Stage II.

79. One Block, comprising 532 rooms, was completed and handed over for occupation by the end of December. The remaining Block was not commenced, pending completion of site formation.

Lo Fu Ngam.

80. Site formation work was commenced and construction work on 4 out of the 8 Blocks, comprising 1,510 rooms, was commenced by the end of the year.

Wong Tai Sin.

81. Sketch plans were approved for Areas 'A' and 'B' and working drawings were well in hand for the first phase of this development.

Pump House, Cheung Sha Wan.

82. The pumphouse to provide sea water for flushing purposes at Shek Kip Mei and Li Cheng Uk was completed in July.

Resettlement Factory, Cheung Sha Wan.

83. A contract was let for piling to foundations, and working drawings for the building were completed.

Stores Department

Reprovisioning of Government Stores, North Point.

84. In order to permit the extension of Electric Road through the site of the Hong Kong Electric Company's Power Station at North Point, the Electric Company surrendered to Government a portion of their site in exchange for a portion of the adjoining Government Stores site. This necessitated the reprovisioning of the storage accommodation, offices, dangerous goods storage and furniture workshops, which were surrendered with the portion of the Government site.

85. Sketch plans approved by the end of March provide for metal workshops and a dangerous goods store in single storey buildings; a two-storied extension to the furniture workshops and a five-storey stores and office block with offices on the top floor.

13

Edit History

2026-05-11 20:19:38 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Stage II. 79. One Block, comprising 532 rooms, was completed and handed over for occupation by the end of December. The remaining Block was not commenced, pending completion of site formation. Lo Fu Ngam. 80. Site formation work was commenced and construction work on 4 out of the 8 Blocks, comprising 1,510 rooms, was commenced by the end of the year. Wong Tai Sin. 81. Sketch plans were approved for Areas 'A' and 'B' and working drawings were well in hand for the first phase of this development. Pump House, Cheung Sha Wan. 82. The pumphouse to provide sea water for flushing purposes at Shek Kip Mei and Li Cheng Uk was completed in July. Resettlement Factory, Cheung Sha Wan. 83. A contract was let for piling to foundations, and working drawings for the building were completed. Stores Department Reprovisioning of Government Stores, North Point. 84. In order to permit the extension of Electric Road through the site of the Hong Kong Electric Company's Power Station at North Point, the Electric Company surrendered to Government a portion of their site in exchange for a portion of the adjoining Government Stores site. This necessitated the reprovisioning of the storage accommodation, offices, dangerous goods storage and furniture workshops, which were surrendered with the portion of the Government site. 85. Sketch plans approved by the end of March provide for metal workshops and a dangerous goods store in single storey buildings; a two-storied extension to the furniture workshops and a five-storey stores and office block with offices on the top floor. 13
Baseline (Original)
Stage II. 79. One Block, comprising 532 rooms, was completed and handed over for occupation by the end of December. The remaining Block was not commenced, pending completion of site formation. Lo Fu Ngam. 80. Site formation work was commenced and construction work on 4 out of the 8 Blocks, comprising 1,510 rooms, was commenced by the end of the year. Wong Tai Sin. 81. Sketch plans were approved for Areas 'A' and 'B' and working drawings were well in hand for the first phase of this development. Pump House, Cheung Sha Wan. 82. The pumphouse to provide sea water for flushing pur- poses at Shek Kip Mei and Li Cheng Uk was completed in July. Resettlement Factory, Cheung Sha Wan. 83. A contract was let for piling to foundations, and working drawings for the building were completed. Stores Department Reprovisioning of Government Stores, North Point. 84. In order to permit the extension of Electric Road through the site of the Hong Kong Electric Company's Power Station at North Point, the Electric Company surrendered to Government a portion of their site in exchange for a portion of the adjoining Government Stores site. This necessitated the reprovisioning of the storage accommodation, offices, dangerous goods storage and furniture workshops, which were surrendered with the portion of the Government site. 85. Sketch plans approved by the end of March provide for metal workshops and a dangerous goods store in single storey buildings; a two storied extension to the furniture workshops and a five storey stores and office block with offices on the top floor. 13
2026-05-11 20:19:38 · Baseline
View content

Stage II.

79. One Block, comprising 532 rooms, was completed and handed over for occupation by the end of December. The remaining Block was not commenced, pending completion of site formation.

Lo Fu Ngam.

80. Site formation work was commenced and construction work on 4 out of the 8 Blocks, comprising 1,510 rooms, was commenced by the end of the year.

Wong Tai Sin.

81. Sketch plans were approved for Areas 'A' and 'B' and working drawings were well in hand for the first phase of this development.

Pump House, Cheung Sha Wan.

82. The pumphouse to provide sea water for flushing pur- poses at Shek Kip Mei and Li Cheng Uk was completed in July.

Resettlement Factory, Cheung Sha Wan.

83. A contract was let for piling to foundations, and working drawings for the building were completed.

Stores Department

Reprovisioning of Government Stores, North Point.

84. In order to permit the extension of Electric Road through the site of the Hong Kong Electric Company's Power Station at North Point, the Electric Company surrendered to Government a portion of their site in exchange for a portion of the adjoining Government Stores site. This necessitated the reprovisioning of the storage accommodation, offices, dangerous goods storage and furniture workshops, which were surrendered with the portion of the Government site.

85. Sketch plans approved by the end of March provide for metal workshops and a dangerous goods store in single storey buildings; a two storied extension to the furniture workshops and a five storey stores and office block with offices on the top floor.