9.09. As part of a scheme to improve the two sharp hair-pin bends on Magazine Gap Road, widening and realignment of the carriageway at the upper bend, at the junction with May Road was put in hand.
9.10. Roads reconstructed in reinforced concrete included Tung Lo Wan Road north of Wun Sha Street, Hoi Ning Street north of Shau Kei Wan Road, Queen's Street, Jardines Bazaar, Wellington Street and Lyndhurst Terrace.
ISLAND ROADS OUTSIDE CITY LIMITS
9.11. The extension of Java Road from Healthy Street West towards Healthy Street East was completed and will provide a valuable alternative route for east-bound traffic from the North Point Vehicular Ferry Pier to King's Road.
9.12. Road-widening schemes were well advanced at Victoria Road from Kennedy Town to Mt. Davis Road and along a section of Cape Collinson Road which also included construction of a link road to Chai Wan. Widening of a considerable length of Chung Hom Kok Road was completed.
9.13. With the completion of Deep Water Bay Road widening, the anticipated increase in traffic using the junction of this road with Repulse Bay Road precipitated the need to carry out improvements, and work was put in hand to separate north and south bound traffic and to eliminate dangerous right-turning movements.
9.14. On Repulse Bay Road, work commenced on the widening of the narrow bridge over Beach Road which is located on a sharp bend and has been a constant hazard to traffic.
9.15. Major work started on the section of Pokfulam Road between Pokfulam Village and Victoria Road, involving widening and substantial realignment to eliminate the existing dangerous and steep bends.
9.16. The resurfacing of roads took place on a large scale and included sections of King's Road, Des Voeux Road, Wong Nai Chung Road, Queen's Road East, Leighton Road, Hennessy Road and many minor roads.
KOWLOON ROADS
9.17. The reconstruction of Nathan Road to withstand the heavy present-day traffic loads was continued and that section from Pak Hoi Street to Wing Sing Lane was completed, whilst the work on the portion from Nullah Road to Boundary Street was commenced.
57
9.09. As part of a scheme to improve the two sharp hair-pin bends on Magazine Gap Road, widening and realignment of the carriageway at the upper bend, at the junction with May Road was put in hand.
9.10. Roads reconstructed in reinforced concrete included Tung Lo Wan Road north of Wun Sha Street, Hoi Ning Street north of Shau Kei Wan Road, Queen's Street, Jardines Bazaar, Wellington Street and Lyndhurst Terrace.
ISLAND ROADS OUTSIDE CITY LIMITS
9.11. The extension of Java Road from Healthy Street West towards Healthy Street East was completed and will provide a valuable alter- native route for east-bound traffic from the North Point Vehicular Ferry Pier to King's Road.
9.12. Road-widening schemes were well advanced at Victoria Road from Kennedy Town to Mt. Davis Road and along a section of Cape Collinson Road which also included construction of a link road to Chai Wan. Widening of a considerable length of Chung Hom Kok Road was completed.
9.13. With the completion of Deep Water Bay Road widening, the anticipated increase in traffic using the junction of this road with Repulse Bay Road precipitated the need to carry out improvements, and work was put in hand to separate north and south bound traffic and to elimi- nate dangerous right-turning movements.
9.14. On Repulse Bay Road, work commenced on the widening of the narrow bridge over Beach Road which is located on a sharp bend and has been a constant hazard to traffic.
9.15. Major work started on the section of Pokfulam Road between Pokfulam Village and Victoria Road, involving widening and substantial realignment to eliminate the existing dangerous and steep bends.
9.16. The resurfacing of roads took place on a large scale and in- cluded sections of King's Road, Des Voeux Road, Wong Nai Chung Road, Queen's Road East, Leighton Road, Hennessy Road and many minor roads.
KOWLOON ROADS
9.17. The reconstruction of Nathan Road to withstand the heavy present-day traffic loads was continued and that section from Pak Hoi Street to Wing Sing Lane was completed, whilst the work on the portion from Nullah Road to Boundary Street was commenced.