ELECTRICAL SECTION

221. The number of items of electrical plant and appliances in use at the end of the year totalled 22,274—about 12% more than in the previous year. The programme for servicing and maintaining in good running order the 1,269 electric motors (totalling 10,311 H.P.), 8,714 fans, 6,507 heaters and radiators, 1,021 cookers and hot-plates, 1,928 water heaters and boilers and 2,835 miscellaneous items was satisfactorily carried out.

222. Major electrical installations completed included:

3 Nos. 480 H.P. motors at the Tsuen Wan waterworks pumping station
1 No. 370 H.P. motor and main switchboard at the Kau Wa Keng waterworks pumping station
1 No. 320 H.P. motor and associated switchgear at the Elliot waterworks pumping station
3 Nos. 98 H.P. motors and
1 No. 368 H.P. motor and associated switchgear at the new Garden Road waterworks pumping station
3 Nos. 30 H.P. motors at the Mong Kok Road sewerage station
2 Nos. 18 H.P. motors at the Nan Chang Street sewerage station
2 Nos. 20 H.P. motors and
1 No. 10 H.P. motor at the Anchor Street sewerage station
1 No. 405 H.P. motor and
2 Nos. 175 H.P. motors at the Tai Tam Tuk waterworks pumping station
1 No. 75 H.P. air compressor at the Hok Yuen quarry
1 No. 55 K.W. emergency generator at the basement plant room, Central Block, New Government Offices
2 Nos. 500 K.V.A. transformers and associated high tension switchgears at the Mount Butler quarry

223. The Electrical Workshop continued to be fully employed during the year; 18,834 maintenance visits were made, 14,359 faults repaired, 15,613 jobs completed, 1,584 installation tests made, 254 estimates prepared and 1,428 inventories made out.

224. Vehicle Actuated Traffic Control Signals were installed, and regulated to suit prevailing traffic conditions at the junctions of:

Hennessey Road/Tin Lok Lane/Marsh Road
Hennessey Road/Percival Street
Caine Road/Arbuthnot Road/Upper Albert Road
Pok Fu Lam Road/Bonham Road/Hill Road
Des Voeux Road West/Connaught Road West
Pok Fu Lam Road/Queen's Road West/Western Street

Belisha beacons were installed at the following locations:

Wong Nei Chong Road
Hennessey Road
Queen's Road East

1 crossing 2 crossings 3 crossings

Page 36

...


