1958-1959 — Page 50

Public Works Department Annual Report 工務司署年報 All AI Reviewed

completed by the end of the year. To give the wall initial stability a 50-feet wide bund was created behind it with spoil from site formation works for the nearby Tai Wo Hau multi-storey resettlement blocks.

Reclamation for the Tong Mi Road Extension

221. The dredging of the foundation trench for some 550 feet of sea wall for the Tong Mi Road extension commenced but had to be suspended owing to numerous public objections. The precasting of all the concrete blockwork was however completed.

Reclamation at Peng Chau Island, South

222. This small reclamation of 1,200 square yards, protected by 200 feet of pitched rubble walling, has improved the central waterfront of Peng Chau.

Chi Ma Wan Prison Pier Extension

223. A contract for the extension of the existing pier was let in April and completed in October.

Sok Kwu Wan Pier

224. Work on this pier on Lamma Island commenced in December. By the end of the year all precast work at North Point Depot had been completed and the construction of the causeway and the erection of the temporary staging had started.

Ferry Pier and Sea Wall at Cheung Chau

225. This included sea wall protection of the foreshore and the construction of a new pier to provide two ferry berths with improved protection and facilities for passengers. Work commenced in February.

Pier at Kei Ling Ha Hoi in Tolo Harbour

226. The construction of this pier, measuring 80 feet long by 30 feet wide with a 120-feet long approach, started in November. Owing to the remoteness of this difficult site, the piles were cast at the North Point Depot and transported by barge some 30 miles up the coast, largely through open water. By the end of March, pile driving had been completed and the decking and construction of the approach had started.

Typhoon Shelter at Tsing Yi

227. As the reclamation of the bay at Tsuen Wan has absorbed the natural anchorage for native craft, work started on the formation of an


Page 40

Edit History

2026-05-11 20:44:09 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
completed by the end of the year. To give the wall initial stability a 50-feet wide bund was created behind it with spoil from site formation works for the nearby Tai Wo Hau multi-storey resettlement blocks. Reclamation for the Tong Mi Road Extension 221. The dredging of the foundation trench for some 550 feet of sea wall for the Tong Mi Road extension commenced but had to be suspended owing to numerous public objections. The precasting of all the concrete blockwork was however completed. Reclamation at Peng Chau Island, South 222. This small reclamation of 1,200 square yards, protected by 200 feet of pitched rubble walling, has improved the central waterfront of Peng Chau. Chi Ma Wan Prison Pier Extension 223. A contract for the extension of the existing pier was let in April and completed in October. Sok Kwu Wan Pier 224. Work on this pier on Lamma Island commenced in December. By the end of the year all precast work at North Point Depot had been completed and the construction of the causeway and the erection of the temporary staging had started. Ferry Pier and Sea Wall at Cheung Chau 225. This included sea wall protection of the foreshore and the construction of a new pier to provide two ferry berths with improved protection and facilities for passengers. Work commenced in February. Pier at Kei Ling Ha Hoi in Tolo Harbour 226. The construction of this pier, measuring 80 feet long by 30 feet wide with a 120-feet long approach, started in November. Owing to the remoteness of this difficult site, the piles were cast at the North Point Depot and transported by barge some 30 miles up the coast, largely through open water. By the end of March, pile driving had been completed and the decking and construction of the approach had started. Typhoon Shelter at Tsing Yi 227. As the reclamation of the bay at Tsuen Wan has absorbed the natural anchorage for native craft, work started on the formation of an Page 40
Baseline (Original)
completed by the end of the year. To give the wall initial stability a 50-feet wide bund was created behind it with spoil from site formation works for the nearby Tai Wo Hau multi-storey resettlement blocks. Reclamation for the Tong Mi Road Extension 221. The dredging of the foundation trench for some 550 feet of sea wall for the Tong Mi Road extension commenced but had to be suspended owing to numerous public objections. The precasting of all the concrete blockwork was however completed. Reclamation at Peng Chau Island, South 222. This small reclamation of 1,200 square yards, protected by 200 feet of pitched rubble walling, has improved the central waterfront of Peng Chau. Chi Ma Wan Prison Pier Extension 223. A contract for the extension of the existing pier was let in April and completed in October. Sok Kwu Wan Pier 224. Work on this pier on Lamma Island commenced in December. By the end of the year all precast work at North Point Depot had been completed and the construction of the causeway and the erection of the temporary staging had started. Ferry Pier and Sea Wall at Cheung Chau 225. This included sea wall protection of the foreshore and the construction of a new pier to provide two ferry berths with improved protection and facilities for passengers. Work commenced in February. Pier at Kei Ling Ha Hoi in Tolo Harbour 226. The construction of this pier, measuring 80 feet long by 30 feet wide with a 120-feet long approach, started in November. Owing to the remoteness of this difficult site, the piles were cast at the North Point Depot and transported by barge some 30 miles up the coast, largely through open water. By the end of March, pile driving had been completed and the decking and construction of the approach had started. Typhoon Shelter at Tsing Yi 227. As the reclamation of the bay at Tsuen Wan has absorbed the natural anchorage for native craft, work started on the formation of an 40
2026-05-11 20:44:09 · Baseline
View content

completed by the end of the year. To give the wall initial stability a 50-feet wide bund was created behind it with spoil from site formation works for the nearby Tai Wo Hau multi-storey resettlement blocks.

Reclamation for the Tong Mi Road Extension

221. The dredging of the foundation trench for some 550 feet of sea wall for the Tong Mi Road extension commenced but had to be suspended owing to numerous public objections. The precasting of all the concrete blockwork was however completed.

Reclamation at Peng Chau Island, South

222. This small reclamation of 1,200 square yards, protected by 200 feet of pitched rubble walling, has improved the central waterfront of Peng Chau.

Chi Ma Wan Prison Pier Extension

223. A contract for the extension of the existing pier was let in April and completed in October.

Sok Kwu Wan Pier

224. Work on this pier on Lamma Island commenced in December. By the end of the year all precast work at North Point Depot had been completed and the construction of the causeway and the erection of the temporary staging had started.

Ferry Pier and Sea Wall at Cheung Chau

225. This included sea wall protection of the foreshore and the construction of a new pier to provide two ferry berths with improved protection and facilities for passengers. Work commenced in February.

Pier at Kei Ling Ha Hoi in Tolo Harbour

226. The construction of this pier, measuring 80 feet long by 30 feet wide with a 120-feet long approach, started in November. Owing to the remoteness of this difficult site, the piles were cast at the North Point Depot and transported by barge some 30 miles up the coast, largely through open water. By the end of March, pile driving had been completed and the decking and construction of the approach had started.

Typhoon Shelter at Tsing Yi

227. As the reclamation of the bay at Tsuen Wan has absorbed the natural anchorage for native craft, work started on the formation of an

40

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.