270. A start was made on the roundabout at the junction of Chatham Road and Gascoigne Road. The roundabout is planned in stages and will be able, eventually, to accommodate the extension of Nairn Road.
271. The work of widening and forming Castle Peak Road between the hospital and Lai Chi Kok Gap into a dual carriageway was practically completed and a separate contract was let for concrete surfacing. Ma Tau Wei Road was also partly reconstructed in concrete with dual carriageways and a service road.
272. A comprehensive programme of maintenance and resurfacing was successfully executed, much of it in conjunction with the restoration of roads damaged in rainstorms.
NEW TERRITORIES ROADS
273. A considerable number of new feeder roads were built in the New Territories to provide access to outlying districts. The most important of these were the road linking Luk Keng Village with the Sha Tau Kok Road, extensions of the Ping Tse feeder road to Ta Kwu Ling and of the road from Ting Kok to Tai Mei Tuk which is to form the main access to the Plover Cove water supply scheme. Yet another feeder road was constructed from Sai Kung to Tai Mong Tsai.
274. On the south coast of Lantao the 10-foot road was extended 4½ miles from Cheung Sha to Shek Pik and work was initiated on the widening of the 4-mile section between Silvermine Bay and Cheung Sha.
275. Portions of the Castle Peak and Tai Po Roads were resurfaced. The latter road was completely washed out in many places in June and it took several months to repair the damage.
276. Major works undertaken included the first stage in the widening of Tsing Lung Tau causeway, the improvement and surfacing of Anderson Road from its junction with Clearwater Bay Road to Po Lam Road, the reconstruction and widening to dual carriageways of part of Texaco Road, improvements incorporating a second carriageway to Castle Peak Road between Kwai Chung and Chai Wan Kok.
277. The first stage of widening Hiram's Highway from Clearwater Bay Road to Ho Chung was completed and work well advanced on the second stage between Ho Chung and Sai Kung.
48
Page 60
Page 61
270. A start was made on the roundabout at the junction of Chatham Road and Gascoigne Road. The roundabout is planned in stages and will be able, eventually, to accommodate the extension of Nairn Road.
271. The work of widening and forming Castle Peak Road between the hospital and Lai Chi Kok Gap into a dual carriageway was practically completed and a separate contract was let for concrete surfacing. Ma Tau Wei Road was also partly reconstructed in concrete with dual carriageways and a service road.
272. A comprehensive programme of maintenance and resurfacing was successfully executed, much of it in conjunction with the restora- tion of roads damaged in rainstorms.
NEW TERRITORIES ROADS
273. A considerable number of new feeder roads were built in the New Territories to provide access to outlying districts. The most important of these were the road linking Luk Keng Village with the Sha Tau Kok Road, extensions of the Ping Tse feeder road to Ta Kwu Ling and of the road from Ting Kok to Tai Mei Tuk which is to form the main access to the Plover Cove water supply scheme. Yet another feeder road was constructed from Sai Kung to Tai Mong Tsai.
274. On the south coast of Lantao the 10-foot road was extended 41⁄2 miles from Cheung Sha to Shek Pik and work was initiated on the widening of the 4-mile section between Silvermine Bay and Cheung Sha.
275. Portions of the Castle Peak and Tai Po Roads were resurfaced. The latter road was completely washed out in many places in June and it took several months to repair the damage.
276. Major works undertaken included the first stage in the widening of Tsing Lung Tau causeway, the improvement and surfacing of Anderson Road from its junction with Clearwater Bay Road to Po Lam Road, the reconstruction and widening to dual carriageways of part of Texaco Road, improvements incorporating a second carriage- way to Castle Peak Road between Kwai Chung and Chai Wan Kok.
277. The first stage of widening Hiram's Highway from Clearwater Bay Road to Ho Chung was completed and work well advanced on the second stage between Ho Chung and Sai Kung.