78. Sketch plans were prepared for the erection of a pair of semi-detached houses similar to the Maryknoll quarters recently built at Stanley.
PUBLIC WORKS DEPARTMENT
P.W.D. Depots and Quarters
79. Working drawings commenced for two Roads Office depots; one on the Shek O Road included an office, store and ten quarters in a single-storey building; the second, adjacent to the Sai Wan Rapid Gravity Filters, included a store and eleven quarters in three storeys on a restricted site. The second scheme has been delayed because of a shortage of structural engineers.
Showers for Hok Un Quarry
80. Sketch plans were prepared for a building with showers and changing facilities for the workers at the quarry.
RESETTLEMENT DEPARTMENT
Shek Kip Mei, Stage II (Redevelopment)
81. The last of the six blocks in the contract, containing some 420 domestic rooms, was completed early in the year.
Shek Kip Mei, Stage III (Redevelopment)
82. A contract for the demolition of twenty-six bungalows commenced in April and was completed in December.
83. A further contract for the demolition of seventeen bungalows, together with the construction of nine blocks of resettlement flats started in June. By the end of the year, six blocks of flats had been completed providing some 2,492 domestic rooms.
Lo Fu Ngam
84. Construction of this estate of six blocks of flats, containing 1,089 domestic rooms and commenced the previous year, was completed. The scheme had been delayed because of rock obstructing site formation.
Cheung Sha Wan Flatted Factory
85. A contract for the superstructure was let in June and completed in September. The building is of five storeys and provides a total of 470 working units of 198 square feet (ninety-four units per floor). A roof area of some 15,528 square feet is available for letting out as
78. Sketch plans were prepared for the erection of a pair of semi- detached houses similar to the Maryknoll quarters recently built at Stanley.
PUBLIC WORKS DEPARTMENT
P.W.D. Depots and Quarters
79. Working drawings commenced for two Roads Office depots; one on the Shek O Road included an office, store and ten quarters in a single-storey building; the second, adjacent to the Sai Wan Rapid Gravity Filters, included a store and eleven quarters in three storeys on a restricted site. The second scheme has been delayed because of a shortage of structural engineers.
Showers for Hok Un Quarry
80. Sketch plans were prepared for a building with showers and changing facilities for the workers at the quarry.
RESETTLEMENT DEPARTMENT
Shek Kip Mei, Stage II (Redevelopment)
81. The last of the six blocks in the contract, containing some 420 domestic rooms, was completed early in the year.
Shek Kip Mei, Stage III (Redevelopment)
82. A contract for the demolition of twenty six bungalows com- menced in April and was completed in December.
83. A further contract for the demolition of seventeen bungalows, together with the construction of nine blocks of resettlement flats started in June. By the end of the year six blocks of flats had been completed providing some 2,492 domestic rooms.
Lo Fu Ngam
84. Construction of this estate of six blocks of flats, containing 1,089 domestic rooms and commenced the previous year, was completed. The scheme had been delayed because of rock obstructing site formation.
Cheung Sha Wan Flatted Factory
85. A contract for the superstructure was let in June and completed in September. The building is of five storeys and provides a total of 470 working units of 198 square feet (ninety four units per floor). A roof area of some 15,528 square feet is available for letting out as