1965-1966 — Page 123

Public Works Department Annual Report 工務司署年報 All AI Reviewed

APPENDIX L

CIVIL ENGINEERING OFFICE

SUMMARY OF MAJOR LAND FORMATION WORKS

Location Área to be formed (acres) Estimated cost ($M.) Area Completed (acres) Expenditure ($M.) to 31.3.66 Kwun Tong 614.48 105.00 573.6 81.0 Kowloon Bay 530.38 94.20 139.80 2.00 Sam Ka Tsuen ... 40.00 22.00 5.01 Ho Man Tin 121.00 22.70 55.00 8.38 Lung Cheung Road Development Area No. 3 47.00 7.50 47.00 4.95 Lung Cheung Road Development Area No. 1 153.50 26.79 11.50 2.99 Kwai Chung North Development Area 9 Stage I ... 93.10 53.00 5.37 Kwai Chung Development Stage II ... 225.00 200.00 64.00 Ho Tung Lau, Sha Tin 20.90 5.50 ... 0.80 ... 98

Remarks

Kwun Tong Industrial Zone 5, Section E incorporated in Kowloon Bay Scheme.

Reclamation being formed by public dumping. Full scheme not yet approved.

Site formation and drainage work in hand; for industrial use.

Sites for residential and community use. Site formation works and road surfacing in progress.

Sites for residential and commercial use completed. Internal road works nearly completed.

Lung Cheung Road Development Area No. 1 - Sites for Government and community use.

Kwai Chung North Development Area 9 Stage I - Sites for resettlement, low-cost housing and private development.

Kwai Chung Development Stage II - ...

Ho Tung Lau, Sha Tin - Under Consultants. Sites for resettlement, low-cost and private housing and industrial development.

... - For railway workshops, etc.

Edit History

2026-05-11 23:45:45 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
APPENDIX L CIVIL ENGINEERING OFFICE SUMMARY OF MAJOR LAND FORMATION WORKS Location Área to be formed (acres) Estimated cost ($M.) Area Completed (acres) Expenditure ($M.) to 31.3.66 Kwun Tong 614.48 105.00 573.6 81.0 Kowloon Bay 530.38 94.20 139.80 2.00 Sam Ka Tsuen ... 40.00 22.00 5.01 Ho Man Tin 121.00 22.70 55.00 8.38 Lung Cheung Road Development Area No. 3 47.00 7.50 47.00 4.95 Lung Cheung Road Development Area No. 1 153.50 26.79 11.50 2.99 Kwai Chung North Development Area 9 Stage I ... 93.10 53.00 5.37 Kwai Chung Development Stage II ... 225.00 200.00 64.00 Ho Tung Lau, Sha Tin 20.90 5.50 ... 0.80 ... 98 Remarks Kwun Tong Industrial Zone 5, Section E incorporated in Kowloon Bay Scheme. Reclamation being formed by public dumping. Full scheme not yet approved. Site formation and drainage work in hand; for industrial use. Sites for residential and community use. Site formation works and road surfacing in progress. Sites for residential and commercial use completed. Internal road works nearly completed. Lung Cheung Road Development Area No. 1 - Sites for Government and community use. Kwai Chung North Development Area 9 Stage I - Sites for resettlement, low-cost housing and private development. Kwai Chung Development Stage II - ... Ho Tung Lau, Sha Tin - Under Consultants. Sites for resettlement, low-cost and private housing and industrial development. ... - For railway workshops, etc.
Baseline (Original)
APPENDIX L CIVIL ENGINEERING OFFICE SUMMARY OF MAJOR LAND FORMATION WORKS Location Área to Estimated be formed (acres) cost ($M.) Area Completed (acres) Expenditure ($M.) to 31.3.66 Kwun Tong 614.48 105.00 573.6 81.0 ... Kowloon Bay 530,38 94.20 139.80 2.00 Sam Ka Tsuen ... 40.00 12.60 22.00 5.01 Ho Man Tin 121.00 22.70 55.00 8.38 Lung Cheung Road Development Area No. 3 47.00 7.50 47.00 4.95 ... Remarks Kwun Tong Industrial Zone 5, Section E incor- porated in Kowloon Bay Scheme. Reclamation being formed by public dumping. Full scheme not yet approved. Site formation and drain- age work in hand; for industrial use. Sites for residential and community use. Site for- mation works and road surfacing in progress. Sites for residential and commercial use completed. Internal road works nearly completed. Lung Cheung Road Development Area No. 1 153.50 26.79 11.50 2.99 Sites for Government and community use. Kwai Chung North Development Area 9 Stage I ... 93.10 22.00 53.00 5.37 Sites for resettlement, low- cost housing and private development. Kwai Chung Development Stage II ... 225.00 64.00 200.00 60.00 Ho Tung Lau, Sha Tin 20.90 5.50 98 0.80 Under Consultants. Sites for resettlement, low-cost and private housing and industrial development. For railway workshops, etc.
2026-05-11 23:45:45 · Baseline
View content

APPENDIX L

CIVIL ENGINEERING OFFICE

SUMMARY OF MAJOR LAND FORMATION WORKS

Location

Área to Estimated be formed

(acres)

cost ($M.)

Area Completed (acres)

Expenditure ($M.) to 31.3.66

Kwun Tong

614.48

105.00

573.6

81.0

...

Kowloon Bay

530,38

94.20

139.80

2.00

Sam Ka Tsuen

...

40.00

12.60

22.00

5.01

Ho Man Tin

121.00

22.70 55.00

8.38

Lung Cheung Road

Development

Area No. 3

47.00

7.50

47.00

4.95

...

Remarks

Kwun Tong Industrial Zone 5, Section E incor- porated in Kowloon Bay Scheme.

Reclamation being formed by public dumping. Full scheme not yet approved.

Site formation and drain- age work in hand; for industrial use.

Sites for residential and community use. Site for- mation works and road surfacing in progress.

Sites for residential and commercial use completed. Internal road works nearly completed.

Lung Cheung Road

Development

Area No. 1

153.50 26.79

11.50

2.99

Sites for Government and community use.

Kwai Chung North

Development

Area 9 Stage I ... 93.10

22.00

53.00

5.37

Sites for resettlement, low- cost housing and private development.

Kwai Chung

Development

Stage II ...

225.00 64.00 200.00

60.00

Ho Tung Lau, Sha

Tin

20.90

5.50

98

0.80

Under Consultants. Sites for resettlement, low-cost and private housing and industrial development.

For railway workshops, etc.