Resettlement Department
Li Cheng Uk, Block ‘A’.
74. This was referred to in last year's report as "Tonkin Street Resettlement Flats". This seven-storey block of flats, consisting of 840 rooms, was completed in March.
Li Cheng Uk, Phase I.
75. A large site at Li Cheng Uk was reserved for the construction of further blocks of resettlement flats. In order to facilitate movement of the squatters on the site, it was necessary to carry out the development in phases. Site formation for the first phase, consisting of seven blocks, was commenced in May and completed in January.
76. During site formation an ancient tomb was discovered which it was decided to retain; this necessitated omitting two of the blocks from the contract. Building work on the five remaining blocks, consisting of 2,824 rooms, was commenced in August and completed in February.
Li Cheng Uk, Phase II.
77. Site formation for the second phase, consisting of five blocks with a total of 3,010 rooms, was commenced in July but completion of the work was delayed owing to the presence of large quantities of rock. Building work commenced in February and very good progress was made.
Li Cheng Uk, Phase III.
78. Sketch plans for the third phase, providing a further 1,386 rooms, were prepared in January and approved in February.
Tai Hang Tung Resettlement Flats.
79. An additional site was obtained adjoining the Tai Hang Tung Resettlement Flats referred to in last year's report. This site, called "Area 'G'", was planned for an additional six blocks
15
Page 15
...
...
...
Resettlement Department
Li Cheng Uk, Block ‘A'.
74. This was referred to in last year's report as "Tonkin Street Resettlement Flats". This seven-storey block of flats, consisting of 840 rooms, was completed in March.
Li Cheng Uk, Phase I.
75. A large site at Li Cheng Uk was reserved for the construction of further blocks of resettlement flats. In order to facilitate movement of the squatters on the site, it was necessary to carry out the development in phases. Site forma- tion for the first phase, consisting of seven blocks, was commenced in May and completed in January.
76. During site formation an ancient tomb was discovered which it was decided to retain; this necessitated omitting two of the blocks from the contract. Building work on the five remaining blocks, consisting of 2,824 rooms, was commenced in August and completed in February.
Li Cheng Uk, Phase II.
77. Site formation for the second phase, consisting of five blocks with a total of 3,010 rooms, was commenced in July but completion of the work was delayed owing to the presence of large quantities of rock. Building work commenced in February and very good progress was made.
Li Cheng Uk, Phase III.
78. Sketch plans for the third phase, providing a further 1,386 rooms, were prepared in January and approved in February.
Tai Hang Tung Resettlement Flats.
This
79. An additional site was obtained adjoining the Tai Hang Tung Resettlement Flats referred to in last year's report. site, called "Area 'G' ", was planned for an additional six blocks
15
.............
...........
: