New Territories Administration

Shek Wu Hui Market.

51. This building was completed in May.

San Hui Market.

52. This market, covering an area of about 3,737 square feet, consists of a single-storey building with reinforced concrete columns, steel roof trusses and asbestos roofing. A total of forty stalls are to be provided. The site forms part of an existing pond and filling of the area was completed in February. Working drawings were nearing completion by the end of March.

Latrine at Cheung Chau.

53. Working drawings for this latrine, consisting of twenty-three seats and caretaker's quarters, were completed but work was unable to commence as the site had not been finally approved.

Police Department

Western Police Station and Quarters.

54. This scheme was described in last year's report, and the first stage, consisting of a police station with barrack accommodation for rank and file and quarters for single inspectors above, was completed in June.

55. Construction of the second stage, consisting of a nine-storey block of rank and file quarters providing 112 quarters, was commenced in January and satisfactory progress was maintained.

56. Working drawings for the third stage - an eight-storey block of sixteen flats for married inspectorate staff - were nearing completion.

11

Edit History

2026-05-11 20:10:45 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
New Territories Administration Shek Wu Hui Market. 51. This building was completed in May. San Hui Market. 52. This market, covering an area of about 3,737 square feet, consists of a single-storey building with reinforced concrete columns, steel roof trusses and asbestos roofing. A total of forty stalls are to be provided. The site forms part of an existing pond and filling of the area was completed in February. Working drawings were nearing completion by the end of March. Latrine at Cheung Chau. 53. Working drawings for this latrine, consisting of twenty-three seats and caretaker's quarters, were completed but work was unable to commence as the site had not been finally approved. Police Department Western Police Station and Quarters. 54. This scheme was described in last year's report, and the first stage, consisting of a police station with barrack accommodation for rank and file and quarters for single inspectors above, was completed in June. 55. Construction of the second stage, consisting of a nine-storey block of rank and file quarters providing 112 quarters, was commenced in January and satisfactory progress was maintained. 56. Working drawings for the third stage - an eight-storey block of sixteen flats for married inspectorate staff - were nearing completion. 11
Baseline (Original)
New Territories Administration Shek Wu Hui Market. 51. This building was completed in May. San Hui Market. 52. This market, covering an area of about 3,737 square feet, consists of a single-storey building with reinforced concrete columns, steel roof trusses and asbestos roofing. A total of forty stalls are to be provided. The site forms part of an existing pond and filling of the area was completed in February. Working drawings were nearing completion by the end of March. Latrine at Cheung Chau. 53. Working drawings for this latrine, consisting of twenty- three seats and caretaker's quarters, were completed but work was unable to commence as the site had not been finally approved. Police Department Western Police Station and Quarters. 54. This scheme was described in last year's report, and the first stage, consisting of a police station with barrack accom- modation for rank and file and quarters for single inspectors above, was completed in June. 55. Construction of the second stage, consisting of a nine- storey block of rank and file quarters providing 112 quarters, was commenced in January and satisfactory progress was maintained. 56. Working drawings for the third stage-an eight-storey block of sixteen flats for married inspectorate staff-were nearing completion. 11
2026-05-11 20:10:45 · Baseline
View content

New Territories Administration

Shek Wu Hui Market.

51. This building was completed in May.

San Hui Market.

52. This market, covering an area of about 3,737 square feet, consists of a single-storey building with reinforced concrete columns, steel roof trusses and asbestos roofing. A total of forty stalls are to be provided. The site forms part of an existing pond and filling of the area was completed in February. Working drawings were nearing completion by the end of March.

Latrine at Cheung Chau.

53. Working drawings for this latrine, consisting of twenty- three seats and caretaker's quarters, were completed but work was unable to commence as the site had not been finally approved.

Police Department

Western Police Station and Quarters.

54. This scheme was described in last year's report, and the first stage, consisting of a police station with barrack accom- modation for rank and file and quarters for single inspectors above, was completed in June.

55. Construction of the second stage, consisting of a nine- storey block of rank and file quarters providing 112 quarters, was commenced in January and satisfactory progress was maintained.

56. Working drawings for the third stage-an eight-storey block of sixteen flats for married inspectorate staff-were nearing completion.