1962-1963 — Page 66

Public Works Department Annual Report 工務司署年報 All AI Reviewed

ROADS OFFICE

WORKS SECTION

Chief Engineer:

J. R. WHITAKER, M.A. (Cantab.), A.M.I.C.E., M.I.Mun.E., A.M.I.T.E.

GENERAL

9.01. Relatively little damage was caused to roads by the severe rainstorms in June and the passing of typhoon 'Wanda' over the Colony in September, except in the New Territories where the areas worst affected were Sai Kung, Tai Po and Sha Tau Kok.

9.02. Construction of new roads totalled 10 miles. 4 miles of roads in the New Territories were taken over from the War Department, 13 miles of existing roads were reconstructed and 35 miles surfaced or resurfaced. The general maintenance of roads and footpaths, although initially hampered by rain and typhoons, was greatly assisted by the exceptionally dry weather in the latter part of the year.

9.03. General improvement schemes to existing roads were implemented in many areas. These took the form of junction modifications, improved widths, alignments and superelevation of carriageway, provision of passing bays on narrow roads and of dividing strips with fencing where increased vehicle and pedestrian control was required.

9.04. The following expenditure was incurred:

Hong Kong Kowloon New Territories Total New Roads $2,205,000 $6,548,000 $7,572,000 $16,325,000 Reconstruction & Improvements $2,530,000 Maintenance $1,802,000 $4,977,000 $1,803,000 $2,092,000 $9,599,000 $2,513,000 $6,118,000 Storm Damage $389,000 $143,000 $856,000 $1,388,000 Total $6,926,000 $13,471,000 $13,033,000 $33,430,000

9.05. Details follow of the work and responsibilities of the Roads Office, divided partly on a regional basis and partly on a functional basis.

CITY ROADS, VICTORIA

9.06. The widening of Pok Fu Lam Road adjoining the University recreation ground and the construction of a bus terminus in this area were completed. An unusual feature of the project was the reversal of

Page 48


should be revised to meet the exact format requirement as

ROADS OFFICE

WORKS SECTION

Chief Engineer:

J. R. WHITAKER, M.A. (Cantab.), A.M.I.C.E., M.I.Mun.E., A.M.I.T.E.

GENERAL

9.01. Relatively little damage was caused to roads by the severe rainstorms in June and the passing of typhoon 'Wanda' over the Colony in September, except in the New Territories where the areas worst affected were Sai Kung, Tai Po and Sha Tau Kok.

9.02. Construction of new roads totalled 10 miles. 4 miles of roads in the New Territories were taken over from the War Department, 13 miles of existing roads were reconstructed and 35 miles surfaced or resurfaced. The general maintenance of roads and footpaths, although initially hampered by rain and typhoons, was greatly assisted by the exceptionally dry weather in the latter part of the year.

9.03. General improvement schemes to existing roads were implemented in many areas. These took the form of junction modifications, improved widths, alignments and superelevation of carriageway, provision of passing bays on narrow roads and of dividing strips with fencing where increased vehicle and pedestrian control was required.

9.04. The following expenditure was incurred:

Hong Kong Kowloon New Territories Total New Roads $2,205,000 $6,548,000 $7,572,000 $16,325,000 Reconstruction & Improvements $2,530,000 Maintenance $1,802,000 $4,977,000 $2,513,000 $6,118,000 $9,599,000 Storm Damage $389,000 $143,000 $856,000 $1,388,000 Total $6,926,000 $13,471,000 $13,033,000 $33,430,000

9.05. Details follow of the work and responsibilities of the Roads Office, divided partly on a regional basis and partly on a functional basis.

CITY ROADS, VICTORIA

9.06. The widening of Pok Fu Lam Road adjoining the University recreation ground and the construction of a bus terminus in this area were completed. An unusual feature of the project was the reversal of

Page 48

The final output is

ROADS OFFICE

WORKS SECTION

Chief Engineer:

J. R. WHITAKER, M.A. (Cantab.), A.M.I.C.E., M.I.Mun.E., A.M.I.T.E.

GENERAL

9.01. Relatively little damage was caused to roads by the severe rainstorms in June and the passing of typhoon 'Wanda' over the Colony in September, except in the New Territories where the areas worst affected were Sai Kung, Tai Po and Sha Tau Kok.

9.02. Construction of new roads totalled 10 miles. 4 miles of roads in the New Territories were taken over from the War Department, 13 miles of existing roads were reconstructed and 35 miles surfaced or resurfaced. The general maintenance of roads and footpaths, although initially hampered by rain and typhoons, was greatly assisted by the exceptionally dry weather in the latter part of the year.

9.03. General improvement schemes to existing roads were implemented in many areas. These took the form of junction modifications, improved widths, alignments and superelevation of carriageway, provision of passing bays on narrow roads and of dividing strips with fencing where increased vehicle and pedestrian control was required.

