comprises an eight-floored block of sixteen 2 and 3 bedroom flats for Prison Officers; a block of 40 single room married quarters for Warders in ten upper floors, with balcony, kitchen and toilet for each flat, and with two lower floors for garage and storage; and a three-floored block with barrack accommodation for 40 Warders with garages at the ground floor level. The scheme provides garage accommodation for 12 vehicles. H.M. Prison, Chimawan, Lantao.

66. Work was started on the conversion of the former Home for the Disabled, at Chimawan, into a Prison for 600 short-term prisoners. Alterations were required to the kitchen and the dormitory toilets, and additional site drainage work was carried out. One existing hut was converted into a Sick Bay and Dressers' Quarter. The work was nearing completion by the end of March.

Prison Offices, Stanley Prison.

67. Sketch plans were prepared and approved for a single-storey block of offices for Stanley Prison.

Public Works Department

New Electrical and Mechanical Workshops, Caroline Hill.

68. A start was made on the working drawings for the final stage of this scheme. The project comprises the phased demolition of existing offices and construction of new offices, workshops and quarters, providing a total floor area for this stage of 47,550 square feet, with an additional 5,900 square feet of covered parking area and some ancillary buildings.

P.W.D. Offices and Depot, Kowloon.

69. This scheme was fully described in last year's report. A nine-month contract was let in August for the construction of the five-storey administration block and the adjacent single-storey workshop block. A decision was later made to add the three extra office floors (for which the administration block had been designed) as a three months' extension to the building contract. A re-arrangement of the office floors was made to accommodate a Post Office and Registry for Births and Deaths at the ground floor level, P.W.D. offices on the first to fourth floors, and Urban Services offices and Medical Department offices on the fifth and sixth floors.

21

11

Page 11

Edit History

2026-05-11 20:19:23 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Page 21 comprises an eight-floored block of sixteen 2 and 3 bedroom flats for Prison Officers; a block of 40 single room married quarters for Warders in ten upper floors, with balcony, kitchen and toilet for each flat, and with two lower floors for garage and storage; and a three-floored block with barrack accommodation for 40 Warders with garages at the ground floor level. The scheme provides garage accommodation for 12 vehicles. H.M. Prison, Chimawan, Lantao. 66. Work was started on the conversion of the former Home for the Disabled, at Chimawan, into a Prison for 600 short-term prisoners. Alterations were required to the kitchen and the dormitory toilets, and additional site drainage work was carried out. One existing hut was converted into a Sick Bay and Dressers' Quarter. The work was nearing completion by the end of March. Prison Offices, Stanley Prison. 67. Sketch plans were prepared and approved for a single-storey block of offices for Stanley Prison. Public Works Department New Electrical and Mechanical Workshops, Caroline Hill. 68. A start was made on the working drawings for the final stage of this scheme. The project comprises the phased demolition of existing offices and construction of new offices, workshops and quarters, providing a total floor area for this stage of 47,550 square feet, with an additional 5,900 square feet of covered parking area and some ancillary buildings. P.W.D. Offices and Depot, Kowloon. 69. This scheme was fully described in last year's report. A nine-month contract was let in August for the construction of the five-storey administration block and the adjacent single-storey workshop block. A decision was later made to add the three extra office floors (for which the administration block had been designed) as a three months' extension to the building contract. A re-arrangement of the office floors was made to accommodate a Post Office and Registry for Births and Deaths at the ground floor level, P.W.D. offices on the first to fourth floors, and Urban Services offices and Medical Department offices on the fifth and sixth floors. 21 11 Page 11
Baseline (Original)
Page comprises an eight floored block of sixteen 2 and 3 bedroom flats for Prison Officers; a block of 40 single room married quarters for Warders in ten upper floors, with balcony, kitchen and toilet for each flat, and with two lower floors for garage and storage; and a three floored block with barrack accommoda- tion for 40 Warders with garages at the ground floor level. The scheme provides garage accommodation for 12 vehicles. H.M. Prison, Chimawan, Lantao. 66. Work was started on the conversion of the former Home for the Disabled, at Chimawan, into a Prison for 600 short term prisoners. Alterations were required to the kitchen and the dormitory toilets, and additional site drainage work was carried out. One existing hut was converted into a Sick Bay and Dressers' Quarter. The work was nearing completion by the end of March. Prison Offices, Stanley Prison. 67. Sketch plans were prepared and approved for a single storey block of offices for Stanley Prison. Public Works Department New Electrical and Mechanical Workshops, Caroline Hill. 68. A start was made on the working drawings for the final stage of this scheme. The project comprises the phased demoli- tion of existing offices and construction of new offices, work- shops and quarters, providing a total floor area for this stage of 47,550 square feet, with an additional 5,900 square feet of covered parking area and some ancillary buildings. P.W.D. Offices and Depot, Kowloon. 69. This scheme was fully described in last year's report. A nine month contract was let in August for the construction of the five storey administration block and the adjacent single storey workshop block. A decision was later made to add the three extra office floors (for which the administration block had been designed) as a three months' extension to the building contract. A re-arrangement of the office floors was made to accommodate a Post Office and Registry for Births and Deaths at the ground floor level, P.W.D. offices on the first to fourth floors, and Urban Services offices and Medical Department offices on the fifth and sixth floors. 21 11 T
2026-05-11 20:19:23 · Baseline
View content

Page

comprises an eight floored block of sixteen 2 and 3 bedroom flats for Prison Officers; a block of 40 single room married quarters for Warders in ten upper floors, with balcony, kitchen and toilet for each flat, and with two lower floors for garage and storage; and a three floored block with barrack accommoda- tion for 40 Warders with garages at the ground floor level. The scheme provides garage accommodation for 12 vehicles. H.M. Prison, Chimawan, Lantao.

66. Work was started on the conversion of the former Home for the Disabled, at Chimawan, into a Prison for 600 short term prisoners. Alterations were required to the kitchen and the dormitory toilets, and additional site drainage work was carried out. One existing hut was converted into a Sick Bay and Dressers' Quarter. The work was nearing completion by the end of March.

Prison Offices, Stanley Prison.

67. Sketch plans were prepared and approved for a single storey block of offices for Stanley Prison.

Public Works Department

New Electrical and Mechanical Workshops, Caroline Hill.

68. A start was made on the working drawings for the final stage of this scheme. The project comprises the phased demoli- tion of existing offices and construction of new offices, work- shops and quarters, providing a total floor area for this stage of 47,550 square feet, with an additional 5,900 square feet of covered parking area and some ancillary buildings.

P.W.D. Offices and Depot, Kowloon.

69. This scheme was fully described in last year's report. A nine month contract was let in August for the construction of the five storey administration block and the adjacent single storey workshop block. A decision was later made to add the three extra office floors (for which the administration block had been designed) as a three months' extension to the building contract. A re-arrangement of the office floors was made to accommodate a Post Office and Registry for Births and Deaths at the ground floor level, P.W.D. offices on the first to fourth floors, and Urban Services offices and Medical Department offices on the fifth and sixth floors.