1960-1961 — Page 82

Public Works Department Annual Report 工務司署年報 All AI Reviewed

(2) Yau Tong Road—900 feet of 18" main to extend the Kwun Tong distribution system.

(3) Prince Edward Road—610 feet of 18" main laid at Kowloon City Roundabout to improve distribution.

(4) Cheung Sha Wan Road and Lai Chi Kok Road—2,500 feet of new 12" main as an extension to item (1) above.

(5) Waterloo Road—2,400 feet of 10" pipe in replacement of undersized 6" pipe.

(6) Resettlement Estates—Approximately 8,000 feet of cast iron and asbestos cement fresh and salt water mains varying from 4" to 8" diameter.

(7) Tsuen Wan—10,300 feet of mains from 6" to 15" diameter.

(8) Fanling—400 feet of 8" and 1,900 feet of 6" for the new principal feed to the area.

(9) Tai Po Kau—Tai Po Market—900 feet of 6" and 480 feet of 8" to complete work started last year.

Service Reservoirs

321. All service reservoirs were cleaned and sterilized, their inlet and outlet valves were tested and where necessary overhauled.

322. Fresh water service reservoirs at Tai Po Road and Kau Wah Keng in Kowloon were completed and those at King's Park and North Point were sufficiently completed for one half to be brought into commission while work on the remaining half proceeded.

323. The salt water service reservoir at Piper's Hill was commissioned.

Catchwaters

324. The usual troubles from blocked catchwaters due to landslips following heavy summer rains were experienced, but no major damage was sustained, clearance being effected in time to avoid serious loss of inflow to the reservoirs.

325. Major blockages occurred in the Tai Tam group of catchwaters, and in the Jubilee catchwaters where reconstruction of a section became necessary. Improvements carried out in 1959-60 proved their worth and undoubtedly prevented further major damage.

326. Flood diversion gates were installed on some of the new Tai Lam Chung catchwaters.

Tsuen Wan and Kwun Tong Supplies

327. To meet new development, extension of the distribution systems continued in conjunction with the formation of roads,