9.04. The following expenditure was incurred:

Hong Kong Kowloon New Territories Total New Roads $2,205,000 $6,548,000 $7,572,000 $16,325,000 Reconstruction & Improvements $2,530,000 Maintenance $1,802,000 $4,977,000 $2,513,000 $6,118,000 $9,599,000 Storm Damage $389,000 $143,000 $856,000 $1,388,000 Total $6,926,000 $13,471,000 $13,033,000 $33,430,000

9.05. Details follow of the work and responsibilities of the Roads Office, divided partly on a regional basis and partly on a functional basis.

CITY ROADS, VICTORIA

9.06. The widening of Pok Fu Lam Road adjoining the University recreation ground and the construction of a bus terminus in this area were completed. An unusual feature of the project was the reversal of

Page 48

Edit History

2026-05-11 22:26:25 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
ROADS OFFICE WORKS SECTION Chief Engineer: J. R. WHITAKER, M.A. (Cantab.), A.M.I.C.E., M.I.Mun.E., A.M.I.T.E. GENERAL 9.01. Relatively little damage was caused to roads by the severe rainstorms in June and the passing of typhoon 'Wanda' over the Colony in September, except in the New Territories where the areas worst affected were Sai Kung, Tai Po and Sha Tau Kok. 9.02. Construction of new roads totalled 10 miles. 4 miles of roads in the New Territories were taken over from the War Department, 13 miles of existing roads were reconstructed and 35 miles surfaced or resurfaced. The general maintenance of roads and footpaths, although initially hampered by rain and typhoons, was greatly assisted by the exceptionally dry weather in the latter part of the year. 9.03. General improvement schemes to existing roads were implemented in many areas. These took the form of junction modifications, improved widths, alignments and superelevation of carriageway, provision of passing bays on narrow roads and of dividing strips with fencing where increased vehicle and pedestrian control was required. 9.04. The following expenditure was incurred: Hong Kong Kowloon New Territories Total New Roads $2,205,000 $6,548,000 $7,572,000 $16,325,000 Reconstruction & Improvements $2,530,000 Maintenance $1,802,000 $4,977,000 $1,803,000 $2,092,000 $9,599,000 $2,513,000 $6,118,000 Storm Damage $389,000 $143,000 $856,000 $1,388,000 Total $6,926,000 $13,471,000 $13,033,000 $33,430,000 9.05. Details follow of the work and responsibilities of the Roads Office, divided partly on a regional basis and partly on a functional basis. CITY ROADS, VICTORIA 9.06. The widening of Pok Fu Lam Road adjoining the University recreation ground and the construction of a bus terminus in this area were completed. An unusual feature of the project was the reversal of Page 48 should be revised to meet the exact format requirement as ROADS OFFICE WORKS SECTION Chief Engineer: J. R. WHITAKER, M.A. (Cantab.), A.M.I.C.E., M.I.Mun.E., A.M.I.T.E. GENERAL 9.01. Relatively little damage was caused to roads by the severe rainstorms in June and the passing of typhoon 'Wanda' over the Colony in September, except in the New Territories where the areas worst affected were Sai Kung, Tai Po and Sha Tau Kok. 9.02. Construction of new roads totalled 10 miles. 4 miles of roads in the New Territories were taken over from the War Department, 13 miles of existing roads were reconstructed and 35 miles surfaced or resurfaced. The general maintenance of roads and footpaths, although initially hampered by rain and typhoons, was greatly assisted by the exceptionally dry weather in the latter part of the year. 9.03. General improvement schemes to existing roads were implemented in many areas. These took the form of junction modifications, improved widths, alignments and superelevation of carriageway, provision of passing bays on narrow roads and of dividing strips with fencing where increased vehicle and pedestrian control was required. 9.04. The following expenditure was incurred: Hong Kong Kowloon New Territories Total New Roads $2,205,000 $6,548,000 $7,572,000 $16,325,000 Reconstruction & Improvements $2,530,000 Maintenance $1,802,000 $4,977,000 $2,513,000 $6,118,000 $9,599,000 Storm Damage $389,000 $143,000 $856,000 $1,388,000 Total $6,926,000 $13,471,000 $13,033,000 $33,430,000 9.05. Details follow of the work and responsibilities of the Roads Office, divided partly on a regional basis and partly on a functional basis. CITY ROADS, VICTORIA 9.06. The widening of Pok Fu Lam Road adjoining the University recreation ground and the construction of a bus terminus in this area were completed. An unusual feature of the project was the reversal of Page 48 The final output is ROADS OFFICE WORKS SECTION Chief Engineer: J. R. WHITAKER, M.A. (Cantab.), A.M.I.C.E., M.I.Mun.E., A.M.I.T.E. GENERAL 9.01. Relatively little damage was caused to roads by the severe rainstorms in June and the passing of typhoon 'Wanda' over the Colony in September, except in the New Territories where the areas worst affected were Sai Kung, Tai Po and Sha Tau Kok. 9.02. Construction of new roads totalled 10 miles. 4 miles of roads in the New Territories were taken over from the War Department, 13 miles of existing roads were reconstructed and 35 miles surfaced or resurfaced. The general maintenance of roads and footpaths, although initially hampered by rain and typhoons, was greatly assisted by the exceptionally dry weather in the latter part of the year. 9.03. General improvement schemes to existing roads were implemented in many areas. These took the form of junction modifications, improved widths, alignments and superelevation of carriageway, provision of passing bays on narrow roads and of dividing strips with fencing where increased vehicle and pedestrian control was required. 9.04. The following expenditure was incurred: Hong Kong Kowloon New Territories Total New Roads $2,205,000 $6,548,000 $7,572,000 $16,325,000 Reconstruction & Improvements $2,530,000 Maintenance $1,802,000 $4,977,000 $2,513,000 $6,118,000 $9,599,000 Storm Damage $389,000 $143,000 $856,000 $1,388,000 Total $6,926,000 $13,471,000 $13,033,000 $33,430,000 9.05. Details follow of the work and responsibilities of the Roads Office, divided partly on a regional basis and partly on a functional basis. CITY ROADS, VICTORIA 9.06. The widening of Pok Fu Lam Road adjoining the University recreation ground and the construction of a bus terminus in this area were completed. An unusual feature of the project was the reversal of Page 48
Baseline (Original)
ROADS OFFICE WORKS SECTION Chief Engineer: J. R. WHITAKER, M.A. (Cantab.), A.M.I.C.E., M.I.Mun.E., A.M.I.T.E. GENERAL 9.01. Relatively little damage was caused to roads by the severe rainstorms in June and the passing of typhoon 'Wanda' over the Colony in September, except in the New Territories where the areas worst affected were Sai Kung, Tai Po and Sha Tau Kok. 9.02. Construction of new roads totalled 10 miles. 4 miles of roads in the New Territories were taken over from the War Department, 13 miles of existing roads were reconstructed and 35 miles surfaced or resurfaced. The general maintenance of roads and footpaths, although initially hampered by rain and typhoons, was greatly assisted by the exceptionally dry weather in the latter part of the year. 9.03. General improvement schemes to existing roads were imple- mented in many areas. These took the form of junction modifications, improved widths, alignments and superelevation of carriageway, pro- vision of passing bays on narrow roads and of dividing strips with fencing where increased vehicle and pedestrian control was required. 9.04. The following expenditure was incurred: Hong Kong Kowloon New Territories Total New Roads $2,205,000 $ 6,548,000 $ 7,572,000 $16,325,000 Reconstruction & Improvements 2,530,000 Maintenance 1,802,000 4,977,000 1,803,000 2,092,000 9,599,000 2,513,000 6,118,000 Storm Damage 389,000 143,000 856,000 1,388,000 Total $6,926,000 $13,471,000 $13,033,000 $33,430,000 9.05. Details follow of the work and responsibilities of the Roads Office, divided partly on a regional basis and partly on a functional basis. CITY ROADS, VICTORIA 9.06. The widening of Pok Fu Lam Road adjoining the University recreation ground and the construction of a bus terminus in this area were completed. An unusual feature of the project was the reversal of 48
2026-05-11 22:26:25 · Baseline
View content

