78. Maintenance of Buildings.-Government Buildings were kept in a good state of repair. Painting, colourwashing and repairs in accordance with the recurring programme were carried out to seven buildings. Major repairs included:-Lai Chi Kok Prison-alterations to Hot Water System, Kowloon City Police Station-alterations to Charge Room, Cheung Sha Wan Market-renewal of matsheds.

Expenditure $7,170.59

79. Improvements to Buildings.-The principal improvements carried out under this head were as follows:-Sham Shui Po Police Station-alterations to Charge Room, Lai Chi Kok Prison-provision of sunshades to Warders' Quarters and alterations to drainage, Kowloon City Police Station-plastering to Offices and Barrack Rooms.

Expenditure $3,046.84

80. Roads and Bridges (Maintenance and Improvements).-The surfaces of approximately 83 miles of roads were maintained in a satisfactory condition.

The following are particulars of the additional areas laid with improved surfacing during the year:

(1) Tarring and sanding 44,906 (2) 2½" granolithic paving laid on footways 14,501 (3) Slab paving laid on footways. 2,202 (4) New dry macadam surfacing. 44,906

Expenditure $24,292.82

81. Maintenance of Telephones.-The lines and instruments were maintained in good order.

Expenditure $396.74

82. Maintenance of Sewers, Nullahs, etc.-The sewers, storm water drains, and trained nullahs were cleansed, repaired, and maintained in good condition, the open channels and nullahs being cleansed by the Sanitary Department. Sand deposits, as

Edit History

2026-05-11 14:36:45 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
25 NEW KOWLOON. 78. Maintenance of Buildings.-Government Buildings were kept in a good state of repair. Painting, colourwashing and repairs in accordance with the recurring programme were carried out to seven buildings. Major repairs included:-Lai Chi Kok Prison-alterations to Hot Water System, Kowloon City Police Station-alterations to Charge Room, Cheung Sha Wan Market-renewal of matsheds. Expenditure $7,170.59 79. Improvements to Buildings.-The principal improvements carried out under this head were as follows:-Sham Shui Po Police Station-alterations to Charge Room, Lai Chi Kok Prison-provision of sunshades to Warders' Quarters and alterations to drainage, Kowloon City Police Station-plastering to Offices and Barrack Rooms. Expenditure $3,046.84 80. Roads and Bridges (Maintenance and Improvements).-The surfaces of approximately 83 miles of roads were maintained in a satisfactory condition. The following are particulars of the additional areas laid with improved surfacing during the year: (1) Tarring and sanding 44,906 (2) 2½" granolithic paving laid on footways 14,501 (3) Slab paving laid on footways. 2,202 (4) New dry macadam surfacing. 44,906 Expenditure $24,292.82 81. Maintenance of Telephones.-The lines and instruments were maintained in good order. Expenditure $396.74 82. Maintenance of Sewers, Nullahs, etc.-The sewers, storm water drains, and trained nullahs were cleansed, repaired, and maintained in good condition, the open channels and nullahs being cleansed by the Sanitary Department. Sand deposits, as
Baseline (Original)
25 - NEW KOWLOON. 78. Maintenance of Buildings.-Government Buildings were kept in a good state of repair. Painting, colourwashing and re- pairs in accordance with the recurring programme were carried out to seven buildings. Major repairs included:-Lai Chi Kok Frison-alterations to Hot Water System, Kowloon City Police Station-alterations to Charge Room, Cheung Sha Wan Market- renewal of matsheds. Expenditure $7,170.59 79. Improvements to Buildings.-The principal improve- ments carried out under this head were as follows:-Sham Shui Po Police Station-alterations to Charge Room, Lai Chi Kok Prison-provision of sunshades to Warders' Quarters and altera- tions to drainage, Kowloon City Police Station-plastering to Offices and Barrack Rooms. Expenditure $3,046.84 80. Roads and Bridges (Maintenance and Improvements), The surfaces of approximately 83 miles of roads were maintained in a satisfactory condition. The following are particulars of the additional areas laid with improved surfacing during the year:- Square yards. (1) Tarring and sanding 44,906 (2) 21" granolithic paving laid on footways 14,501 (3) Slab paving laid on footways. 2,202 (4) New dry macadam surfacing. 44,906 Expenditure $24,292.82 81. Maintenance of Telephones.-The lines and instruments were maintained in good order. Expenditure $396.74 82. Maintenance of Sewers, Nullahs, etc.-The sewers, storm water drains, and trained nullahs were cleansed, repaired, and maintained in good condition, the open channels and nullahs being cleansed by the Sanitary Department. Sand deposits, as
2026-05-11 14:36:45 · Baseline
View content

25

-

NEW KOWLOON.

78. Maintenance of Buildings.-Government Buildings were kept in a good state of repair. Painting, colourwashing and re- pairs

in accordance with the recurring programme were carried out to seven buildings. Major repairs included:-Lai Chi Kok Frison-alterations to Hot Water System, Kowloon City Police Station-alterations to Charge Room, Cheung Sha Wan Market- renewal of matsheds.

Expenditure

$7,170.59

79. Improvements to Buildings.-The principal improve- ments carried out under this head were as follows:-Sham Shui Po Police Station-alterations to Charge Room, Lai Chi Kok Prison-provision of sunshades to Warders' Quarters and altera- tions to drainage, Kowloon City Police Station-plastering to Offices and Barrack Rooms.

Expenditure

$3,046.84

80. Roads and Bridges (Maintenance and Improvements), The surfaces of approximately 83 miles of roads were maintained in a satisfactory condition.

The following are particulars of the additional areas laid with improved surfacing during the year:-

Square yards.

(1) Tarring and sanding

44,906

(2) 21" granolithic paving laid on footways

14,501

(3) Slab paving laid on footways.

2,202

(4) New dry macadam surfacing.

44,906

Expenditure

$24,292.82

81. Maintenance of Telephones.-The lines and instruments were maintained in good order.

Expenditure

$396.74

82. Maintenance of Sewers, Nullahs, etc.-The sewers, storm water drains, and trained nullahs were cleansed, repaired, and maintained in good condition, the open channels and nullahs being cleansed by the Sanitary Department. Sand deposits, as