of service flats, and the Ede Road site with 72 Type III quarters and Magazine Gap with 96 Type II quarters.
Western District Magistracy
2.75. Working drawings for this scheme, consisting of a Magistracy on the lower floors and Government offices above, were nearing completion.
Beaconsfield Arcade
2.76. This building will accommodate the various clubs connected with the volunteer uniformed services which are now scattered over various parts of the City. Demolition and site formation were completed and tenders called for the building.
Workshops and Offices
2.77. A large stores and workshops building was under construction at Kai Tak Airport and will provide rented accommodation for the various airlines.
2.78. Piling was completed for Electrical & Mechanical Workshops, Kowloon, and tenders called for construction of the building.
2.79. Working drawings were in hand for the multi-storey Electrical and Mechanical Workshop and Office Block at Caroline Hill. This scheme also includes some departmental quarters and accommodation for the Civil Aid Services and depots for the Roads and Drainage Offices.
2.80. Satisfactory progress was maintained on the construction of the new Government Offices at Kwun Tong, which are now required to house those departments directly connected with the management of this new area.
Kai Tak Airport Terminal Building
2.81. Construction of the Terminal Building was slightly behind schedule and further delay was expected due to late delivery of special equipment.
MAINTENANCE SECTION
Maintenance of Government Buildings
2.82. Routine maintenance programmes were carried out on 214 Government and Government leased buildings. The total expenditure on maintenance of all buildings amounted to $6,546,000 an increase of $2,506,000 on the previous year.
14
of service flats, and the Ede Road site with 72 Type III quarters and Magazine Gap with 96 Type II quarters.
Western District Magistracy
2.75. Working drawings for this scheme, consisting of a Magistracy on the lower floors and Government offices above, were nearing completion.
Beaconsfield Arcade
2.76. This building will accommodate the various clubs connected with the volunteer uniformed services which are now scattered over various parts of the City. Demolition and site formation were completed and tenders called for the building.
Workshops and Offices
2.77. A large stores and workshops building was under construction at Kai Tak Airport and will provide rented accommodation for the various airlines.
2.78. Piling was completed for Electrical & Mechanical Workshops, Kowloon, and tenders called for construction of the building.
2.79. Working drawings were in hand for the multi-storey Electrical and Mechanical Workshop and Office Block at Caroline Hill. This scheme also includes some departmental quarters and accommodation for the Civil Aid Services and depots for the Roads and Drainage Offices.
2.80. Satisfactory progress was maintained on the construction of the new Government Offices at Kwun Tong, which are now required to house those departments directly connected with the management of this new area.
Kai Tak Airport Terminal Building
2.81. Construction of the Terminal Building was slightly behind schedule and further delay was expected due to late delivery of special equipment.
MAINTENANCE SECTION
Maintenance of Government Buildings
2.82. Routine maintenance programmes were carried out on 214 Government and Government leased buildings. The total expenditure on maintenance of all buildings amounted to $6,546,000 an increase of $2,506,000 on the previous year.
14
of service flats, and the Ede Road site with 72 Type III quarters and Magazine Gap with 96 Type II quarters.
Western District Magistracy
2.75. Working drawings for this scheme, consisting of a Magistracy on the lower floors and Government offices above, were nearing completion.
Beaconsfield Arcade
2.76. This building will accommodate the various clubs connected with the volunteer uniformed services which are now scattered over various parts of the City. Demolition and site formation were completed and tenders called for the building.
Workshops and Offices
2.77. A large stores and workshops building was under construction at Kai Tak Airport and will provide rented accommodation for the various airlines.
2.78. Piling was completed for Electrical & Mechanical Workshops, Kowloon, and tenders called for construction of the building.
2.79. Working drawings were in hand for the multi-storey Electrical and Mechanical Workshop and Office Block at Caroline Hill. This scheme also includes some departmental quarters and accommodation for the Civil Aid Services and depots for the Roads and Drainage Offices.
2.80. Satisfactory progress was maintained on the construction of the new Government Offices at Kwun Tong, which are now required to house those departments directly connected with the management of this new area.
Kai Tak Airport Terminal Building
2.81. Construction of the Terminal Building was slightly behind schedule and further delay was expected due to late delivery of special equipment.
MAINTENANCE SECTION
Maintenance of Government Buildings
2.82. Routine maintenance programmes were carried out on 214 Government and Government leased buildings. The total expenditure on maintenance of all buildings amounted to $6,546,000 an increase of $2,506,000 on the previous year.
14