69. Dredging Foreshores:-The working cost and capacity of the two Government Grab Dredgers during the year were as follows:
Particulars.
Grab Dredger No. 1. Grab Dredger No. 2. Days working 275 263 Days working for The Hong Kong and Whampoa Dock Co., Ltd. in connection with the salvage of S.S. 'Conte Verde' and S.S. 'Talamba' at Sai Wan, no output being recorded. 15 12 Days under repairs... rd. to 13th Sept. and 18th October to 8th November 1937. 1st to 9th August, 20th September to 18th October, and 15th to 20th December, 1937. Cost of repairs and replacements $3,353.60 $4,049.03 Cube yards of silt removed 45,390.14 43,959.81 All-in cost of removing silt including transportation and deposition but excluding depreciation 34.93 cents 38.35 centsOf the total of 89,349.95 cube yards of silt removed, 76,802 cube yards were dredged from the foreshores and in maintaining depth of water within Causeway Bay Typhoon Shelter, Harbour of Refuge at Yaumati, and alongside Public Piers; 2,595.14 cube yards were dredged on behalf of the Admiralty; whilst 9,952.81 cube yards were dredged in connection with the formation of bed for the New Cross Harbour Water Mains, the cost of which was met by Special Warrant No. 86 of 1937. 6,879.28 cube yards of silt dredged were utilized in covering scavenging refuse dumped at Kun Tong.
Expenditure $21,698.09
Q 20
69. Dredging Foreshores:-The working cost and capacity of the two Government Grab Dredgers during the year were as follows:
Particulars.
Grab Dredger No. 1. Grab Dredger No. 2.
Days working
Days working for The Hong Kong and Whampoa Dock Co., Ltd. in con- nection with
with the salvage of S.S. 'Conte Verde' and S.S. Talamba' at Sai Wan, no out- put being recorded.
Days under repairs...
Cost of repairs and
replacements
Cube yards of silt
removed
All-in cost of remov- ing silt including transportation and deposition but ex- cluding deprecia- tion
275
15
rd. to 13th. Sept. and 18th. October to 8th. November 1937.
$ 3,353.60
45,390.14
34.93 cents
263
12
1st. to 9th. August, 20th. September to 18th. October, and 15th. to 20th. December, 1937.
$ 4,049.03
43,959.81
38.35 cents
Of the total of 89,349.95 cube yards of silt removed, 76,802 cube yards were dredged from the foreshores and in maintaining depth of water within Causeway Bay Typhoon Shelter, Harbour of Refuge at Yaumati, and alongside Public Piers; 2,595.14 cube yards were dredged on behalf of the Admiralty; whilst 9,952.81 cube yards were dredged in connection with the formation of bed for the New Cross Harbour Water Mains, the cost of which was met by Special Warrant No. 86 of 1937. 6,879.28 cube yards of silt dredged were utilized in covering scavenging refuse dumped at Kun Tong.
Expenditure
$21,698.09