comparatively short time and were relaxed on 22nd August following heavy rain.

8.02. The sub-department was seriously affected by a large-scale walkout of labour on 8th June. This was connected with the disturbances which affected the whole Colony, and a considerable number of workmen, some 256 out of a labour force of approximately 1,700, were dismissed from their posts. Re-adjustment of the staff remaining on duty permitted supply to be maintained effectively, although activities in some less essential spheres were necessarily curtailed. By the end of the year, normality had been regained in most sections, and good progress had been made on the backlog of maintenance works.

8.03. Progress on several major works was delayed by problems associated with contractors' financial difficulties and the strict control placed on the supply of explosives, but these problems had been largely resolved by the end of the year.

8.04. The Waterworks Office is represented on various working parties and committees, including:

Committee Representative(s) Water Resources Policy Committee Director of Water Supplies & Government Water Engineer Plover Cove Progress Committee Director of Water Supplies

86

No need to change "Pal" and "Pa 111" as they seem to be unrelated to the main text and might be page metadata or unrelated OCR fragments. However, without more context, it's hard to determine their significance. If they are part of the original scan and not relevant to the content, they can be left as is or removed based on further instructions. For now, they are left out as they don't seem directly connected to the main content. The final output is in HTML format as requested.

Edit History

2026-05-12 00:45:52 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
WATERWORKS OFFICE Director of Water Supplies: E. P. WILMOT-MORGAN, O.B.E., J.P., B.Sc., M.I.C.E., M.I.W.E. A. S. ROBERTSON, B.Sc. (Hons.), A.M.I.C.E., A.M.I.Struct.E., A.M.I.W.E. (Acting) Government Water Engineer: A. S. ROBERTSON, B.Sc. (Hons.), A.M.I.C.E., A.M.I.Struct.E., A.M.I.W.E. W. T. KNIGHT, A.M.I.C.E., A.M.I.Mun.E., M.Inst.Q. (Acting) Assistant Government Water Engineers: W. T. KNIGHT, A.M.I.C.E., A.M.I.Mun.E., M.Inst.Q. J. M. PETTIGREW, A.M.I.Mech.E. W. D. A. TUCKER, M.A. (Eng.), A.M.I.C.E. (Acting) GENERAL 8.01. 1967 was another crisis year for the Waterworks office. A deteriorating supply situation which developed out of very low rainfall after August 1966, allied with failure to negotiate additional supplies from China for July, August and September 1967, finally led to the introduction of a four-hour supply every fourth day in mid-July. Fortunately, these extreme measures were only necessary for a comparatively short time and were relaxed on 22nd August following heavy rain. 8.02. The sub-department was seriously affected by a large-scale walkout of labour on 8th June. This was connected with the disturbances which affected the whole Colony, and a considerable number of workmen, some 256 out of a labour force of approximately 1,700, were dismissed from their posts. Re-adjustment of the staff remaining on duty permitted supply to be maintained effectively, although activities in some less essential spheres were necessarily curtailed. By the end of the year, normality had been regained in most sections, and good progress had been made on the backlog of maintenance works. 8.03. Progress on several major works was delayed by problems associated with contractors' financial difficulties and the strict control placed on the supply of explosives, but these problems had been largely resolved by the end of the year. 8.04. The Waterworks Office is represented on various working parties and committees, including: Committee Representative(s) Water Resources Policy Committee Director of Water Supplies & Government Water Engineer Plover Cove Progress Committee Director of Water Supplies 86 No need to change "Pal" and "Pa 111" as they seem to be unrelated to the main text and might be page metadata or unrelated OCR fragments. However, without more context, it's hard to determine their significance. If they are part of the original scan and not relevant to the content, they can be left as is or removed based on further instructions. For now, they are left out as they don't seem directly connected to the main content. The final output is in HTML format as requested.
Baseline (Original)
WATERWORKS OFFICE Director of Water Supplies: E. P. WILMOT-MORGAN, O.B.E., J.P., B.Sc., M.I.C.E., M.I.W.E. A. S. ROBERTSON, B.Sc. (Hons.), A.M.I.C.E., A.M.I.Struct.E., A.M.I.W.E. (Acting) Government Water Engineer: A. S. ROBERTSON, B.Sc. (Hons.), A.M.I.C.E., A.M.I.Struct.E., A.M.I.W.E. W. T. KNIGHT, A.M.I.C.E., A.M.I.Mun.E., M.Inst.Q. (Acting) Assistant Government Water Engineers: W. T. KNIGHT, A.M.I.C.E., A.M.I.Mun.E., M.Inst.Q. J. M. PETTIGREW, A.M.I.Mech.E. W. D. A. TUCKER, M.A. (Eng.), A.M.I.C.E. (Acting) GENERAL 8.01. 1967 was another crisis year for the Waterworks office. A deteriorating supply situation which developed out of very low rainfall after August 1966, allied with failure to negotiate additional supplies from China for July, August and September 1967, finally led to the introduction of a four hour supply every fourth day in mid-July. Fortunately these extreme measures were only necessary for a compara- tively short time and were relaxed on 22nd August following heavy rain. 8.02. The sub-department was seriously affected by a large scale walkout of labour on 8th June. This was connected with the disturbances which affected the whole Colony and a considerable number of workmen, some 256 out of a labour force of approximately 1,700, were dismissed from their posts. Re-adjustment of the staff remaining on duty permitted supply to be maintained effectively, although activities in some less essential spheres were necessarily curtailed. By the end of the year normality had been regained in most sections and good progress had been made on the backlog of maintenance works. 8.03. Progress on several major works was delayed by problems associated with contractors' financial difficulties and the strict control placed on the supply of explosives but these problems had been largely resolved by the end of the year. 8.04. The Waterworks Office is represented on various working parties and committees including: Committee Water Resources Policy Committee Plover Cove Progress Committee 86 Representative(s) Director of Water Supplies & Government Water Engineer Director of Water Supplies Pal Pa 111
2026-05-12 00:45:52 · Baseline
View content