Page 62

Edit History

2026-05-11 21:18:34 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
(2) Yau Tong Road—900 feet of 18" main to extend the Kwun Tong distribution system. (3) Prince Edward Road—610 feet of 18" main laid at Kowloon City Roundabout to improve distribution. (4) Cheung Sha Wan Road and Lai Chi Kok Road—2,500 feet of new 12" main as an extension to item (1) above. (5) Waterloo Road—2,400 feet of 10" pipe in replacement of undersized 6" pipe. (6) Resettlement Estates—Approximately 8,000 feet of cast iron and asbestos cement fresh and salt water mains varying from 4" to 8" diameter. (7) Tsuen Wan—10,300 feet of mains from 6" to 15" diameter. (8) Fanling—400 feet of 8" and 1,900 feet of 6" for the new principal feed to the area. (9) Tai Po Kau—Tai Po Market—900 feet of 6" and 480 feet of 8" to complete work started last year. Service Reservoirs 321. All service reservoirs were cleaned and sterilized, their inlet and outlet valves were tested and where necessary overhauled. 322. Fresh water service reservoirs at Tai Po Road and Kau Wah Keng in Kowloon were completed and those at King's Park and North Point were sufficiently completed for one half to be brought into commission while work on the remaining half proceeded. 323. The salt water service reservoir at Piper's Hill was commissioned. Catchwaters 324. The usual troubles from blocked catchwaters due to landslips following heavy summer rains were experienced, but no major damage was sustained, clearance being effected in time to avoid serious loss of inflow to the reservoirs. 325. Major blockages occurred in the Tai Tam group of catchwaters, and in the Jubilee catchwaters where reconstruction of a section became necessary. Improvements carried out in 1959-60 proved their worth and undoubtedly prevented further major damage. 326. Flood diversion gates were installed on some of the new Tai Lam Chung catchwaters. Tsuen Wan and Kwun Tong Supplies 327. To meet new development, extension of the distribution systems continued in conjunction with the formation of roads, Page 62
Baseline (Original)
(2) Yau Tong Road-900 feet of 18" main to extend the Kwun Tong distribution system. (3) Prince Edward Road-610 feet of 18" main laid at Kowloon City Roundabout to improve distribution. (4) Cheung Sha Wan Road and Lai Chi Kok Road--2,500 feet of new 12" main as an extension to item (1) above. (5) Waterloo Road-2,400 feet of 10" pipe in replacement of undersized 6" pipe. (6) Resettlement Estates-Approximately 8,000 feet of cast iron and asbestos cement fresh and salt water mains varying from 4" to 8" diameter. (7) Tsuen Wan-10,300 feet of mains from 6" to 15" diameter. (8) Fanling-400 feet of 8′′ and 1,900 feet of 6" for the new principal feed to the area. (9) Tai Po Kau-Tai Po Market-900 feet of 6" and 480 feet of 8" to complete work started last year. Service Reservoirs 321. All service reservoirs were cleaned and sterilized, their inlet and outlet valves were tested and where necessary overhauled. 322. Fresh water service reservoirs at Tai Po Road and Kau Wah Keng in Kowloon were completed and those at King's Park and North Point were sufficiently completed for one half to be brought into com- mission while work on the remaining half proceeded. 323. The salt water service reservoir at Piper's Hill was commis- sioned. Catchwaters 324. The usual troubles from blocked catchwaters due to landslips following heavy summer rains were experienced, but no major damage was sustained, clearance being effected in time to avoid serious loss of inflow to the reservoirs. 325. Major blockages occurred in the Tai Tam group of catchwaters, and in the Jubilee catchwaters where reconstruction of a section became necessary. Improvements carried out in 1959-60 proved their worth and undoubtedly prevented further major damage. 326. Flood diversion gates were installed on some of the new Tai Lam Chung catchwaters. Tsuen Wan and Kwun Tong Supplies 327. To meet new development, extension of the distribution systems continued in conjunction with the formation of roads, 62
2026-05-11 21:18:34 · Baseline
View content

(2) Yau Tong Road-900 feet of 18" main to extend the Kwun Tong

distribution system.

(3) Prince Edward Road-610 feet of 18" main laid at Kowloon City

Roundabout to improve distribution.

(4) Cheung Sha Wan Road and Lai Chi Kok Road--2,500 feet of new

12" main as an extension to item (1) above.

(5) Waterloo Road-2,400 feet of 10" pipe in replacement of undersized

6" pipe.

(6) Resettlement Estates-Approximately 8,000 feet of cast iron and asbestos cement fresh and salt water mains varying from 4" to 8" diameter.

(7) Tsuen Wan-10,300 feet of mains from 6" to 15" diameter.

(8) Fanling-400 feet of 8′′ and 1,900 feet of 6" for the new principal

feed to the area.

(9) Tai Po Kau-Tai Po Market-900 feet of 6" and 480 feet of 8"

to complete work started last year.

Service Reservoirs

321. All service reservoirs were cleaned and sterilized, their inlet and outlet valves were tested and where necessary overhauled.

322. Fresh water service reservoirs at Tai Po Road and Kau Wah Keng in Kowloon were completed and those at King's Park and North Point were sufficiently completed for one half to be brought into com- mission while work on the remaining half proceeded.

323. The salt water service reservoir at Piper's Hill was commis- sioned.

Catchwaters

324. The usual troubles from blocked catchwaters due to landslips following heavy summer rains were experienced, but no major damage was sustained, clearance being effected in time to avoid serious loss of inflow to the reservoirs.

325. Major blockages occurred in the Tai Tam group of catchwaters, and in the Jubilee catchwaters where reconstruction of a section became necessary. Improvements carried out in 1959-60 proved their worth and undoubtedly prevented further major damage.

326. Flood diversion gates were installed on some of the new Tai Lam Chung catchwaters.

Tsuen Wan and Kwun Tong Supplies

327. To meet new development, extension of the distribution systems continued in conjunction with the formation of roads,

62

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.