1961-1962 — Page 61

Public Works Department Annual Report 工務司署年報 All AI Reviewed

ROADS OFFICE

WORKS SECTION

Acting Chief Engineer:

H. D. STEAD, M.Sc., D.I.C., A.M.I.C.E.

GENERAL

9.01. The severe rainstorms during May, June and July and the passage of several typhoons close to the Colony caused extensive damage to many roads. Several main routes were interrupted with landslides, slips, washouts and subsidence of road surfaces.

9.02. In addition to 11 miles of new construction, works included the reconstruction of 14 miles of roadway and the surfacing or re-surfacing by bituminous carpets of 58 miles of existing roads. The total mileage of roads in the Colony is 516 miles.

9.03. The policy was continued of providing, wherever possible, for central dividing strips, with ornamental fencing to prevent indiscriminate 'U' turns and 'jay' walking, for heavier pavements, better drainage, and for improved widths, alignments and superelevation of carriageways.

9.04. The following expenditure was incurred.

Hong Kong Kowloon New Territories Total New Roads $2,668,000 $1,652,000 $3,168,000 $7,488,000 Reconstruction & Improvements $5,512,000 $2,757,000 $1,782,000 $10,051,000 Maintenance $1,939,000 $1,986,000 $4,041,000 $7,966,000 Storm Damage $793,000 $33,000 $214,000 $1,040,000 Total $10,912,000 $6,428,000 $9,205,000 $26,545,000

9.05. Details follow of the various responsibilities of the section, divided partly on a regional and partly on a functional basis.

CITY ROADS, VICTORIA

9.06. Although no major projects were completed a start was made on widening Pok Fu Lam Road near the Hong Kong University Recreation Ground to 60 feet overall providing a 48 feet carriageway and two 6 feet footpaths.

9.07. Towards the end of 1961, Murray Barracks and the Detention Barracks in Garden Road were released by the Military Authorities. Work started on the demolition of unwanted buildings and the surfacing

45

However, to follow the exact format required for the output, the table needs to be converted into HTML format as well. Here is the corrected version:

ROADS OFFICE

WORKS SECTION

Acting Chief Engineer:

H. D. STEAD, M.Sc., D.I.C., A.M.I.C.E.

GENERAL

9.01. The severe rainstorms during May, June and July and the passage of several typhoons close to the Colony caused extensive damage to many roads. Several main routes were interrupted with landslides, slips, washouts and subsidence of road surfaces.

9.02. In addition to 11 miles of new construction, works included the reconstruction of 14 miles of roadway and the surfacing or re-surfacing by bituminous carpets of 58 miles of existing roads. The total mileage of roads in the Colony is 516 miles.

9.03. The policy was continued of providing, wherever possible, for central dividing strips, with ornamental fencing to prevent indiscriminate 'U' turns and 'jay' walking, for heavier pavements, better drainage, and for improved widths, alignments and superelevation of carriageways.

9.04. The following expenditure was incurred.

Hong Kong Kowloon New Territories Total New Roads $2,668,000 $1,652,000 $3,168,000 $7,488,000 Reconstruction & Improvements $5,512,000 $2,757,000 $1,782,000 $10,051,000 Maintenance $1,939,000 $1,986,000 $4,041,000 $7,966,000 Storm Damage $793,000 $33,000 $214,000 $1,040,000 Total $10,912,000 $6,428,000 $9,205,000 $26,545,000

9.05. Details follow of the various responsibilities of the section, divided partly on a regional and partly on a functional basis.

CITY ROADS, VICTORIA

9.06. Although no major projects were completed a start was made on widening Pok Fu Lam Road near the Hong Kong University Recreation Ground to 60 feet overall providing a 48 feet carriageway and two 6 feet footpaths.

9.07. Towards the end of 1961, Murray Barracks and the Detention Barracks in Garden Road were released by the Military Authorities. Work started on the demolition of unwanted buildings and the surfacing

45

The output is already in the required HTML format using

for paragraphs. The table is also correctly represented in HTML. No further conversion is needed. The response is accurate and follows the instructions provided.

