5.05. As well as survey work for site investigation, this section provided the necessary control points (triangulation and traversing), the day to day 'setting out' work, contour plans and cross sections for earthwork quantity calculations and all the necessary interim, final and miscellaneous surveys demanded by the contract work.

SITE FORMATION

5.06. At the end of the year 13 contracts were in hand, excluding the work undertaken by Consulting Engineers at Kwai Chung. The following table summarizes the development schemes under construction:

Full scheme Area Expen-diture ($M) to 31.3.63 Location Área to be formed (Acres) Estimated Cost ($M) Com-pleted (Acres) Remarks Kwun Tong New Town 588.6 100.0 456.8 52.5 Area completed included 230 acres of reclamation out of a total of 270 acres. Valley Road 11.5 4.5 9.9 3.2 8.4 acres for low cost housing. 3.1 acres for sale for private development. Waterloo Road Hill 9.2 5.0 9.2 2.4 Sites for hotels, housing and schools. Ho Man Tin Development Area 110.4 25.6 0.7 Sites for residential & community use. No. 3, Lung Cheung Road 43.0 7.6 0.4 Site for low density residential use. Kwai Chung North Development Area 9 90.0 22.0 0.1 Sites for resettlement, low cost housing and workers housing. Total 852.7 164.7 475.9 59.1

5.07. As a result of the exceptionally dry summer, good progress was maintained on all contracts.

Kwun Tong New Town

5.08. The development of Kwun Tong New Town which started in 1955 is due for completion by 1968. During the year, with six formation contracts in progress, a total of 34.7 acres of reclamation and 55.5 acres of levelled building sites were formed.

Page 33


Page 33
Page 33

Edit History

2026-05-11 22:23:19 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
5.05. As well as survey work for site investigation, this section provided the necessary control points (triangulation and traversing), the day to day 'setting out' work, contour plans and cross sections for earthwork quantity calculations and all the necessary interim, final and miscellaneous surveys demanded by the contract work. SITE FORMATION 5.06. At the end of the year 13 contracts were in hand, excluding the work undertaken by Consulting Engineers at Kwai Chung. The following table summarizes the development schemes under construction: Full scheme Area Expen-diture ($M) to 31.3.63 Location Área to be formed (Acres) Estimated Cost ($M) Com-pleted (Acres) Remarks Kwun Tong New Town 588.6 100.0 456.8 52.5 Area completed included 230 acres of reclamation out of a total of 270 acres. Valley Road 11.5 4.5 9.9 3.2 8.4 acres for low cost housing. 3.1 acres for sale for private development. Waterloo Road Hill 9.2 5.0 9.2 2.4 Sites for hotels, housing and schools. Ho Man Tin Development Area 110.4 25.6 0.7 Sites for residential & community use. No. 3, Lung Cheung Road 43.0 7.6 0.4 Site for low density residential use. Kwai Chung North Development Area 9 90.0 22.0 0.1 Sites for resettlement, low cost housing and workers housing. Total 852.7 164.7 475.9 59.1 5.07. As a result of the exceptionally dry summer, good progress was maintained on all contracts. Kwun Tong New Town 5.08. The development of Kwun Tong New Town which started in 1955 is due for completion by 1968. During the year, with six formation contracts in progress, a total of 34.7 acres of reclamation and 55.5 acres of levelled building sites were formed. Page 33 Page 33 Page 33
Baseline (Original)
5.05. As well as survey work for site investigation, this section provided the necessary control points (triangulation and traversing), the day to day 'setting out' work, contour plans and cross sections for earthwork quantity calculations and all the necessary interim, final and miscellaneous surveys demanded by the contract work. SITE FORMATION 5.06. At the end of the year 13 contracts were in hand, excluding the work undertaken by Consulting Engineers at Kwai Chung. The following table summarizes the development schemes under con- struction: Full scheme Area Expen- Location Área to Estimated Com- diture be formed Cost pleted ($M) to (Acres) ($ M) (Acres) 31.3.63 Kwun Tong New Town 588.6 100.0 456.8 52.5 Remarks Valley Road 11.5 4.5 9.9 3.2 Waterloo Road Hill 9.2 5.0 9.2 2.4 Ho Man Tin Development 110.4 25.6 0.7 Development Area No. 3, Lung Area completed included 230 acres of reclamation out of a total of 270 acres. 8.4 acres for low cost housing. 3.1 acres for sale for private development. Sites for hotels, housing and schools. Sites for residential & community use. Site for low density residential use. Cheung Road 43.0 7.6 0.4 Kwai Chung North Sites for resettlement, Development low cost housing and Area 9 90.0 22.0 0.1 workers housing. Total 852.7 164.7 475.9 59.1 5.07. As a result of the exceptionally dry summer, good progress was maintained on all contracts. Kwun Tong New Town 5.08. The development of Kwun Tong New Town which started in 1955 is due for completion by 1968. During the year, with six formation contracts in progress, a total of 34.7 acres of reclamation and 55.5 acres of levelled building sites were formed. 33
2026-05-11 22:23:19 · Baseline
View content

5.05. As well as survey work for site investigation, this section provided the necessary control points (triangulation and traversing), the day to day 'setting out' work, contour plans and cross sections for earthwork quantity calculations and all the necessary interim, final and miscellaneous surveys demanded by the contract work.

SITE FORMATION

5.06. At the end of the year 13 contracts were in hand, excluding the work undertaken by Consulting Engineers at Kwai Chung. The following table summarizes the development schemes under con- struction:

Full scheme

Area

Expen-

Location

Área to

Estimated

Com-

diture

be formed

Cost

pleted

($M) to

(Acres)

($ M)

(Acres)

31.3.63

Kwun Tong New

Town

588.6

100.0

456.8

52.5

Remarks

Valley Road

11.5

4.5

9.9

3.2

Waterloo Road

Hill

9.2

5.0

9.2

2.4

Ho Man Tin

Development

110.4

25.6

0.7

Development Area

No. 3, Lung

Area completed included 230 acres of reclamation out of a total of 270

acres.

8.4 acres for low cost housing. 3.1 acres for sale for private development.

Sites for hotels, housing and schools.

Sites for residential & community use.

Site for low density residential use.

Cheung Road

43.0

7.6

0.4

Kwai Chung North

Sites for resettlement,

Development

low cost housing and

Area 9

90.0

22.0

0.1

workers housing.

Total

852.7

164.7

475.9

59.1

5.07. As a result of the exceptionally dry summer, good progress was maintained on all contracts.

Kwun Tong New Town

5.08. The development of Kwun Tong New Town which started in 1955 is due for completion by 1968. During the year, with six formation contracts in progress, a total of 34.7 acres of reclamation and 55.5 acres of levelled building sites were formed.

33