(3) Kwai Chung Central (Area C): Construction of the remaining ten 8-storey blocks was in hand. When completed, this estate will provide accommodation for about 23,300 people.
(4) Tai Wo Hau Stage III: Construction of twenty-two 8-storey blocks was in hand and this further stage of the Tai Wo Hau Estate will provide accommodation for about 27,300 people.
(5) Yau Tong Bay: This estate comprising twenty-seven 8-storey blocks for about 28,200 people is divided into three working areas. Construction of 18 blocks in Areas A & B were well in hand and site formation work was started for the remaining Area C.
(6) Tsz Wan Shan: Site formation work based on the revised scheme was in its final stages. Construction of thirty-six 8-storey blocks and two sixteen-storey blocks was in hand and another two 16-storey blocks were being piled. This estate is expected to house about 180,000 people with provision for thirteen 24-classroom annexe schools.
(7) Ham Tin Area 'A': There will be six 16-storey blocks in the estate for about 48,000 people and site-formation work was well advanced. Piling for the first block was completed and construction of the block started.
(8) Sau Mau Ping: This estate is divided into two working stages. In Stage I with seventeen 8-storey blocks for about 21,000 people, piling for the blocks was completed and construction of sixteen blocks was in hand. Stage II was designed to accommodate some 120,000 people in 16-storey blocks was approved. Site-formation work based on the revised layout was in hand by the Development Office.
(9) Tung Tau (Stage II): There will be two 8-storey (H) type, one 8-storey (I) type and two 16-storey blocks in this section of the Tung Tau Estate. Construction of the two 8-storey (H) type and two 16-storey blocks was in hand. This stage will provide accommodation for some 23,000 people.
(10) Aberdeen (site II): Site formation formerly carried out by the Development Office was taken over by Port Works Office to form building platforms for two 8-storey and five 16-storey blocks accommodating 26,000 people.
(11) Kwai Chung (North): Site formation work was in hand by Development Office. Accommodation will be provided for 65,000 people in 8- and 16-storey domestic blocks.
Drawings and plans under preparation:
2.49. Feasibility plans, detailed sketch plans or contract drawings were also prepared for various other estates at:
(1) Yuen Long: Working drawings for site formation for this estate were completed, providing building areas to house about 10,000 people in eight 8-storey blocks.
(2) Jordan Valley (West): A revised sketch layout was prepared for the 16-storey blocks for about 69,000 people.
(3) Cheung Sha Wan: As with Jordan Valley (West), a sketch scheme for seven 16-storey blocks which will accommodate some 40,000 people was prepared.
15
(3) Kwai Chung Central (Area C): Construction of the remaining ten 8-storey blocks was in hand. When completed, this estate will provide accommodation for about 23,300 people.
(4) Tai Wo Hau Stage III: Construction of twenty-two 8-storey blocks was in hand and this further stage of the Tai Wo Hau Estate will provide accommodation for about 27,300 people.
(5) Yau Tong Bay: This estate comprising twenty-seven 8-storey blocks for about 28,200 people is divided into three working area. Con- struction of 18 blocks in Areas A & B were well in hand and site formation work was started for the remaining Area C.
(6) Tsz Wan Shan: Site formation work based on the revised scheme was in its final stages. Construction of thirty-six 8-storey blocks and two sixteen-storey blocks was in hand and another two 16-storey blocks were being piled. This estate is expected to house about 180,000 people with provision for thirteen 24-classroom annexe schools.
(7) Ham Tin Area 'A': There will be six 16-storey blocks in the estate for about 48,000 people and site-formation work was well advanced. Piling for the first block was completed and construction of the block started.
(8) Sau Mau Ping: This estate is divided into two working stages. In Stage I with seventeen 8-storey blocks for about 21,000 people, piling for the blocks was completed and construction of sixteen blocks was in hand. Stage II was designed to accommodate some 120,000 people in 16-storey blocks was approved. Site-formation work based on the revised layout was in hand by the Development Office.
(9) Tung Tau (Stage II): There will be two 8-storey (H) type, one 8-storey (I) type and two 16-storey blocks in this section of the Tung Tau Estate. Construction of the two 8-storey (H) type and two 16-storey blocks was in hand. This stage will provide accommodation for some 23,000 people.
(10) Aberdeen (site II): Site formation formerly carried out by the Development Office was taken over by Port Works Office to form building platforms for two 8-storey and five 16-storey blocks accom- modating 26,000 people.
(11) Kwai Chung (North): Site formation work was in hand by Develop- ment Office. Accommodation will be provided for 65,000 people in 8- and 16-storey domestic blocks.
Drawings and plans under preparation:
2.49. Feasibility plans, detailed sketch plans or contract drawings were also prepared for various other estates at:
(1) Yuen Long: Working drawings for site formation for this estate were completed, providing building areas to house about 10,000 people in eight 8-storey blocks.
(2) Jordan Valley (West): A revised sketch layout was prepared for the
16-storey blocks for about 69,000 people.
(3) Cheung Sha Wan: As with Jordan Valley (West), a sketch scheme for seven 16-storey blocks which will accommodate some 40,000 people was prepared.