23. Ho Tung School. This school is to be erected on the site of the old Belilios Reformatory at Causeway Bay. Sketch plans were commenced in January, 1952, and the accommodation to be provided comprises twelve classrooms, four handwork rooms and a covered play area adaptable for use as an assembly hall.
24. Taipo School and Extensions to King's College. Owing to shortage of staff in the Architectural Office, private architects were commissioned to undertake these works. No building work had commenced at the end of the year.
Medical Department
25. New Wards, Kowloon Hospital. This scheme was referred to in last year's report. Work was completed at the end of August, 1951.
26. Central Medical Dispensary. This scheme was referred to in last year's report. Building work was completed in May, 1951.
27. Extension to Outpatients' Department, Kowloon Hospital. As a result of the serious over-crowding of the existing out-patients and casualty block at Kowloon Hospital, the Architectural Office was instructed in August, 1951, to prepare a scheme for extending the existing building to provide a new casualty block. The scheme provided for a large central working space with adjacent examination cubicles and operating rooms. Building work was commenced in January, 1952 and considerable progress had been made towards completion by the end of March, 1952.
7
23. Ho Tung School. This school is to be erected on the site of the old Belilios Reformatory at Causeway Bay. Sketch plans were commenced in January, 1952, and the accommodation to be provided comprises twelve classrooms, four handwork rooms and a covered play area adaptable for use as an assembly hall.
24. Taipo School and Extensions to King's College. Owing to shortage of staff in the Architectural Office, private architects were commissioned to undertake these works. No building work had commenced at the end of the year.
Medical Department
25. New Wards, Kowloon Hospital. This scheme was referred to in last year's report. Work was completed at the end of August, 1951.
26. Central Medical Dispensary. This scheme was re- ferred to in last year's report. Building work was completed in May, 1951.
27. Extension to Outpatients' Department, Kowloon Hos- pital. As a result of the serious over-crowding of the existing out-patients and casualty block at Kowloon Hospital, the Architectural Office was instructed in August, 1951, to prepare a scheme for extending the existing building to provide a new casualty block. The scheme provided for a large central work- ing space with adjacent examination cubicles and operating rooms. Building work was commenced in January, 1952 and considerable progress had been made towards completion by the end of March, 1952.
7