1964-1965 — Page 163

Public Works Department Annual Report 工務司署年報 All AI Reviewed

Kwun Tong High Level Supply

7.57. From a combined treated and flushing water pump house at the north eastern extremity of the Jordan Valley Resettlement Estate water will be pumped to a combined reservoir on the summit of Shum Wan Shan. This will supply the higher developments above Kwun Tong in general and the Sau Mau Ping Resettlement Estate in particular. Both reservoirs were substantially completed with the exception of a section of the fresh water reservoir cover slab. 1,700 ft. of the 27" and 24" dia. fresh water delivery main from the pump house and outlet main from the reservoir were laid, together with 300 ft. of the flushing water main. A contract was awarded for the construction of the pump house and quarters and an order placed for the pumping equipment.

Water Supply to Resettlement Estate at Sau Mau Ping

7.58. This will be provided from Kwun Tong High Level service reservoir by ring mains of 24" dia. for fresh water, and 15" dia. for flushing water with distribution mains within the estate. 1,600 ft. of 24" and 1,400 ft. of 15" dia. main were laid, thus completing 15% of the ring mains.

Water Supply to Tsz Wan Shan and Wang Tau Hom Resettlement Estates

7.59. Tsz Wan Shan is provided by fresh and sea water pumped from the Diamond Hill combined pumping station to the high level Fung Wong reservoirs from where the water gravitates to the two estates and other high level development above Kai Tak. Wang Tau Hom was supplied by extension of the low level system and the project was substantially completed during the year.

Valley Road Low Cost Housing Water Supply

7.60. This consists of mainlaying for both fresh and flushing water in conjunction with the development of the estate. 390 ft. of fresh water and 144 ft. of salt water mains were laid.

Yau Tong Water Supply

7.61. This comprises the extension of the trunk main from Kwun Tong to a service reservoir, with a foreshore sea water pump house and reception tank for flushing water constructed jointly with the fresh water service reservoir, including outlet mains. The reservoir site formation was substantially completed and concreting of the walls was started. 900 ft. of 24" and 764 ft. of 18" dia. mains were laid.

