42. Chief Justice's Residence:-Sketch plans were prepared for a residence for H.H. the Chief Justice but, owing to pressure of work, it was decided to commission private architects to carry out the work.

Rehabilitation Loan.

43. Leighton Hill Quarters:-This work was referred to in paragraph 33 of last year's Annual Report. The Contractors were called in at the end of the six-months' maintenance period to carry out extensive repairs to defective work, chiefly plaster.

44. Peak Pavilion Quarters:-This scheme was referred to in paragraph 34 of last year's Annual Report. Various bills were paid during the year.

45. Queen's Gardens Quarters:-This scheme was referred to in paragraph 35 of last year's Annual Report. The building was completed on 31st May, 1949. (Seven weeks ahead of schedule).

46. King's Park Quarters:-This scheme was referred to in paragraph 36 of last year's Annual Report. The building was completed on 31st October, 1949 (103 weeks ahead of schedule).

47. Kowloon City Police Station:-This scheme was referred to in paragraph 37 of last year's Annual Report. Working drawings were completed during the year and a contract let on 9th September, 1949.

48. Bay View Police Station:-This scheme was referred to in last year's Annual Report. Working drawings were completed during the year and a contract let on 4th May, 1950. At the end of the year the contract was ahead of schedule and nearing completion.

49. Hung Hom Police Station:-This scheme was referred to in paragraph 38 of last year's Annual Report. Working drawings were completed during the year and a contract let on 25th August, 1949. At the end of the year the contract was ahead of schedule and nearing completion.

50. Shaukiwan Police Station: This scheme was referred to in paragraph 40 of last year's Annual Report. Working drawings were completed during the year and a contract let on 14th June, 1949 and completed on 21st March, 1950.

Edit History

2026-05-11 18:40:08 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
42. Chief Justice's Residence:-Sketch plans were prepared for a residence for H.H. the Chief Justice but, owing to pressure of work, it was decided to commission private architects to carry out the work. Rehabilitation Loan. 43. Leighton Hill Quarters:-This work was referred to in paragraph 33 of last year's Annual Report. The Contractors were called in at the end of the six-months' maintenance period to carry out extensive repairs to defective work, chiefly plaster. 44. Peak Pavilion Quarters:-This scheme was referred to in paragraph 34 of last year's Annual Report. Various bills were paid during the year. 45. Queen's Gardens Quarters:-This scheme was referred to in paragraph 35 of last year's Annual Report. The building was completed on 31st May, 1949. (Seven weeks ahead of schedule). 46. King's Park Quarters:-This scheme was referred to in paragraph 36 of last year's Annual Report. The building was completed on 31st October, 1949 (103 weeks ahead of schedule). 47. Kowloon City Police Station:-This scheme was referred to in paragraph 37 of last year's Annual Report. Working drawings were completed during the year and a contract let on 9th September, 1949. 48. Bay View Police Station:-This scheme was referred to in last year's Annual Report. Working drawings were completed during the year and a contract let on 4th May, 1950. At the end of the year the contract was ahead of schedule and nearing completion. 49. Hung Hom Police Station:-This scheme was referred to in paragraph 38 of last year's Annual Report. Working drawings were completed during the year and a contract let on 25th August, 1949. At the end of the year the contract was ahead of schedule and nearing completion. 50. Shaukiwan Police Station: This scheme was referred to in paragraph 40 of last year's Annual Report. Working drawings were completed during the year and a contract let on 14th June, 1949 and completed on 21st March, 1950.
Baseline (Original)
7 42. Chief Justice's Residence:-Sketch plans were pre- pared for a residence for H.H. the Chief Justice but, owing to pressure of work, it was decided to commission private architects to carry out the work. Rehabilitation Loan. 43. Leighton Hill Quarters:-This work was referred to in paragraph 33 of last year's Annual Report. The Contractors were called in at the end of the six-months' maintenance period to carry out extensive repairs to defective work, chiefly plaster. 44. Peak Pavilion Quarters: -This scheme was referred to in paragraph 34 of last year's Annual Report. Various bills were paid during the year. 45. Queen's Gardens Quarters: -This scheme was referred to in paragraph 35 of last year's Annual Report. The building was completed on 31st May, 1949. (Seven weeks ahead of schedule). 46. King's Park Quarters:-This scheme was referred to in paragraph 36 of last year's Annual Report. The building was completed on 31st October, 1949 (103 weeks ahead of schedule). 47. Kowloon City Police Station:-This scheme was re- ferred to in paragraph 37 of last year's Annual Report. Working drawings were completed during the year and a contract let on 9th September, 1949. 48. Bay View Police Station: -This scheme was referred to in last year's Annual Report. Working drawings were com- pleted during the year and a contract let on 4th May, 1950. At the end of the year the contract was ahead of schedule and near- ing completion. 49. Hung Hom Police Station: -This scheme was referred to in paragraph 38 of last year's Annual Report. Working drawings were completed during the year and a contract let on 25th August, 1949. At the end of the year the contract was ahead of schedule and nearing completion. 50. Shaukiwan Police Station: This scheme was referred to in paragraph 40 of last year's Annual Report. Working drawings were completed during the year and a contract let on 14th June, 1949 and completed on 21st March, 1950.
2026-05-11 18:40:08 · Baseline
View content

7

42. Chief Justice's Residence:-Sketch plans were pre- pared for a residence for H.H. the Chief Justice but, owing to pressure of work, it was decided to commission private architects to carry out the work.

Rehabilitation Loan.

43. Leighton Hill Quarters:-This work was referred to in paragraph 33 of last year's Annual Report. The Contractors were called in at the end of the six-months' maintenance period to carry out extensive repairs to defective work, chiefly plaster.

44. Peak Pavilion Quarters: -This scheme was referred to in paragraph 34 of last year's Annual Report. Various bills were paid during the year.

45. Queen's Gardens Quarters: -This scheme was referred to in paragraph 35 of last year's Annual Report. The building was completed on 31st May, 1949. (Seven weeks ahead of schedule).

46. King's Park Quarters:-This scheme was referred to in paragraph 36 of last year's Annual Report. The building was completed on 31st October, 1949 (103 weeks ahead of schedule).

47. Kowloon City Police Station:-This scheme was re- ferred to in paragraph 37 of last year's Annual Report. Working drawings were completed during the year and a contract let on 9th September, 1949.

48. Bay View Police Station: -This scheme was referred to in last year's Annual Report. Working drawings were com- pleted during the year and a contract let on 4th May, 1950. At the end of the year the contract was ahead of schedule and near- ing completion.

49. Hung Hom Police Station: -This scheme was referred to in paragraph 38 of last year's Annual Report. Working drawings were completed during the year and a contract let on 25th August, 1949. At the end of the year the contract was ahead of schedule and nearing completion.

50. Shaukiwan Police Station: This scheme was referred to in paragraph 40 of last year's Annual Report. Working drawings were completed during the year and a contract let on 14th June, 1949 and completed on 21st March, 1950.