water during the winter, both being produced by the same plant; the heat being rejected to or extracted from seawater pumped from the harbour.

7.12. Among the projects still under construction were two of the largest yet undertaken by Government; that for the Queen Elizabeth Hospital will have a plant capacity of 1,500 tons, and that at Kai Tak Air Terminal Building 1,000 tons. The main refrigeration plant at Queen Elizabeth Hospital is of particular interest as the main compressor sets are to be steam turbine driven centrifugal units and these will be the first of their kind in the Colony.

7.22. Private architects engaged on Government projects continued to call on the services of the Section for the design, specification, and supervision of air-conditioning installations. Two installations of this category were completed during the year with a combined capacity of 807 tons refrigeration, and a further 4 schemes were in progress with a total capacity of 1,274 tons of refrigeration.

7.23. The increased use of air-conditioning and refrigeration plant and equipment is illustrated in the following comparative figures for the last four years:

1958-59 1959-60 1960-61 1961-62 Air-conditioning plant 61 69 82 93 Total capacity of above in tons of refrigeration 1,100 1,515 2,597 Room air coolers in use 301 467 652 841 Refrigerators in use 1,714 1,883 2,230 3,648 Cold stores and mortuaries 6 8 11 11

7.24. The task of maintaining this plant and equipment in efficient running order was carried out by staff from the workshops whose operations for the year embraced 902 overhaul tasks, 14,928 maintenance visits, and attendance to 1,700 fault calls. The air-conditioning and refrigeration workshops also carried out the complete re-installation of the air-conditioning system at Government House as well as 15 minor installations during the year. 254 new refrigerators were installed and 459 items of electrical appliances and equipment tested.

ELECTRICAL SECTION

7.25. The number of orders executed by this Section rose by 27.5% to 37,607.

7.26. A large number of new traffic aids were installed, including 16 sets of duplicate traffic signals, 3 sets of pedestrian operated traffic signals...

has been revised to

water during the winter, both being produced by the same plant; the heat being rejected to or extracted from seawater pumped from the harbour.

7.12. Among the projects still under construction were two of the largest yet undertaken by Government; that for the Queen Elizabeth Hospital will have a plant capacity of 1,500 tons, and that at Kai Tak Air Terminal Building 1,000 tons. The main refrigeration plant at Queen Elizabeth Hospital is of particular interest as the main compressor sets are to be steam turbine driven centrifugal units and these will be the first of their kind in the Colony.

7.22. Private architects engaged on Government projects continued to call on the services of the Section for the design, specification, and supervision of air-conditioning installations. Two installations of this category were completed during the year with a combined capacity of 807 tons refrigeration, and a further 4 schemes were in progress with a total capacity of 1,274 tons of refrigeration.

7.23. The increased use of air-conditioning and refrigeration plant and equipment is illustrated in the following comparative figures for the last four years:

1958-59 1959-60 1960-61 1961-62 Air-conditioning plant 61 69 82 93 Total capacity of above in tons of refrigeration 1,100 1,515 2,597 3648 Room air coolers in use 301 467 652 841 Refrigerators in use 1,714 1,883 2,230 2,574 Cold stores and mortuaries 6 8 11 11

7.24. The task of maintaining this plant and equipment in efficient running order was carried out by staff from the workshops whose operations for the year embraced 902 overhaul tasks, 14,928 maintenance visits, and attendance to 1,700 fault calls. The air-conditioning and refrigeration workshops also carried out the complete re-installation of the air-conditioning system at Government House as well as 15 minor installations during the year. 254 new refrigerators were installed and 459 items of electrical appliances and equipment tested.

