Yau Ma Tei Slipway Reprovisioning
4.27. Work continued in the former Kowloon Naval Camber on Stage I of this scheme, which includes the construction of three slipways and a pier. These will replace the existing Marine Department facilities in Yau Ma Tei typhoon shelter.
Cha Kwo Ling Reclamation
4.28. The contract for the seawall fronting the Cha Kwo Ling reclamation was completed. When this reclamation of 10 acres is finished it will provide land for the waterfront road giving easier access to the Yau Tong Bay shipyards and the proposed industrial development at Sam Ka Tsuen.
Sam Ka Tsuen Reclamation and Breakwater
4.29. The reclamation, seawall and breakwater have been completed. The 16 acres of reclaimed land are planned for industrial use. The breakwater has provided a much needed sheltered anchorage for small craft based in this area.
Waglan Pier
4.30. The construction of a new pier at Waglan Island was completed. This pier facilitates the supply and relief of the crews who operate the marine and air navigation station situated on the island.
Kau Lau Wan and Wong Shek Piers
4.31. Work was completed on the construction of these two prestressed concrete piers thus providing the local farming and fishing communities with a much easier access to the markets for their produce.
Shuen Wan Typhoon Shelter
4.32. Tenders were called for completion of the breakwater arm, the core of which had already been formed using rock excavated from the Plover Cove Scheme tunnels. When completed the breakwater will provide 27 acres of typhoon shelter for local craft.
Refuse Disposal Incinerator
4.33. Progress on the plant installation is described in para. 6.18(i) of the Electrical and Mechanical Office section. The design of the civil engineering and building works was carried out by a firm of consultants while the contract management of the civil works was the responsibility of this Division. At Kennedy Town the building and civil engineering works were completed and at Lai Chi Kok they were substantially completed.
41
Yau Ma Tei Slipway Reprovisioning
4.27. Work continued in the former Kowloon Naval Camber on Stage I of this scheme, which includes the construction of three slipways and a pier. These will replace the existing Marine Department facilities in Yau Ma Tei typhoon shelter.
Cha Kwo Ling Reclamation
4.28. The contract for the seawall fronting the Cha Kwo Ling rec- lamation was completed. When this reclamation of 10 acres is finished it will provide land for the waterfront road giving easier access to the Yau Tong Bay shipyards and the proposed industrial development at Sam Ka Tsuen.
Sam Ka Tsuen Reclamation and Breakwater
4.29. The reclamation, seawall and breakwater have been completed. The 16 acres of reclaimed land are planned for industrial use. The break water has provided a much needed sheltered anchorage for small craft based in this area.
Waglan Pier
4.30. The construction of a new pier at Waglan Island was com- pleted. This pier facilitates the supply and relief of the crews who operate the marine and air navigation station situated on the island.
Kau Lau Wan and Wong Shek Piers
4.31. Work was completed on the construction of these two prestress- ed concrete piers thus providing the local farming and fishing com- munities with a much easier access to the markets for their produce.
Shuen Wan Typhoon Shelter
4.32. Tenders were called for completion of the breakwater arm, the core of which had already been formed using rock excavated from the Plover Cove Scheme tunnels. When completed the breakwater will provide 27 acres of typhoon shelter for local craft.
Refuse Disposal Incinerator
4.33. Progress on the plant installation is described in para. 6.18(i) of the Electrical and Mechanical Office section. The design of the civil engineering and building works was carried out by a firm of consultants while the contract management of the civil works was the responsibility of this Division. At Kennedy Town the building and civil engineering works were completed and at Lai Chi Kok they were substantially com-