ROADS OFFICE

WORKS SECTION

Chief Engineer:

J. R. WHITAKER, M.A. (Cantab.), A.M.I.C.E., M.I.Mun.E., A.M.I.T.E.

GENERAL

9.01. Relatively little damage was caused to roads by the severe rainstorms in June and the passing of typhoon 'Wanda' over the Colony in September, except in the New Territories where the areas worst affected were Sai Kung, Tai Po and Sha Tau Kok.

9.02. Construction of new roads totalled 10 miles. 4 miles of roads in the New Territories were taken over from the War Department, 13 miles of existing roads were reconstructed and 35 miles surfaced or resurfaced. The general maintenance of roads and footpaths, although initially hampered by rain and typhoons, was greatly assisted by the exceptionally dry weather in the latter part of the year.

9.03. General improvement schemes to existing roads were imple- mented in many areas. These took the form of junction modifications, improved widths, alignments and superelevation of carriageway, pro- vision of passing bays on narrow roads and of dividing strips with fencing where increased vehicle and pedestrian control was required.

9.04. The following expenditure was incurred:

Hong Kong

Kowloon

New Territories

Total

New Roads

$2,205,000 $ 6,548,000

$ 7,572,000

$16,325,000

Reconstruction & Improvements

2,530,000

Maintenance

1,802,000

4,977,000 1,803,000

2,092,000

9,599,000

2,513,000

6,118,000

Storm Damage

389,000

143,000

856,000

1,388,000

Total

$6,926,000

$13,471,000

$13,033,000 $33,430,000

9.05. Details follow of the work and responsibilities of the Roads Office, divided partly on a regional basis and partly on a functional basis.

CITY ROADS, VICTORIA

9.06. The widening of Pok Fu Lam Road adjoining the University recreation ground and the construction of a bus terminus in this area were completed. An unusual feature of the project was the reversal of

48

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.