1936 — Page 48

Public Works Department Annual Report 工務司署年報 All AI Reviewed

Q 46

Street near Pak Hoi Street and 260 feet of 2" wrought iron piping were laid at Ho Mun Tin Hill as an extension to Kowloon Inland Lot No. 3355.

Expenditure

$3,900.73

(b) Meters :- 310 meters were issued from Store and charged to this head during the year.

Expenditure

$20,774.05

158. Port Works:- Expenditure under this head was for the transportation of rail tracks, tipping waggons, etc., from Sung Wong Toi Refuse Dump to Hung Hom Government Store, and the installation of a navigation light at Ma Tau Kok Refuse Boat Pier.

159.

Expenditure

MISCELLANEOUS.

$382.41

Flush Latrine—Junction of Prince Edward Road and Boundary Street :- No expenditure was incurred as it was decided to postpone this work.

Expenditure

$ Nil

160. Conversion of Dry to Flush-Hung Hom Market:- It was decided not to proceed with this work and therefore no expenditure was incurred.

Expenditure

$ Nil

161. Postal Kiosk-Hung Hom Market:- It was decided to postpone this work and therefore no expenditure was incurred.

Expenditure

$ Nil

162. Coal Bins—Yaumati Slipway:— Sketch plans were prepared but it was decided to postpone the work and therefore no expenditure was incurred.

Expenditure

$ Nil

163. Exhumation of Chinese Cemeteries:- No expenditure was incurred during the year.

Expenditure

$ Nil.

164. Chinese Cemeteries-Laying out new areas:- Work carried out under this head is covered by paragraph 43 of the Report.

Expenditure

$4,937.60

Edit History

2026-05-11 15:39:57 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Q 46 Street near Pak Hoi Street and 260 feet of 2" wrought iron piping were laid at Ho Mun Tin Hill as an extension to Kowloon Inland Lot No. 3355. Expenditure $3,900.73 (b) Meters :- 310 meters were issued from Store and charged to this head during the year. Expenditure $20,774.05 158. Port Works:- Expenditure under this head was for the transportation of rail tracks, tipping waggons, etc., from Sung Wong Toi Refuse Dump to Hung Hom Government Store, and the installation of a navigation light at Ma Tau Kok Refuse Boat Pier. 159. Expenditure MISCELLANEOUS. $382.41 Flush Latrine—Junction of Prince Edward Road and Boundary Street :- No expenditure was incurred as it was decided to postpone this work. Expenditure $ Nil 160. Conversion of Dry to Flush-Hung Hom Market:- It was decided not to proceed with this work and therefore no expenditure was incurred. Expenditure $ Nil 161. Postal Kiosk-Hung Hom Market:- It was decided to postpone this work and therefore no expenditure was incurred. Expenditure $ Nil 162. Coal Bins—Yaumati Slipway:— Sketch plans were prepared but it was decided to postpone the work and therefore no expenditure was incurred. Expenditure $ Nil 163. Exhumation of Chinese Cemeteries:- No expenditure was incurred during the year. Expenditure $ Nil. 164. Chinese Cemeteries-Laying out new areas:- Work carried out under this head is covered by paragraph 43 of the Report. Expenditure $4,937.60
Baseline (Original)
Q 46 Street near Pak Hoi Street and 260 feet of 2" wrought iron piping were laid at Ho Mun Tin Hill as an extension to Kowloon Inland Lot No. 3355. Expenditure $3,900.73 (b) Meters :-310 meters were issued from Store and charged to this head during the year. Expenditure $20,774.05 158. Port Works:-Expenditure under this head was for the transportation of rail tracks, tipping waggons, etc., from Sung Wong Toi Refuse Dump to Hung Hom Government Store, and the installation of a navigation light at Ma Tau Kok Refuse Boat Pier. 159. Expenditure MISCELLANEOUS. $ 382.41 Flush Latrine—Junction of Prince Edward Road and Boundary Street :-No expenditure was incurred as it was decided to postpone this work. Expenditure $ Nil 160. Conversion of Dry to Flush-Hung Hom Market:- It was decided not to proceed with this work and therefore no expenditure was incurred. Expenditure $ Nil 161. Postal Kiosk-Hung Hom Market:-It was decided to postpone this work and therefore no expenditure was incurred. Expenditure $ Nil 162. Coal Bins—Yaumati Slipway:—Sketch plans were prepared but it was decided to postpone the work and there- fore no expenditure was incurred. Expenditure $ Nil 163. Exhumation of Chinese Cemeteries:-No expendi- ture was incurred during the year. Expenditure $ Nil. 164. Chinese Cemeteries-Laying out new areas:-Work carried out under this head is covered by paragraph 43 of the Report. Expenditure $4,937.60
2026-05-11 15:39:57 · Baseline
View content

Q 46

Street near Pak Hoi Street and 260 feet of 2" wrought iron piping were laid at Ho Mun Tin Hill as an extension to Kowloon Inland Lot No. 3355.

Expenditure

$3,900.73

(b) Meters :-310 meters were issued from Store and charged to this head during the year.

Expenditure

$20,774.05

158. Port Works:-Expenditure under this head was for the transportation of rail tracks, tipping waggons, etc., from Sung Wong Toi Refuse Dump to Hung Hom Government Store, and the installation of a navigation light at Ma Tau Kok Refuse Boat Pier.

159.

Expenditure

MISCELLANEOUS.

$ 382.41

Flush Latrine—Junction of Prince Edward Road and Boundary Street :-No expenditure was incurred as it was decided to postpone this work.

Expenditure

$ Nil

160. Conversion of Dry to Flush-Hung Hom Market:- It was decided not to proceed with this work and therefore no expenditure was incurred.

Expenditure

$ Nil

161. Postal Kiosk-Hung Hom Market:-It was decided to postpone this work and therefore no expenditure was incurred.

Expenditure

$ Nil

162. Coal Bins—Yaumati Slipway:—Sketch plans were prepared but it was decided to postpone the work and there- fore no expenditure was incurred.

Expenditure

$ Nil

163. Exhumation of Chinese Cemeteries:-No expendi- ture was incurred during the year.

Expenditure

$ Nil.

164. Chinese Cemeteries-Laying out new areas:-Work carried out under this head is covered by paragraph 43 of the Report.

Expenditure

$4,937.60