82

Edit History

2026-05-11 23:26:52 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Kwun Tong High Level Supply 7.57. From a combined treated and flushing water pump house at the north eastern extremity of the Jordan Valley Resettlement Estate water will be pumped to a combined reservoir on the summit of Shum Wan Shan. This will supply the higher developments above Kwun Tong in general and the Sau Mau Ping Resettlement Estate in particular. Both reservoirs were substantially completed with the exception of a section of the fresh water reservoir cover slab. 1,700 ft. of the 27" and 24" dia. fresh water delivery main from the pump house and outlet main from the reservoir were laid, together with 300 ft. of the flushing water main. A contract was awarded for the construction of the pump house and quarters and an order placed for the pumping equipment. Water Supply to Resettlement Estate at Sau Mau Ping 7.58. This will be provided from Kwun Tong High Level service reservoir by ring mains of 24" dia. for fresh water, and 15" dia. for flushing water with distribution mains within the estate. 1,600 ft. of 24" and 1,400 ft. of 15" dia. main were laid, thus completing 15% of the ring mains. Water Supply to Tsz Wan Shan and Wang Tau Hom Resettlement Estates 7.59. Tsz Wan Shan is provided by fresh and sea water pumped from the Diamond Hill combined pumping station to the high level Fung Wong reservoirs from where the water gravitates to the two estates and other high level development above Kai Tak. Wang Tau Hom was supplied by extension of the low level system and the project was substantially completed during the year. Valley Road Low Cost Housing Water Supply 7.60. This consists of mainlaying for both fresh and flushing water in conjunction with the development of the estate. 390 ft. of fresh water and 144 ft. of salt water mains were laid. Yau Tong Water Supply 7.61. This comprises the extension of the trunk main from Kwun Tong to a service reservoir, with a foreshore sea water pump house and reception tank for flushing water constructed jointly with the fresh water service reservoir, including outlet mains. The reservoir site formation was substantially completed and concreting of the walls was started. 900 ft. of 24" and 764 ft. of 18" dia. mains were laid. 82
Baseline (Original)
Kwun Tong High Level Supply 7.57. From a combined treated and flushing water pump house at the north eastern extremity of the Jordan Valley Resettlement Estate water will be pumped to a combined reservoir on the summit of Shum Wan Shan. This will supply the higher developments above Kwun Tong in general and the Sau Mau Ping Resettlement Estate in particular. Both reservoirs were substantially completed with the exception of a section of the fresh water reservoir cover slab. 1,700 ft. of the 27" and 24′′ dia. fresh water delivery main from the pump house and outlet main from the reservoir were laid, together with 300 ft. of the flushing water main. A contract was awarded for the construction of the pump house and quarters and an order placed for the pumping equipment. Water Supply to Resettlement Estate at Sau Mau Ping 7.58. This will be provided from Kwun Tong High Level service reservoir by ring mains of 24" dia. for fresh water, and 15" dia. for flushing water with distribution mains within the estate. 1,600 ft. of 24" and 1,400 ft. of 15" dia. main were laid, thus completing 15% of the ring mains. Water Supply to Tsz Wan Shan and Wang Tau Hom Resettlement Estates 7.59. Tsz Wan Shan is provided by fresh and sea water pumped from the Diamond Hill combined pumping station to the high level Fung Wong reservoirs from where the water gravitates to the two estates and other high level development above Kai Tak. Wang Tau Hom was supplied by extension of the low level system and the project was sub- stantially completed during the year. Valley Road Low Cost Housing Water Supply 7.60. This consists of mainlaying for both fresh and flushing water in conjunction with the development of the estate. 390 ft. of fresh water and 144 ft. of salt water mains were laid. Yau Tong Water Supply 7.61. This comprises the extension of the trunk main from Kwun Tong to a service reservoir, with a foreshore sea water pump house and reception tank for flushing water constructed jointly with the fresh water service reservoir, including outlet mains. The reservoir site formation was substantially completed and concreting of the walls was started. 900 ft. of 24′′ and 764 ft. of 18" dia. mains were laid. 82
2026-05-11 23:26:52 · Baseline
View content

Kwun Tong High Level Supply

7.57. From a combined treated and flushing water pump house at the north eastern extremity of the Jordan Valley Resettlement Estate water will be pumped to a combined reservoir on the summit of Shum Wan Shan. This will supply the higher developments above Kwun Tong in general and the Sau Mau Ping Resettlement Estate in particular. Both reservoirs were substantially completed with the exception of a section of the fresh water reservoir cover slab. 1,700 ft. of the 27" and 24′′ dia. fresh water delivery main from the pump house and outlet main from the reservoir were laid, together with 300 ft. of the flushing water main. A contract was awarded for the construction of the pump house and quarters and an order placed for the pumping equipment.

Water Supply to Resettlement Estate at Sau Mau Ping

7.58. This will be provided from Kwun Tong High Level service reservoir by ring mains of 24" dia. for fresh water, and 15" dia. for flushing water with distribution mains within the estate. 1,600 ft. of 24" and 1,400 ft. of 15" dia. main were laid, thus completing 15% of the ring mains.

Water Supply to Tsz Wan Shan and Wang Tau Hom Resettlement Estates

7.59. Tsz Wan Shan is provided by fresh and sea water pumped from the Diamond Hill combined pumping station to the high level Fung Wong reservoirs from where the water gravitates to the two estates and other high level development above Kai Tak. Wang Tau Hom was supplied by extension of the low level system and the project was sub- stantially completed during the year.

Valley Road Low Cost Housing Water Supply

7.60. This consists of mainlaying for both fresh and flushing water in conjunction with the development of the estate. 390 ft. of fresh water and 144 ft. of salt water mains were laid.

Yau Tong Water Supply

7.61. This comprises the extension of the trunk main from Kwun Tong to a service reservoir, with a foreshore sea water pump house and reception tank for flushing water constructed jointly with the fresh water service reservoir, including outlet mains. The reservoir site formation was substantially completed and concreting of the walls was started. 900 ft. of 24′′ and 764 ft. of 18" dia. mains were laid.

82