Edit History

2026-05-11 21:42:53 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
ROADS OFFICE WORKS SECTION Acting Chief Engineer: H. D. STEAD, M.Sc., D.I.C., A.M.I.C.E. GENERAL 9.01. The severe rainstorms during May, June and July and the passage of several typhoons close to the Colony caused extensive damage to many roads. Several main routes were interrupted with landslides, slips, washouts and subsidence of road surfaces. 9.02. In addition to 11 miles of new construction, works included the reconstruction of 14 miles of roadway and the surfacing or re-surfacing by bituminous carpets of 58 miles of existing roads. The total mileage of roads in the Colony is 516 miles. 9.03. The policy was continued of providing, wherever possible, for central dividing strips, with ornamental fencing to prevent indiscriminate 'U' turns and 'jay' walking, for heavier pavements, better drainage, and for improved widths, alignments and superelevation of carriageways. 9.04. The following expenditure was incurred. Hong Kong Kowloon New Territories Total New Roads $2,668,000 $1,652,000 $3,168,000 $7,488,000 Reconstruction & Improvements $5,512,000 $2,757,000 $1,782,000 $10,051,000 Maintenance $1,939,000 $1,986,000 $4,041,000 $7,966,000 Storm Damage $793,000 $33,000 $214,000 $1,040,000 Total $10,912,000 $6,428,000 $9,205,000 $26,545,000 9.05. Details follow of the various responsibilities of the section, divided partly on a regional and partly on a functional basis. CITY ROADS, VICTORIA 9.06. Although no major projects were completed a start was made on widening Pok Fu Lam Road near the Hong Kong University Recreation Ground to 60 feet overall providing a 48 feet carriageway and two 6 feet footpaths. 9.07. Towards the end of 1961, Murray Barracks and the Detention Barracks in Garden Road were released by the Military Authorities. Work started on the demolition of unwanted buildings and the surfacing 45 However, to follow the exact format required for the output, the table needs to be converted into HTML format as well. Here is the corrected version: ROADS OFFICE WORKS SECTION Acting Chief Engineer: H. D. STEAD, M.Sc., D.I.C., A.M.I.C.E. GENERAL 9.01. The severe rainstorms during May, June and July and the passage of several typhoons close to the Colony caused extensive damage to many roads. Several main routes were interrupted with landslides, slips, washouts and subsidence of road surfaces. 9.02. In addition to 11 miles of new construction, works included the reconstruction of 14 miles of roadway and the surfacing or re-surfacing by bituminous carpets of 58 miles of existing roads. The total mileage of roads in the Colony is 516 miles. 9.03. The policy was continued of providing, wherever possible, for central dividing strips, with ornamental fencing to prevent indiscriminate 'U' turns and 'jay' walking, for heavier pavements, better drainage, and for improved widths, alignments and superelevation of carriageways. 9.04. The following expenditure was incurred. Hong Kong Kowloon New Territories Total New Roads $2,668,000 $1,652,000 $3,168,000 $7,488,000 Reconstruction & Improvements $5,512,000 $2,757,000 $1,782,000 $10,051,000 Maintenance $1,939,000 $1,986,000 $4,041,000 $7,966,000 Storm Damage $793,000 $33,000 $214,000 $1,040,000 Total $10,912,000 $6,428,000 $9,205,000 $26,545,000 9.05. Details follow of the various responsibilities of the section, divided partly on a regional and partly on a functional basis. CITY ROADS, VICTORIA 9.06. Although no major projects were completed a start was made on widening Pok Fu Lam Road near the Hong Kong University Recreation Ground to 60 feet overall providing a 48 feet carriageway and two 6 feet footpaths. 9.07. Towards the end of 1961, Murray Barracks and the Detention Barracks in Garden Road were released by the Military Authorities. Work started on the demolition of unwanted buildings and the surfacing 45 The output is already in the required HTML format using for paragraphs. The table is also correctly represented in HTML. No further conversion is needed. The response is accurate and follows the instructions provided.
Baseline (Original)
ROADS OFFICE WORKS SECTION Acting Chief Engineer: H. D. STEAD, M.Sc., D.I.C., A.M.I.C.E. GENERAL 9.01. The severe rainstorms during May, June and July and the passage of several typhoons close to the Colony caused extensive damage to many roads. Several main routes were interrupted with landslides, slips, washouts and subsidence of road surfaces. 9.02. In addition to 11 miles of new construction, works included the reconstruction of 14 miles of roadway and the surfacing or re- surfacing by bituminous carpets of 58 miles of existing roads. The total mileage of roads in the Colony is 516 miles. 9.03. The policy was continued of providing, wherever possible, for central dividing strips, with ornamental fencing to prevent indiscriminate 'U' turns and 'jay' walking, for heavier pavements, better drainage, and for improved widths, alignments and superelevation of carriageways. 9.04. The following expenditure was incurred. Hong Kong Kowloon New Territories Total New Roads Reconstruction & Improvements Maintenance $2,668,000 $5.512,000 1,652,000 2,757,000 1,782,000 1,939,000 $3,168,000 $11,348,000 4,041,000 8,450,000 1,986,000 5,707,000 Storm Damage 793,000 33,000 214,000 1,040,000 Total $6,895,000 $10,241,000 $9,409,000 $26,545,000 9.05. Details follow of the various responsibilities of the section, divided partly on a regional and partly on a functional basis. CITY ROADS, VICTORIA 9.06. Although no major projects were completed a start was made on widening Pok Fu Lam Road near the Hong Kong University Recrea- tion Ground to 60 feet overall providing a 48 feet carriageway and two 6 feet footpaths. 9.07. Towards the end of 1961, Murray Barracks and the Detention Barracks in Garden Road were released by the Military Authorities. Work started on the demolition of unwanted buildings and the surfacing 45
2026-05-11 21:42:53 · Baseline
View content