Page 36

Edit History

2026-05-11 20:32:33 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
ELECTRICAL SECTION 221. The number of items of electrical plant and appliances in use at the end of the year totalled 22,274—about 12% more than in the previous year. The programme for servicing and maintaining in good running order the 1,269 electric motors (totalling 10,311 H.P.), 8,714 fans, 6,507 heaters and radiators, 1,021 cookers and hot-plates, 1,928 water heaters and boilers and 2,835 miscellaneous items was satisfactorily carried out. 222. Major electrical installations completed included: 3 Nos. 480 H.P. motors at the Tsuen Wan waterworks pumping station 1 No. 370 H.P. motor and main switchboard at the Kau Wa Keng waterworks pumping station 1 No. 320 H.P. motor and associated switchgear at the Elliot waterworks pumping station 3 Nos. 98 H.P. motors and 1 No. 368 H.P. motor and associated switchgear at the new Garden Road waterworks pumping station 3 Nos. 30 H.P. motors at the Mong Kok Road sewerage station 2 Nos. 18 H.P. motors at the Nan Chang Street sewerage station 2 Nos. 20 H.P. motors and 1 No. 10 H.P. motor at the Anchor Street sewerage station 1 No. 405 H.P. motor and 2 Nos. 175 H.P. motors at the Tai Tam Tuk waterworks pumping station 1 No. 75 H.P. air compressor at the Hok Yuen quarry 1 No. 55 K.W. emergency generator at the basement plant room, Central Block, New Government Offices 2 Nos. 500 K.V.A. transformers and associated high tension switchgears at the Mount Butler quarry 223. The Electrical Workshop continued to be fully employed during the year; 18,834 maintenance visits were made, 14,359 faults repaired, 15,613 jobs completed, 1,584 installation tests made, 254 estimates prepared and 1,428 inventories made out. 224. Vehicle Actuated Traffic Control Signals were installed, and regulated to suit prevailing traffic conditions at the junctions of: Hennessey Road/Tin Lok Lane/Marsh Road Hennessey Road/Percival Street Caine Road/Arbuthnot Road/Upper Albert Road Pok Fu Lam Road/Bonham Road/Hill Road Des Voeux Road West/Connaught Road West Pok Fu Lam Road/Queen's Road West/Western Street Belisha beacons were installed at the following locations: Wong Nei Chong Road Hennessey Road Queen's Road East 1 crossing 2 crossings 3 crossings Page 36 ... Page 36
Baseline (Original)
ELECTRICAL SECTION 221. The number of items of electrical plant and appliances in use at the end of the year totalled 22,274-about 12% more than in the previous year. The programme for servicing and maintaining in good running order the 1,269 electric motors (totalling 10,311 H.P.), 8,714 fans, 6,507 heaters and radiators, 1,021 cookers and hot-plates, 1,928 water heaters and boilers and 2,835 miscellaneous items was satisfac- torily carried out. 222. Major electrical installations completed included: 3 Nos. 480 H.P. motors at the Tsuen Wan waterworks pumping station 1 No. 370 H.P. motor and main switchboard at the Kau Wa Kang waterworks pumping station 1 No. 320 H.P. motor and associated switchgear at the Elliot waterworks pumping station 3 Nos. 98 H.P. motors and 1 No. 368 H.P. motor and associated switchgear at the new Garden Road waterworks pumping station 3 Nos. 30 H.P. motors at the Mong Kok Road sewerage station 2 Nos. 18 H.P. motors at the Nan Chang Street sewerage station 2 Nos. 20 H.P. motors and 1 No. 10 H.P. motor at the Anchor Street sewerage station 1 No. 405 H.P. motor and 2 Nos. 175 H.P. motors at the Tai Tam Tuk waterworks pumping station 1 No. 75 H.P. air compressor at the Hok Yuen quarry 1 No. 55 K.W. emergency generator at the basement plant room, Central Block, New Government Offices 2 Nos. 500 K.V.A. transformers and associated high tension switchgears at the Mount Butler quarry 223. The Electrical Workshop continued to be fully employed during the year; 18,834 maintenance visits were made, 14,359 faults repaired, 15,613 jobs completed, 1,584 installation tests made, 254 estimates prepared and 1,428 inventories made out. 224. Vehicle Actuated Traffic Control Signals were installed, and regulated to suit prevailing traffic conditions at the junctions of: Hennessey Road/Tin Lok Lane/Marsh Road Hennessey Road/Percival Street Caine Road/Arbuthnot Road/Upper Albert Road Pok Fu Lam Road/Bonham Road/Hill Road Des Voeux Road West/Connaught Road West Pok Fu Lam Road/Queen's Road West/Western Street Belisha beacons were installed at the following locations: Wong Nei Chong Road Hennessey Road Queen's Road East ... 1 crossing 2 crossings 3 crossings 36
2026-05-11 20:32:33 · Baseline
View content

ELECTRICAL SECTION

221. The number of items of electrical plant and appliances in use at the end of the year totalled 22,274-about 12% more than in the previous year. The programme for servicing and maintaining in good running order the 1,269 electric motors (totalling 10,311 H.P.), 8,714 fans, 6,507 heaters and radiators, 1,021 cookers and hot-plates, 1,928 water heaters and boilers and 2,835 miscellaneous items was satisfac- torily carried out.

222. Major electrical installations completed included:

3 Nos. 480 H.P. motors at the Tsuen Wan waterworks pumping station 1 No. 370 H.P. motor and main switchboard at the Kau Wa Kang

waterworks pumping station

1 No. 320 H.P. motor and associated switchgear at the Elliot waterworks

pumping station

3 Nos. 98 H.P. motors and

1 No. 368 H.P. motor and associated switchgear at the new Garden Road

waterworks pumping station

3 Nos. 30 H.P. motors at the Mong Kok Road sewerage station

2 Nos. 18 H.P. motors at the Nan Chang Street sewerage station

2 Nos. 20 H.P. motors and

1 No. 10 H.P. motor at the Anchor Street sewerage station

1 No. 405 H.P. motor and

2 Nos. 175 H.P. motors at the Tai Tam Tuk waterworks pumping station 1 No. 75 H.P. air compressor at the Hok Yuen quarry

1 No. 55 K.W. emergency generator at the basement plant room, Central

Block, New Government Offices

2 Nos. 500 K.V.A. transformers and associated high tension switchgears

at the Mount Butler quarry

223. The Electrical Workshop continued to be fully employed during the year; 18,834 maintenance visits were made, 14,359 faults repaired, 15,613 jobs completed, 1,584 installation tests made, 254 estimates prepared and 1,428 inventories made out.

224. Vehicle Actuated Traffic Control Signals were installed, and regulated to suit prevailing traffic conditions at the junctions of:

Hennessey Road/Tin Lok Lane/Marsh Road

Hennessey Road/Percival Street

Caine Road/Arbuthnot Road/Upper Albert Road

Pok Fu Lam Road/Bonham Road/Hill Road

Des Voeux Road West/Connaught Road West

Pok Fu Lam Road/Queen's Road West/Western Street

Belisha beacons were installed at the following locations:

Wong Nei Chong Road

Hennessey Road

Queen's Road East ...

1 crossing

2 crossings 3 crossings

36

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.