42. A small scale model of the hospital was started and a larger scale model of a typical ward was completed.
43. Plans of the final scheme were approved by the Medical Department and work on the collation of detailed information was in hand prior to a start being made on the preparation of final working drawings.
44. Sketch plans for the Sisters' and Nurses' Quarters and the Training School were approved, and a start was made on the working drawings. These buildings will provide accommodation for 18 Senior Sisters, 96 Sisters and 450 Nurses, with training facilities for 150 Nurses.
45. It was apparent, however, that if the programme is to keep to schedule, a considerably larger team of Architects will be required with support from Structural, Electrical and Mechanical Engineers, and Quantity Surveyors.
Shek Kip Mei Polyclinic.
46. This clinic provides a general and maternity clinic, to which was added a chest clinic and X-ray section. Working drawings were completed and construction work was commenced in mid March.
Kowloon Chest Clinic Additions.
47. Plans approved in March included an X-ray unit and dressing rooms, additional dispensary, waiting rooms and registration office.
San Hui Market.
New Territories Administration
48. The market consists of a simple single storey structure with pitched roof and floor area of 3,600 square feet, and contains 40 stalls and two small store rooms. A contract was signed in August and completed at the end of January. A water supply, and surfacing to the outside hawker area were, however, still outstanding at the end of the year.
Latrine at Cheung Chau.
49. This latrine provides 15 male cubicles and 8 female cubicles at ground floor level, with caretaker's quarters over. Construction was started in October and completed in January.
8
42. A small scale model of the hospital was started and a larger scale model of a typical ward was completed.
43. Plans of the final scheme were approved by the Medical Department and work on the collation of detailed information was in hand prior to a start being made on the preparation of final working drawings.
44. Sketch plans for the Sisters' and Nurses' Quarters and the Training School were approved, and a start was made on the working drawings. These buildings will provide accom- modation for 18 Senior Sisters, 96 Sisters and 450 Nurses, with training facilities for 150 Nurses.
45. It was apparent, however, that if the programme is to keep to schedule, a considerably larger team of Architects will be required with support from Structural, Electrical and Mechanical Engineers, and Quantity Surveyors.
Shek Kip Mei Polyclinic.
46. This clinic provides a general and maternity clinic, to which was added a chest clinic and X-ray section. Working drawings were completed and construction work was commenced in mid March.
Kowloon Chest Clinic Additions.
47. Plans approved in March included an X-ray unit and dressing rooms, additional dispensary, waiting rooms and regis- tration office.
San Hui Market.
New Territories Administration
48. The market consists of a simple single storey structure with pitched roof and floor area of 3,600 square feet, and con- tains 40 stalls and two small store rooms. A contract was signed in August and completed at the end of January. A water supply, and surfacing to the outside hawker area were, however, still outstanding at the end of the year.
Latrine at Cheung Chau.
49. This latrine provides 15 male cubicles and 8 female cubicles at ground floor level, with caretakers quarters over. Construction was started in October and completed in January.