including the construction of eighty-five diversion dams and approximately 88,000 feet of concrete-lined irrigation channel.

329. The construction of catchwaters requires compensatory measures for villagers where streams feeding their cultivated areas are intercepted by the new catchwater channels. To this end, as part of the Tai Lam Chung catchwaters scheme, work started on two dams at Tsing Tam (at the head of the valley above Kam Tin) to store 30 million gallons. A possible site for another dam of 120-million gallon capacity at Ho Pui was investigated. Work started on irrigation works connected with the Shek Pik Scheme, and two diversion dams approached completion on Lantao.

Miscellaneous and Minor Works

330. New Territories Supply

(1) Tai O Supply

The completion of this scheme, described in last year's Report, has enabled 100 consumers to receive metered supplies.

(2) Tai Po Supply

To improve the inadequate water pressure in the town of Tai Po, work commenced on laying a new 8-inch diameter pipe from the existing stream intake; about 8,000 feet of a total length of 15,000 feet was laid.

(3) Fan Ling

A small concrete dam was built and three miles of 6-inch diameter pipeline laid from the Fan Ling stream intake to the Fan Ling Cross Roads, to increase storage capacity and improve Fan Ling's water supply.

KAI TAK AIRPORT DEVELOPMENT

Consulting Engineers: Messrs. Scott & Wilson, Kirkpatrick & Partners.

331. The contractors for forming the reclamation and constructing the new runway completed their contract to time on 26th August; the new runway came into commission on 31st August and was formally opened by His Excellency the Governor on 12th September. This contract is believed to have been the largest single civil engineering contract in the history of the Colony. The Société Française d'Entreprises de Dragages et de Travaux Publics undertook the main contract, and Messrs. Gammon (Malaya) Limited, the chief sub-contract.

59

Edit History

2026-05-11 20:47:07 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
including the construction of eighty-five diversion dams and approximately 88,000 feet of concrete-lined irrigation channel.329. The construction of catchwaters requires compensatory measures for villagers where streams feeding their cultivated areas are intercepted by the new catchwater channels. To this end, as part of the Tai Lam Chung catchwaters scheme, work started on two dams at Tsing Tam (at the head of the valley above Kam Tin) to store 30 million gallons. A possible site for another dam of 120-million gallon capacity at Ho Pui was investigated. Work started on irrigation works connected with the Shek Pik Scheme, and two diversion dams approached completion on Lantao.Miscellaneous and Minor Works330. New Territories Supply(1) Tai O SupplyThe completion of this scheme, described in last year's Report, has enabled 100 consumers to receive metered supplies.(2) Tai Po SupplyTo improve the inadequate water pressure in the town of Tai Po, work commenced on laying a new 8-inch diameter pipe from the existing stream intake; about 8,000 feet of a total length of 15,000 feet was laid.(3) Fan LingA small concrete dam was built and three miles of 6-inch diameter pipeline laid from the Fan Ling stream intake to the Fan Ling Cross Roads, to increase storage capacity and improve Fan Ling's water supply.KAI TAK AIRPORT DEVELOPMENTConsulting Engineers: Messrs. Scott & Wilson, Kirkpatrick & Partners.331. The contractors for forming the reclamation and constructing the new runway completed their contract to time on 26th August; the new runway came into commission on 31st August and was formally opened by His Excellency the Governor on 12th September. This contract is believed to have been the largest single civil engineering contract in the history of the Colony. The Société Française d'Entreprises de Dragages et de Travaux Publics undertook the main contract, and Messrs. Gammon (Malaya) Limited, the chief sub-contract.59
Baseline (Original)
including the construction of eighty five diversion dams and approxi- mately 88,000 feet of concrete lined irrigation channel.329. The construction of catchwaters requires compensatory measures for villagers where streams feeding their cultivated areas are intercepted by the new catchwater channels. To this end, as part of the Tai Lam Chung catchwaters scheme, work started on two dams at Tsing Tam (at the head of the valley above Kam Tin) to store 30 million gallons. A possible site for another dam of 120-million gallon capacity at Ho Pui was investigated. Work started on irrigation works connected with the Shek Pik Scheme, and two diversion dams approached completion on Lantao.Miscellaneous and Minor Works330. New Territories Supply(1) Tai O SupplyThe completion of this scheme, described in last year's Report, has enabled 100 consumers to receive metered supplies.(2) Tai Po SupplyTo improve the inadequate water pressure in the town of Tai Po, work commenced on laying a new 8-inch diameter pipe from the existing stream intake; about 8,000 feet of a total length of 15,000 feet was laid.(3) Fan LingA small concrete dam was built and three miles of 6-inch diameter pipeline laid from the Fan Ling stream intake to the Fan Ling Cross Roads, to increase storage capacity and improve Fan Ling's water supply.KAI TAK AIRPORT DEVELOPMENTConsulting Engineers: Messrs. Scott & Wilson, Kirkpatrick & Partners.331. The contractors for forming the reclamation and constructing the new runway completed their contract to time on 26th August; the new runway came into commission on 31st August and was formally opened by His Excellency the Governor on 12th September. This con- tract is believed to have been the largest single civil engineering contract in the history of the Colony. The Societe Francaise d'Entreprises de Dragages et de Travaux Publics undertook the main contract, and Messrs. Gammon (Malaya) Limited, the chief sub-contract.59i!
2026-05-11 20:47:07 · Baseline
View content

including the construction of eighty five diversion dams and approxi- mately 88,000 feet of concrete lined irrigation channel.

329. The construction of catchwaters requires compensatory measures for villagers where streams feeding their cultivated areas are intercepted by the new catchwater channels. To this end, as part of the Tai Lam Chung catchwaters scheme, work started on two dams at Tsing Tam (at the head of the valley above Kam Tin) to store 30 million gallons. A possible site for another dam of 120-million gallon capacity at Ho Pui was investigated. Work started on irrigation works connected with the Shek Pik Scheme, and two diversion dams approached completion on Lantao.

Miscellaneous and Minor Works

330. New Territories Supply

(1) Tai O Supply

The completion of this scheme, described in last year's Report, has enabled 100 consumers to receive metered supplies.

(2) Tai Po Supply

To improve the inadequate water pressure in the town of Tai Po, work commenced on laying a new 8-inch diameter pipe from the existing stream intake; about 8,000 feet of a total length of 15,000 feet was laid.

(3) Fan Ling

A small concrete dam was built and three miles of 6-inch diameter pipeline laid from the Fan Ling stream intake to the Fan Ling Cross Roads, to increase storage capacity and improve Fan Ling's water supply.

KAI TAK AIRPORT DEVELOPMENT

Consulting Engineers: Messrs. Scott & Wilson, Kirkpatrick & Partners.

331. The contractors for forming the reclamation and constructing the new runway completed their contract to time on 26th August; the new runway came into commission on 31st August and was formally opened by His Excellency the Governor on 12th September. This con- tract is believed to have been the largest single civil engineering contract in the history of the Colony. The Societe Francaise d'Entreprises de Dragages et de Travaux Publics undertook the main contract, and Messrs. Gammon (Malaya) Limited, the chief sub-contract.