2.65. Coupled with this achievement was the completion at Tung Tau, of the first of the 16-storey blocks with lifts and individual toilets. Attached to this block was the first of the 6-storey Annex Type Schools. 2.66. Domestic accommodation for 134,000 people was provided in a total of 104 blocks, which were completed during the year, all of these being 8-storey blocks with the exception of the block at Tung Tau. In addition, these 8-storey blocks provided on some of the top floors a total of 151 primary classrooms which, when added to the 24 in the Tung Tau Annex, makes a grand production total for the year of 175 primary classrooms.
2.67. Ground floor shops, hawker bazaars, social welfare centres, administration offices and recreation facilities were also provided in all estates.
2.68. Expenditure on resettlement buildings amounted to $102.4 million compared with $86.7 million in 1963-64.
Buildings completed
2.69 The following resettlement domestic buildings at various estates were completed:
(1) Kwai Chung Central 'C' (2) Tai Wo Hau III
(3) Yau Tong Bay 'A' and 'B'
(4) Sau Mau Ping (5) Chai Wan III
... ...
(6) Tin Wan-Aberdeen
(7) Tsz Wan Shan ...
(8) Tung Tau II
Tung Tau II
Projects in progress
... ... ..
10 blocks (Mk. III)-Estate completed 20 blocks (Mk. III) 18 blocks (Mk. III)—These sections of estate completed 9 blocks (Mk. III) 9 blocks (Mk. III) 9 blocks (Mk. III) 26 blocks (Mk. III) 2 blocks (Mk. II) 1 block (Mk. IV)-16-storey2.70. Site formation, piling or construction was in progress for buildings at the following estates:
(1) Chai Wan (Stage III): This stage of the Chai Wan Estate, when completed, will provide accommodation for about 28,000 people. All the 8-storey blocks were completed and the construction of the remaining three 16-storey blocks was well in hand.
(2) Tin Wan (Aberdeen): Construction of the final four 8-storey blocks was in hand. This estate will provide accommodation for some 17,400 people.
(3) Tai Wo Hau (Stage III): Construction of the last two 8-storey blocks was near completion and the 16-storey block 'X' in this area was also well under way. This further stage of the estate, including block 'X', will provide accommodation for a total of about 30,800 people.
19
2.65. Coupled with this achievement was the completion at Tung Tau, of the first of the 16-storey blocks with lifts and individual toilets. Attached to this block was the first of the 6-storey Annex Type Schools. 2.66. Domestic accommodation for 134,000 people was provided in a total of 104 blocks, which were completed during the year, all of these being 8-storey blocks with the exception of the block at Tung Tau. In addition, these 8-storey blocks provided on some of the top floors a total of 151 primary classrooms which, when added to the 24 in the Tung Tau Annex, makes a grand production total for the year of 175 primary class-
rooms.
2.67. Ground floor shops, hawker bazaars, social welfare centres, administration offices and recreation facilities were also provided in all estates.
2.68. Expenditure on resettlement buildings amounted to $102.4 million compared with $86.7 million in 1963-64.
Buildings completed
2.69 The following resettlement domestic buildings at various estates were completed:
(1) Kwai Chung Central 'C' (2) Tai Wo Hau III
(3) Yau Tong Bay 'A' and 'B'
(4) Sau Mau Ping (5) Chai Wan III
...
...
(6) Tin Wan-Aberdeen
(7) Tsz Wan Shan ...
(8) Tung Tau II
Tung Tau II
Projects in progress
...
...
..
10 blocks (Mk. III)-Estate completed 20 blocks (Mk. III)
18 blocks (Mk. III)—These sections of
estate completed
9 blocks (Mk. III) 9 blocks (Mk. III) 9 blocks (Mk. III) 26 blocks (Mk. III)
2 blocks (Mk. II
1 block (Mk. IV)-16-storey
2.70. Site formation, piling or construction was in progress for build- ings at the following estates:
(1) Chai Wan (Stage III): This stage of the Chai Wan Estate, when completed, will provide accommodation for about 28,000 people. All the 8-storey blocks were completed and the construction of the remaining three 16-storey blocks was well in hand.
(2) Tin Wan (Aberdeen): Construction of the final four 8-storey blocks was in hand. This estate will provide accommodation for some 17,400 people.
(3) Tai Wo Hau (Stage III): Construction of the last two 8-storey blocks was near completion and the 16-storey block 'X' in this area was also well under way. This further stage of the estate, including block 'X', will provide accommodation for a total of about 30,800 people.