(4) Wong Tai Sin (Area D): construction of the last two blocks in this estate was nearing completion.
(5) Wang Tau Hom: site formation and piling for the 25 blocks in this estate were well advanced.
(6) Tai Wo Hau (Stage II): site formation and piling for the six blocks in this estate were nearing completion, and construction of three blocks was commenced.
(7) Lo Fu Ngam (Stage III): site formation and piling for the eleven blocks in this estate were well advanced and construction of two blocks was commenced.
(8) Tsuen Wan: piling was completed and construction of a special silk weaving factory was commenced.
(9) Tze Wan Shan: site formation for this estate of 105 blocks of the new (Mark III) design, was commenced under two separate contracts.
(10) San Po Kong: piling work commenced on the four five-storey factories in this project, which are each similar to the silk weaving factory at Tsuen Wan. Construction of one factory was also commenced.
(11) Aberdeen (Tin Wan): site formation for the 16 blocks (Mark III) in this estate was commenced.
Drawings and Plans under preparation
2.54. Contract drawings were in course of preparation to enable work to commence during the coming year on the following:
(1) Wang Tau Hom (Phase II): an estate containing 13 domestic blocks.
(2) Tsz Wan Shan: an estate containing 105 Mark III domestic blocks.
(3) Yau Tong Bay: revised to provide 21 Mark III domestic blocks.
(4) Shek Kip Mei: one additional domestic block.
Sketch plans were under preparation for resettlement estates at So Mo Ping, Aberdeen (Site 2), Kwai Chung, North, and Chai Wan (Stage III).
Resettlement Department Staff Quarters
2.55.
(1) Kwun Tong: construction of the 14 quarters was completed.
(2) Wong Tai Sin piling work was completed and construction of the 60 quarters progressed well.
(3) Tai Wo Hau: site formation and piling were completed and construction of the 13 quarters was commenced.
(4) Chai Wan: construction of the 9 quarters was well in hand.
2.56. GOVERNMENT LOW COST HOUSING
Construction of the first low cost housing estate of seven blocks at Kwun Tong was commenced providing accommodation for about 6,000 persons in single living units. A start was made on site formation for two further estates and piling commenced on a third estate. These will provide homes for about 30,000 persons.
Page 21
was replaced with the following to adhere to the page numbering rule:` for paragraphs, the corrected response is provided directly above.
Pa 21
(4) Wong Tai Sin (Area D): construction of the last two blocks in this
estate was nearing completion.
(5) Wang Tau Hom: site formation and piling for the 25 blocks in this
estate were well advanced.
(6) Tai Wo Hau (Stage II): site formation and piling for the six blocks in this estate were nearing completion, and construction of three blocks was commenced.
(7) Lo Fu Ngam (Stage III): site formation and piling for the eleven blocks in this estate were well advanced and construction of two blocks was commenced.
(8) Tsuen Wan: piling was completed and construction of a special silk
weaving factory was commenced.
(9) Tze Wan Shan: site formation for this estate of 105 blocks of the new (Mark III) design, was commenced under two separate
contracts.
(10) San Po Kong: piling work commenced on the four five-storey factories in this project, which are each similar to the silk weaving factory at Tsuen Wan. Construction of one factory was also commenced. (11) Aberdeen (Tin Wan): site formation for the 16 blocks (Mark III) in
this estate was commenced.
Drawings and Plans under preparation
2.54.
Contract drawings were in course of preparation to enable work to commence during the coming year on the following:
(1) Wang Tau Hom (Phase II): an estate containing 13 domestic blocks. (2) Tsz Wan Shan: an estate containing 105 Mark III domestic blocks. (3) Yau Tong Bay: revised to provide 21 Mark III domestic blocks. (4) Shek Kip Mei: one additional domestic block.
Sketch plans were under preparation for resettlement estates at So Mo Ping, Aberdeen (Site 2), Kwai Chung, North, and Chai Wan (Stage III).
Resettlement Department Staff Quarters
2.55.
(1) Kwun Tong: construction of the 14 quarters was completed.
(2) Wong Tai Sin piling work was completed and construction of the 60
quarters progressed well.
(3) Tai Wo Hau: site formation and piling were completed and construc-
tion of the 13 quarters was commenced.
(4) Chai Wan: construction of the 9 quarters was well in hand.
2.56.
GOVERNMENT LOW COST HOUSING
Construction of the first low cost housing estate of seven blocks at Kwun Tong was commenced providing accommodation for about 6,000 persons in single living units. A start was made on site formation for two further estates and piling commenced on a third estate. These will provide homes for about 30,000 persons.