Secondary Schools
28. The sketch plans for a new standard 24-classroom Government secondary school for 920 pupils in one session were approved and a start was made on working drawings.
Northcote Teachers' Training College (Replacement)
29. Immediately following completion of the site formation, which included retaining walls and some foundation work, in December 1960, a building contract was let and is expected to take fourteen months to complete. The College, which is described in detail in last year's report, is intended to accommodate 400 students, 200 of whom will be resident in a hostel within the grounds. Quarters for four wardens are also included.
MEDICAL BUILDINGS
Castle Peak Mental Hospital
30. The formal opening of the hospital by His Excellency the Governor took place on 27th March. This marked the completion of the project which provides 1,000 beds and includes ancillary buildings and quarters for all the staff.
Queen Elizabeth Hospital
31. After the completion of the Sisters' and Nurses' Quarters, His Excellency the Governor performed the formal opening ceremony.
32. On completion of the basement structure for the main hospital building in January 1961, tenders were invited for construction of the superstructure.
33. Sketch plans were approved for hostel accommodation for some 130 House Officers, Senior Officers, Male Nurses and Dressers to be built on the same site as the non-departmental quarters in Wylie Road.
Kowloon General Hospital
34. A new operating theatre and ward building together with a new central kitchen block, a staff recreation centre and two single-storey ward blocks for children were completed at the Kowloon General Hospital.
Queen Mary Hospital
35. Sketch plans were in course of preparation for a large extension which will accommodate operating theatres, pharmacies, central sterilizing and radio diagnosis sections.
10
Secondary Schools
28. The sketch plans for a new standard 24-classroom Government secondary school for 920 pupils in one session were approved and a start was made on working drawings.
Northcote Teachers' Training College (Replacement)
29. Immediately following completion of the site formation, which included retaining walls and some foundation work, in December 1960, a building contract was let and is expected to take fourteen months to complete. The College, which is described in detail in last year's report, is intended to accommodate 400 students, 200 of whom will be resident in a hostel within the grounds. Quarters for four wardens are also included.
MEDICAL BUILDINGS
Castle Peak Mental Hospital
30. The formal opening of the hospital by His Excellency the Governor took place on 27th March. This marked the completion of the project which provides 1,000 beds and includes ancillary buildings and quarters for all the staff.
Queen Elizabeth Hospital
31. After the completion of the Sisters' and Nurses' Quarters, His Excellency the Governor performed the formal opening ceremony.
32. On completion of the basement structure for the main hospital building in January 1961, tenders were invited for construction of the superstructure.
33. Sketch plans were approved for hostel accommodation for some 130 House Officers, Senior Officers, Male Nurses and Dressers to be built on the same site as the non-departmental quarters in Wylie Road.
Kowloon General Hospital
34. A new operating theatre and ward building together with a new central kitchen block, a staff recreation centre and two single-storey ward blocks for children were completed at the Kowloon General Hospital.
Queen Mary Hospital
35. Sketch plans were in course of preparation for a large extension which will accommodate operating theatres, pharmacies, central steriliz- ing and radio diagnosis sections.