ELECTRICAL SECTION

7.25. The number of orders executed by this Section rose by 27.5% to 37,607.

7.26. A large number of new traffic aids were installed, including 16 sets of duplicate traffic signals, 3 sets of pedestrian operated traffic signals

38

Edit History

2026-05-11 21:38:13 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
water during the winter, both being produced by the same plant; the heat being rejected to or extracted from seawater pumped from the harbour. 7.12. Among the projects still under construction were two of the largest yet undertaken by Government; that for the Queen Elizabeth Hospital will have a plant capacity of 1,500 tons, and that at Kai Tak Air Terminal Building 1,000 tons. The main refrigeration plant at Queen Elizabeth Hospital is of particular interest as the main compressor sets are to be steam turbine driven centrifugal units and these will be the first of their kind in the Colony. 7.22. Private architects engaged on Government projects continued to call on the services of the Section for the design, specification, and supervision of air-conditioning installations. Two installations of this category were completed during the year with a combined capacity of 807 tons refrigeration, and a further 4 schemes were in progress with a total capacity of 1,274 tons of refrigeration. 7.23. The increased use of air-conditioning and refrigeration plant and equipment is illustrated in the following comparative figures for the last four years: 1958-59 1959-60 1960-61 1961-62 Air-conditioning plant 61 69 82 93 Total capacity of above in tons of refrigeration 1,100 1,515 2,597 Room air coolers in use 301 467 652 841 Refrigerators in use 1,714 1,883 2,230 3,648 Cold stores and mortuaries 6 8 11 11 7.24. The task of maintaining this plant and equipment in efficient running order was carried out by staff from the workshops whose operations for the year embraced 902 overhaul tasks, 14,928 maintenance visits, and attendance to 1,700 fault calls. The air-conditioning and refrigeration workshops also carried out the complete re-installation of the air-conditioning system at Government House as well as 15 minor installations during the year. 254 new refrigerators were installed and 459 items of electrical appliances and equipment tested. ELECTRICAL SECTION 7.25. The number of orders executed by this Section rose by 27.5% to 37,607. 7.26. A large number of new traffic aids were installed, including 16 sets of duplicate traffic signals, 3 sets of pedestrian operated traffic signals... has been revised to water during the winter, both being produced by the same plant; the heat being rejected to or extracted from seawater pumped from the harbour. 7.12. Among the projects still under construction were two of the largest yet undertaken by Government; that for the Queen Elizabeth Hospital will have a plant capacity of 1,500 tons, and that at Kai Tak Air Terminal Building 1,000 tons. The main refrigeration plant at Queen Elizabeth Hospital is of particular interest as the main compressor sets are to be steam turbine driven centrifugal units and these will be the first of their kind in the Colony. 7.22. Private architects engaged on Government projects continued to call on the services of the Section for the design, specification, and supervision of air-conditioning installations. Two installations of this category were completed during the year with a combined capacity of 807 tons refrigeration, and a further 4 schemes were in progress with a total capacity of 1,274 tons of refrigeration. 7.23. The increased use of air-conditioning and refrigeration plant and equipment is illustrated in the following comparative figures for the last four years: 1958-59 1959-60 1960-61 1961-62 Air-conditioning plant 61 69 82 93 Total capacity of above in tons of refrigeration 1,100 1,515 2,597 3648 Room air coolers in use 301 467 652 841 Refrigerators in use 1,714 1,883 2,230 2,574 Cold stores and mortuaries 6 8 11 11 7.24. The task of maintaining this plant and equipment in efficient running order was carried out by staff from the workshops whose operations for the year embraced 902 overhaul tasks, 14,928 maintenance visits, and attendance to 1,700 fault calls. The air-conditioning and refrigeration workshops also carried out the complete re-installation of the air-conditioning system at Government House as well as 15 minor installations during the year. 254 new refrigerators were installed and 459 items of electrical appliances and equipment tested. ELECTRICAL SECTION 7.25. The number of orders executed by this Section rose by 27.5% to 37,607. 7.26. A large number of new traffic aids were installed, including 16 sets of duplicate traffic signals, 3 sets of pedestrian operated traffic signals38
Baseline (Original)
water during the winter, both being produced by the same plant; the heat being rejected to or extracted from seawater puinped from the harbour. 7.12. Among the projects still under construction were two of the largest yet undertaken by Government; that for the Queen Elizabeth Hospital will have a plant capacity of 1,500 tons, and that at Kai Tak Air Terminal Building 1,000 tons. The main refrigeration plant at Queen Elizabeth Hospital is of particular interest as the main compressor sets are to be steam turbine driven centrifugal units and these will be the first of their kind in the Colony. 7.22. Private architects engaged on Government projects continued to call on the services of the Section for the design, specification, and supervision of air-conditioning installations. Two installations of this category were completed during the year with a combined capacity of 807 tons refrigeration, and a further 4 schemes were in progress with a total capacity of 1,274 tons of refrigeration. 7.23. The increased use of air-conditioning and refrigeration plant and equipment is illustrated in the following comparative figures for the last four years: 1958-59 1959-60 Air-conditioning plant 61 69 1960-61 82 1961-62 93 Total capacity of above in tons of refrigeration 1,100 1,515 2,597 Room air coolers in use 301 467 652 3,648 841 Refrigerators in use 1,714 Cold stores and mortuaries 6 1,883 8 2,230 2,574 11 11 7.24. The task of maintaining this plant and equipment in efficient running order was carried out by staff from the workshops whose operations for the year embraced 902 overhaul tasks, 14,928 maintenance visits, and attendance to 1,700 fault calls. The air-conditioning and refrigeration workshops also carried out the complete re-installation of the air-conditioning system at Government House as well as 15 minor installations during the year. 254 new refrigerators were installed and 459 items of electrical applicances and equipment tested. ELECTRICAL SECTION 7.25. The number of orders executed by this Section rose by 27.5% to 37,607. 7.26. A large number of new traffic aids were installed, including 16 sets of duplicate traffic signals, 3 sets of pedestrian operated traffic 38
2026-05-11 21:38:13 · Baseline
View content

