1954-1955 — Page 50

Public Works Department Annual Report 工務司署年報 All AI Reviewed

Page 210. The department's two dredging units each comprising a tug, a grab dredger, and three hopper barges were operated continuously in the removal of silt alongside sea walls and at the outfalls of nullahs and stormwater pipes.

Page 211. The dredgers were also made use of in forming marine foundations for a new box culvert at Sung Wong Toi Road, Kowloon. In addition they were used to expose existing cross-harbour water mains and to form a trench to accommodate new cross-harbour water mains where diversion was necessary on account of the new Central Reclamation.

Page 212. A total of 158,000 cubic yards was dredged during the year.

Page 213. Underwater supervision of the work on the diversion of the cross-harbour water mains was undertaken by the Government divers.

Page 214. Diving surveys were made by the Government divers at various piers and sea walls in addition to miscellaneous diving work carried out for the Marine Department and the Police. Underwater work was also carried out for the Drainage Office on an experimental outfall pipe at Tai Kok Tsui.

Page 215. Public dumping at Cheung Sha Wan, Sung Wong Toi, Hung Hom, Ma Tau Kok and Central Reclamations produced a quantity of fill of some 470,000 cubic yards during the year.

New Construction

Page 216. Kun Tong Reclamation. To meet the growing demand for suitable sites for industrial development, Government decided to reclaim some 78 acres at Kun Tong Bay. The main refuse dump in the Colony, which meantime occupies more than half of this area, is to be resited at Gin Drinkers' Bay as described later. It is estimated that approximately 2 million

Page 38.

Edit History

2026-05-11 20:04:44 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Page 210. The department's two dredging units each comprising a tug, a grab dredger, and three hopper barges were operated continuously in the removal of silt alongside sea walls and at the outfalls of nullahs and stormwater pipes. Page 211. The dredgers were also made use of in forming marine foundations for a new box culvert at Sung Wong Toi Road, Kowloon. In addition they were used to expose existing cross-harbour water mains and to form a trench to accommodate new cross-harbour water mains where diversion was necessary on account of the new Central Reclamation. Page 212. A total of 158,000 cubic yards was dredged during the year. Page 213. Underwater supervision of the work on the diversion of the cross-harbour water mains was undertaken by the Government divers. Page 214. Diving surveys were made by the Government divers at various piers and sea walls in addition to miscellaneous diving work carried out for the Marine Department and the Police. Underwater work was also carried out for the Drainage Office on an experimental outfall pipe at Tai Kok Tsui. Page 215. Public dumping at Cheung Sha Wan, Sung Wong Toi, Hung Hom, Ma Tau Kok and Central Reclamations produced a quantity of fill of some 470,000 cubic yards during the year. New Construction Page 216. Kun Tong Reclamation. To meet the growing demand for suitable sites for industrial development, Government decided to reclaim some 78 acres at Kun Tong Bay. The main refuse dump in the Colony, which meantime occupies more than half of this area, is to be resited at Gin Drinkers' Bay as described later. It is estimated that approximately 2 million Page 38.
Baseline (Original)
Page 210. The department's two dredging units each comprising a tug, a grab dredger, and three hopper barges were operated continuously in the removal of silt alongside sea walls and at the outfalls of nullahs and stormwater pipes. 211. The dredgers were also made use of in forming marine foundations for a new box culvert at Sung Wong Toi Road, Kowloon. In addition they were used to expose existing cross- harbour water mains and to form a trench to accommodate new cross harbour water mains where diversion was necessary on account of the new Central Reclamation. 212. A total of 158,000 cubic yards was dredged during the year. 213. Underwater supervision of the work on the diversion of the cross harbour water mains was undertaken by the Govern- ment divers. 214. Diving surveys were made by the Government divers at various piers and sea walls in addition to miscellaneous diving work carried out for the Marine Department and the Police. Underwater work was also carried out for the Drainage Office on an experimental outfall pipe at Tai Kok Tsui. 215. Public dumping at Cheung Sha Wan, Sung Wong Toi, Hung Hom, Ma Tau Kok and Central Reclamations produced a quantity of fill of some 470,000 cubic yards during the year. New Construction 216. Kun Tong Reclamation. To meet the growing demand for suitable sites for industrial development, Government decided to reclaim some 78 acres at Kun Tong Bay. The main refuse dump in the Colony, which meantime occupies more than half of this area, is to be resited at Gin Drinkers' Bay as described later. It is estimated that approximately 2 million 38
2026-05-11 20:04:44 · Baseline
View content

Page

210. The department's two dredging units each comprising a tug, a grab dredger, and three hopper barges were operated continuously in the removal of silt alongside sea walls and at the outfalls of nullahs and stormwater pipes.

211. The dredgers were also made use of in forming marine foundations for a new box culvert at Sung Wong Toi Road, Kowloon. In addition they were used to expose existing cross- harbour water mains and to form a trench to accommodate new cross harbour water mains where diversion was necessary on account of the new Central Reclamation.

212. A total of 158,000 cubic yards was dredged during the

year.

213. Underwater supervision of the work on the diversion of the cross harbour water mains was undertaken by the Govern- ment divers.

214. Diving surveys were made by the Government divers at various piers and sea walls in addition to miscellaneous diving work carried out for the Marine Department and the Police. Underwater work was also carried out for the Drainage Office on an experimental outfall pipe at Tai Kok Tsui.

215. Public dumping at Cheung Sha Wan, Sung Wong Toi, Hung Hom, Ma Tau Kok and Central Reclamations produced a quantity of fill of some 470,000 cubic yards during the year.

New Construction

216. Kun Tong Reclamation. To meet the growing demand for suitable sites for industrial development, Government decided to reclaim some 78 acres at Kun Tong Bay. The main refuse dump in the Colony, which meantime occupies more than half of this area, is to be resited at Gin Drinkers' Bay as described later. It is estimated that approximately 2 million

38

Comments

Approved members can add comments, bookmarks, and private notes.

No comments yet.

Private Research Note

Private notes are available after approval.