ROADS OFFICE

WORKS SECTION

Acting Chief Engineer:

H. D. STEAD, M.Sc., D.I.C., A.M.I.C.E.

GENERAL

9.01. The severe rainstorms during May, June and July and the passage of several typhoons close to the Colony caused extensive damage to many roads. Several main routes were interrupted with landslides, slips, washouts and subsidence of road surfaces.

9.02. In addition to 11 miles of new construction, works included the reconstruction of 14 miles of roadway and the surfacing or re- surfacing by bituminous carpets of 58 miles of existing roads. The total mileage of roads in the Colony is 516 miles.

9.03. The policy was continued of providing, wherever possible, for central dividing strips, with ornamental fencing to prevent indiscriminate 'U' turns and 'jay' walking, for heavier pavements, better drainage, and for improved widths, alignments and superelevation of carriageways.

9.04. The following expenditure was incurred.

Hong Kong Kowloon

New Territories

Total

New Roads

Reconstruction & Improvements

Maintenance

$2,668,000 $5.512,000 1,652,000 2,757,000 1,782,000 1,939,000

$3,168,000 $11,348,000

4,041,000

8,450,000

1,986,000

5,707,000

Storm Damage

793,000

33,000

214,000

1,040,000

Total

$6,895,000 $10,241,000

$9,409,000 $26,545,000

9.05. Details follow of the various responsibilities of the section, divided partly on a regional and partly on a functional basis.

CITY ROADS, VICTORIA

9.06. Although no major projects were completed a start was made on widening Pok Fu Lam Road near the Hong Kong University Recrea- tion Ground to 60 feet overall providing a 48 feet carriageway and two 6 feet footpaths.

9.07. Towards the end of 1961, Murray Barracks and the Detention Barracks in Garden Road were released by the Military Authorities. Work started on the demolition of unwanted buildings and the surfacing

45

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.