water during the winter, both being produced by the same plant; the heat being rejected to or extracted from seawater puinped from the harbour.

7.12. Among the projects still under construction were two of the largest yet undertaken by Government; that for the Queen Elizabeth Hospital will have a plant capacity of 1,500 tons, and that at Kai Tak Air Terminal Building 1,000 tons. The main refrigeration plant at Queen Elizabeth Hospital is of particular interest as the main compressor sets are to be steam turbine driven centrifugal units and these will be the first of their kind in the Colony.

7.22. Private architects engaged on Government projects continued to call on the services of the Section for the design, specification, and supervision of air-conditioning installations. Two installations of this category were completed during the year with a combined capacity of 807 tons refrigeration, and a further 4 schemes were in progress with a total capacity of 1,274 tons of refrigeration.

7.23. The increased use of air-conditioning and refrigeration plant and equipment is illustrated in the following comparative figures for the last four years:

1958-59

1959-60

Air-conditioning plant

61

69

1960-61

82

1961-62

93

Total capacity of above in tons of

refrigeration

1,100

1,515

2,597

Room air coolers in use

301

467

652

3,648 841

Refrigerators in use

1,714

Cold stores and mortuaries

6

1,883 8

2,230

2,574

11

11

7.24. The task of maintaining this plant and equipment in efficient running order was carried out by staff from the workshops whose operations for the year embraced 902 overhaul tasks, 14,928 maintenance visits, and attendance to 1,700 fault calls. The air-conditioning and refrigeration workshops also carried out the complete re-installation of the air-conditioning system at Government House as well as 15 minor installations during the year. 254 new refrigerators were installed and 459 items of electrical applicances and equipment tested.

ELECTRICAL SECTION

7.25. The number of orders executed by this Section rose by 27.5% to 37,607.

7.26. A large number of new traffic aids were installed, including 16 sets of duplicate traffic signals, 3 sets of pedestrian operated traffic