Resettlement Department Staff Quarters
2.72.
(1) Tai Wo Hau III - Construction of 19 quarters near completion. (2) Tin Wan, Aberdeen - Construction of 15 quarters near completion.
(3) Wang Tau Hom/Lo Fu Ngam - The building for 43 quarters was being piled. 2.73. Working drawings were in course of preparation for the Chai Wan Staff Quarters Extension (10 quarters) and revised layout plans were in hand for the Kwun Tong Staff Quarters Extension (43 quarters) to provide accommodation for the resettlement staff of the Ham Tin, Sau Mau Ping and Yau Tong Estates.
Resettlement Flatted Factories
2.74. Construction was in progress for two 7-storey flatted factories at San Po Kong, two at Cheung Sha Wan, two at Kwun Tong and one at Tai Wo Hau, Tsuen Wan. Piling was in hand for one 7-storey flatted factory at Yuen Long. All these eight factories, when completed, will provide 806,400 sq. ft. working space.
2.75. In addition, site formation for five 7-storey factories at Kwai Chung Area 28, another five at Kwai Chung Area 27, and two at Pak Tin was in hand. A revised sketch plan was prepared for three 7-storey factories at Choi Hung.
SOCIAL WELFARE BUILDINGS
2.76. The Aberdeen Welfare Centre was finished early in the year. A building contract was signed for a Community Centre at Tai Hang Tung but delays on the site formation contract prevented an immediate start on the building work. Sketch plans were completed and site formation was in progress at a site near Lai Chi Kok for an Approved School for Boys. Contract documents were being prepared for the Kowloon Probation Home.
URBAN SERVICES AND PUBLIC BUILDINGS
Parks, Playgrounds, Latrines and Bath-houses
2.77. Stage I of the Kowloon Tsai Park development, which comprised the open air swimming pool and ancillary buildings, was finally completed early in the year and sketch plans were prepared for the remainder of the project which includes the provision of various sports facilities and the layout of the park.
21
Page 21
Resettlement Department Staff Quarters
2.72.
(1) Tai Wo Hau III-Construction of 19 quarters near completion. (2) Tin Wan, Aberdeen-Construction of 15 quarters near completion.
(3) Wang Tau Hom/Lo Fu Ngam-The building for 43 quarters was being piled. 2.73. Working drawings were in course of preparation for the Chai Wan Staff Quarters Extension (10 quarters) and revised layout plans were in hand for the Kwun Tong Staff Quarters Extension (43 quarters) to provide accommodation for the resettlement staff of the Ham Tin, Sau Mau Ping and Yau Tong Estates.
Resettlement Flatted Factories
2.74. Construction was in progress for two 7-storey flatted factories at San Po Kong, two at Cheung Sha Wan, two at Kwun Tong and one at Tai Wo Hau, Tsuen Wan. Piling was in hand for one 7-storey flatted factory at Yuen Long. All these eight factories, when completed, will provide 806,400 sq. ft. working space.
2.75. In addition, site formation for five 7-storey factories at Kwai Chung Area 28, another five at Kwai Chung Area 27, and two at Pak Tin was in hand. A revised sketch plan was prepared for three 7-storey factories at Choi Hung.
SOCIAL WELFARE BUILDINGS
2.76. The Aberdeen Welfare Centre was finished early in the year. A building contract was signed for a Community Centre at Tai Hang Tung but delays on the site formation contract prevented an immediate start on the building work. Sketch plans were completed and site formation was in progress at a site near Lai Chi Kok for an Approved School for Boys. Contract documents were being prepared for the Kowloon Pro- bation Home.
URBAN SERVICES AND PUBLIC BUILDINGS
Parks, Playgrounds, Latrines and Bath-houses
2.77. Stage I of the Kowloon Tsai Park development, which comprised the open air swimming pool and ancillary buildings, was finally completed early in the year and sketch plans were prepared for the remainder of the project which includes the provision of various sports facilities and the layout of the park.