dumping continued. Approximately 560,000 cubic yards of fill were placed.
Chai Wan Reclamation
4.32. A total of 680,000 cubic yards of spoil was placed at Chai Wan Reclamation forming a further 14 acres of the total of 171 acres planned for future reclamation. Construction of the first section of seawall foundation 1,200 feet long commenced in October and a contract for the construction of the seawall was let in March.
Hung Hom Reclamation
4.33. 2,000 feet of seawall in Stage IIB were completed and work continued on a further 1,200 feet in Stage IIA, this being the final stage of this reclamation.
Kowloon Bay Reclamation
4.34. Work on the foundations of 3,000 ft. of seawall continued and in July, construction of the seawall started. This enabled public dumping to proceed and some 60 acres of land to be reclaimed.
Cha Kwo Ling Reclamation
4.35. Work commenced on Stage I of this reclamation involving the construction of approximately 600 feet of seawall. The planning and design for Stage II was completed. This reclamation will provide landing facilities for harbour ferry services, land for a waterfront road and a provisional site for a second refuse incinerator in Kowloon, together with approximately 19 acres of land for industrial use. A sheltered anchorage for small craft will also be provided.
Sam Ka Tsuen Reclamation and Breakwater
4.36. Foundation work neared completion and the construction of the seawall and breakwater was well advanced by the end of the year.
Kennedy Town Reclamation
4.37. Work commenced in November on the construction of a pumphouse and a short extension of the existing seawall at Kennedy Town. The pumphouse is required to provide a sea water supply to the new Kennedy Town refuse incinerator and also for a flushing water supply for the western district. Planning and design were carried out for a further 500 feet extension to the seawall which will retain approximately 3.5 acres of additional reclaimed land.
36
Page 57
dumping continued. Approximately 560,000 cubic yards of fill were placed.
Chai Wan Reclamation
4.32. A total of 680,000 cubic yards of spoil was placed at Chai Wan Reclamation forming a further 14 acres of the total of 171 acres planned for future reclamation. Construction of the first section of seawall foundation 1,200 feet long commenced in October and a contract for the construction of the seawall was let in March.
Hung Hom Reclamation
4.33. 2,000 feet of seawall in Stage IIB were completed and work continued on a further 1,200 feet in Stage IIA, this being the final stage of this reclamation.
Kowloon Bay Reclamation
4.34. Work on the foundations of 3,000 ft. of seawall continued and in July, construction of the seawall started. This enabled public dumping to proceed and some 60 acres of land to be reclaimed.
Cha Kwo Ling Reclamation
4.35. Work commenced on Stage I of this reclamation involving the construction of approximately 600 feet of seawall. The planning and design for Stage II was completed. This reclamation will provide landing facilities for harbour ferry services, land for a waterfront road and a provisional site for a second refuse incinerator in Kowloon, together with approximately 19 acres of land for industrial use. A sheltered an- chorage for small craft will also be provided.
Sam Ka Tsuen Reclamation and Breakwater
4.36. Foundation work neared completion and the construction of the seawall and breakwater was well advanced by the end of the year.
Kennedy Town Reclamation
4.37. Work commenced in November on the construction of a pump- house and a short extension of the existing seawall at Kennedy Town. The pumphouse is required to provide a sea water supply to the new Kennedy Town refuse incinerator and also for a flushing water supply for the western district. Planning and design were carried out for a further 500 feet extension to the seawall which will retain approximately 3.5 acres of additional reclaimed land.