Lok Ma Chau Police Station Canteen.

64. A new single-storey building was constructed within the existing station compound, consisting of a canteen and additional barrack accommodation. Work was completed in February.

Rank and File Quarters, Arsenal Yard.

65. As a second stage in the development of the Arsenal Yard site on which was built the New Police Headquarters referred to in last year's report, an eleven-storey building, consisting of a school on the ground floor and rank and file married quarters above, is to be constructed on the Queen's Road frontage. The school will consist of twelve classrooms, handwork room, domestic science room and teachers' rooms, and there will be 300 quarters above, each consisting of a large living/bedroom, verandah and kitchen with communal lavatory facilities. The flats will have external verandah approach and will be served by a lift. Working drawings were nearing completion.

Prisons Department

Stanley Prison-Assembly and Dining Hall.

66. This building was completed in June.

Quarters for Stanley Training Centre.

67. No work was carried out on this scheme, which was referred to in last year's report, as no funds were provided in the annual estimates.

Public Works Department

New Electrical and Mechanical Workshops.

68. This scheme, which is a redevelopment of the existing workshops and offices at Caroline Hill, was referred to in last year's report. The first stage—the construction of the mechanical workshops, providing a covered floor area of 52,800 square feet—was completed in December.

13

Edit History

2026-05-11 20:10:57 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Lok Ma Chau Police Station Canteen. 64. A new single-storey building was constructed within the existing station compound, consisting of a canteen and additional barrack accommodation. Work was completed in February. Rank and File Quarters, Arsenal Yard. 65. As a second stage in the development of the Arsenal Yard site on which was built the New Police Headquarters referred to in last year's report, an eleven-storey building, consisting of a school on the ground floor and rank and file married quarters above, is to be constructed on the Queen's Road frontage. The school will consist of twelve classrooms, handwork room, domestic science room and teachers' rooms, and there will be 300 quarters above, each consisting of a large living/bedroom, verandah and kitchen with communal lavatory facilities. The flats will have external verandah approach and will be served by a lift. Working drawings were nearing completion. Prisons Department Stanley Prison-Assembly and Dining Hall. 66. This building was completed in June. Quarters for Stanley Training Centre. 67. No work was carried out on this scheme, which was referred to in last year's report, as no funds were provided in the annual estimates. Public Works Department New Electrical and Mechanical Workshops. 68. This scheme, which is a redevelopment of the existing workshops and offices at Caroline Hill, was referred to in last year's report. The first stage—the construction of the mechanical workshops, providing a covered floor area of 52,800 square feet—was completed in December. 13
Baseline (Original)
Lok Ma Chau Police Station Canteen. 64. A new single-storey building was constructed within the existing station compound, consisting of a canteen and additional barrack accommodation. Work was completed in February. Rank and File Quarters, Arsenal Yard. 65. As a second stage in the development of the Arsenal Yard site on which was built the New Police Headquarters referred to in last year's report, an eleven-storey building, con- sisting of a school on the ground floor and rank and file married quarters above, is to be constructed on the Queen's Road frontage. The school will consist of twelve classrooms, hand- work room, domestic science room and teachers' rooms, and there will be 300 quarters above, each consisting of a large living/bedroom, verandah and kitchen with communal lavatory facilities. The flats will have external verandah approach and will be served by a lift. Working drawings were nearing completion. Prisons Department Stanley Prison-Assembly and Dining Hall. 66. This building was completed in June. Quarters for Stanley Training Centre. 67. No work was carried out on this scheme, which was referred to in last year's report, as no funds were provided in the annual estimates. Public Works Department New Electrical and Mechanical Workshops. 68. This scheme, which is a redevelopment of the existing workshops and offices at Caroline Hill, was referred to in last year's report. The first stage-the construction of the mechani- cal workshops, providing a covered floor area of 52,800 square feet-was completed in December. 13
2026-05-11 20:10:57 · Baseline
View content

Lok Ma Chau Police Station Canteen.

64. A new single-storey building was constructed within the existing station compound, consisting of a canteen and additional barrack accommodation. Work was completed in February.

Rank and File Quarters, Arsenal Yard.

65. As a second stage in the development of the Arsenal Yard site on which was built the New Police Headquarters referred to in last year's report, an eleven-storey building, con- sisting of a school on the ground floor and rank and file married quarters above, is to be constructed on the Queen's Road frontage. The school will consist of twelve classrooms, hand- work room, domestic science room and teachers' rooms, and there will be 300 quarters above, each consisting of a large living/bedroom, verandah and kitchen with communal lavatory facilities. The flats will have external verandah approach and will be served by a lift. Working drawings were nearing completion.

Prisons Department

Stanley Prison-Assembly and Dining Hall.

66. This building was completed in June.

Quarters for Stanley Training Centre.

67. No work was carried out on this scheme, which was referred to in last year's report, as no funds were provided in the annual estimates.

Public Works Department

New Electrical and Mechanical Workshops.

68. This scheme, which is a redevelopment of the existing workshops and offices at Caroline Hill, was referred to in last year's report. The first stage-the construction of the mechani- cal workshops, providing a covered floor area of 52,800 square feet-was completed in December.

13

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.