WATERWORKS OFFICE

Director of Water Supplies:

E. P. WILMOT-MORGAN, O.B.E., J.P., B.Sc., M.I.C.E., M.I.W.E.

A. S. ROBERTSON, B.Sc. (Hons.), A.M.I.C.E., A.M.I.Struct.E., A.M.I.W.E. (Acting) Government Water Engineer:

A. S. ROBERTSON, B.Sc. (Hons.), A.M.I.C.E., A.M.I.Struct.E., A.M.I.W.E. W. T. KNIGHT, A.M.I.C.E., A.M.I.Mun.E., M.Inst.Q. (Acting)

Assistant Government Water Engineers:

W. T. KNIGHT, A.M.I.C.E., A.M.I.Mun.E., M.Inst.Q. J. M. PETTIGREW, A.M.I.Mech.E.

W. D. A. TUCKER, M.A. (Eng.), A.M.I.C.E. (Acting)

GENERAL

8.01. 1967 was another crisis year for the Waterworks office. A deteriorating supply situation which developed out of very low rainfall after August 1966, allied with failure to negotiate additional supplies from China for July, August and September 1967, finally led to the introduction of a four hour supply every fourth day in mid-July. Fortunately these extreme measures were only necessary for a compara- tively short time and were relaxed on 22nd August following heavy rain.

8.02. The sub-department was seriously affected by a large scale walkout of labour on 8th June. This was connected with the disturbances which affected the whole Colony and a considerable number of workmen, some 256 out of a labour force of approximately 1,700, were dismissed from their posts. Re-adjustment of the staff remaining on duty permitted supply to be maintained effectively, although activities in some less essential spheres were necessarily curtailed. By the end of the year normality had been regained in most sections and good progress had been made on the backlog of maintenance works.

8.03. Progress on several major works was delayed by problems associated with contractors' financial difficulties and the strict control placed on the supply of explosives but these problems had been largely resolved by the end of the year.

8.04. The Waterworks Office is represented on various working parties and committees including:

Committee

Water Resources Policy Committee

Plover Cove Progress Committee

86

Representative(s)

Director of Water Supplies &

Government Water Engineer Director of Water Supplies

Pal

Pa 111

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.