concrete; G.C.H. "B" Block—Extensive repairs to roof. Ninety-two radiators were cleaned and overhauled, and electrical installation in sixty-nine Government buildings tested and repaired.

Expenditure $111,644.14

70. Improvements to Buildings. The principal improvements carried out under this heading were as follows:-
"Lysholt"—Additional Servants Quarters, etc.; G.C.H. "A" Block—Alterations and additions to provide extra office accommodation; New Government Offices (Post Office Building)—Conversion of Office into Lavatory and alterations to partitions in Broadcasting Studio.

Expenditure $12,622.00

71. Maintenance of Roads and Bridges in City and Improvements to Roads and Bridges in City. The surfaces of approximately seventy-one miles of roads were maintained in a satisfactory condition. The asphaltum treatment of the carriageways was further extended.

72. The following figures show the extent of the operations carried out at the Government Quarry, Tsat Tsz Mui, during the year.

A total quantity of 14,290 cubic yards of various grades of stone were passed through crushers, of which 3,787 cubic yards were made into tar macadam, 1,490 cubic yards into sand-carpeting and 9,013 cubic yards were delivered to various works as the material came from crushers. 41,327 granolithic paving slabs were provided for use on footways, 181 reinforced concrete standards for railings, and 200 concrete pickets were made.

73. The following are particulars of the additional areas laid with improved surfacing during the year:

Tarring and sanding Square yards. 3,588 21" granolithic paving slabs laid on footways 14,601 Asphaltic sand-carpeting laid on 6" cement concrete foundation 12,855 Expenditure $79,884.99

74. Maintenance of Roads and Bridges Outside City and Improvements to Roads and Bridges Outside City. The road surfaces of approximately ninety miles of roads were maintained in a satisfactory condition.

75. The following are particulars of the improved surfacing introduced on a number of roads in addition to those mentioned in previous reports:

Tarring and sanding... Square yards. 43,729 21" granolithic paving slabs laid on footways 694 Expenditure $79,860.76

Edit History

2026-05-11 13:57:19 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
P.W.R. Hong Kong. concrete; G.C.H. "B" Block—Extensive repairs to roof. Ninety-two radiators were cleaned and overhauled, and electrical installation in sixty-nine Government buildings tested and repaired. Expenditure $111,644.14 70. Improvements to Buildings. The principal improvements carried out under this heading were as follows:- "Lysholt"—Additional Servants Quarters, etc.; G.C.H. "A" Block—Alterations and additions to provide extra office accommodation; New Government Offices (Post Office Building)—Conversion of Office into Lavatory and alterations to partitions in Broadcasting Studio. Expenditure $12,622.00 71. Maintenance of Roads and Bridges in City and Improvements to Roads and Bridges in City. The surfaces of approximately seventy-one miles of roads were maintained in a satisfactory condition. The asphaltum treatment of the carriageways was further extended. 72. The following figures show the extent of the operations carried out at the Government Quarry, Tsat Tsz Mui, during the year. A total quantity of 14,290 cubic yards of various grades of stone were passed through crushers, of which 3,787 cubic yards were made into tar macadam, 1,490 cubic yards into sand-carpeting and 9,013 cubic yards were delivered to various works as the material came from crushers. 41,327 granolithic paving slabs were provided for use on footways, 181 reinforced concrete standards for railings, and 200 concrete pickets were made. 73. The following are particulars of the additional areas laid with improved surfacing during the year: Tarring and sanding Square yards. 3,588 21" granolithic paving slabs laid on footways 14,601 Asphaltic sand-carpeting laid on 6" cement concrete foundation 12,855 Expenditure $79,884.99 74. Maintenance of Roads and Bridges Outside City and Improvements to Roads and Bridges Outside City. The road surfaces of approximately ninety miles of roads were maintained in a satisfactory condition. 75. The following are particulars of the improved surfacing introduced on a number of roads in addition to those mentioned in previous reports: Tarring and sanding... Square yards. 43,729 21" granolithic paving slabs laid on footways 694 Expenditure $79,860.76
Baseline (Original)
11 P.W.R. Hong Kong. ! concrete; G.C.H. "B" Block-Extensive repairs to roof. Ninety-two radiators were cleaned and overhaulểu, and electrical installation in sixty-nine Government buildings tested and repaired. Expenditure $111,644.14 70. Improvements to Buildings. The principal improve- ments carried out under this heading were as follows:- "Lysholt"-Additional Servants Quarters, etc.; G.C.H. "A" Block-Alterations and additions to provide extra office accommodation; New Government Offices (Post Office Building)—Conversion of Office into Lavatory and alterations to partitions in Broadcasting Studio. Expenditure $ 12,622.00 71. Maintenance of Roads and Bridges in City and Im- provements to Roads and Bridges in City. The surfaces of ap- proximately seventy-one miles of roads were maintained in a satisfactory condition. The asphaltum treatment of the carriage- ways was further extended. 72. The following figures show the extent of the operations carried out at the Government Quarry, Tsat Tsz Mui, during the year. A total quantity of 14,290 cubic yards of various grades of stone were passed through crushers, of which 3,787 cubic yards were made into tar macadam, 1,490 cubic yards into sand-carpeting and 9,013 cubic yards were delivered to various works as the material came from crushers. 41,327 granolithic paving slabs were provided for use on footways, 181 reinforced concrete standards for railings, and 200 concrete pickets were made. 73. The following are particulars of the additional areas laid with improved surfacing during the year: Tarring and sanding 21" granolithic paving slabs laid on footways Asphaltic sand-carpeting laid on 6" cement concrete foundation Expenditure Square yards. 3,588 14,601 12,855 $79,884.99 74. Maintenance of Roads and Bridges Outside City and Improvements to Roads and Bridges Outside City. The road surfaces of approximately ninety miles of roads were maintained in a satisfactory condition. 75. The following are particulars of the improved surfacing introduced on a number of roads in addition to those mentioned in previous reports:- Tarring and sanding... 21" granolithic paving slabs laid on footways Expenditure Square yards. 43,729 694 $79,860.76
2026-05-11 13:57:19 · Baseline
View content

11

P.W.R. Hong Kong.

!

concrete; G.C.H. "B" Block-Extensive repairs to roof. Ninety-two radiators were cleaned and overhaulểu, and electrical installation in sixty-nine Government buildings tested and repaired.

Expenditure

$111,644.14

70. Improvements to Buildings. The principal improve- ments carried out under this heading were as follows:-

"Lysholt"-Additional Servants Quarters, etc.; G.C.H. "A" Block-Alterations and additions to provide extra office accommodation; New Government Offices (Post Office Building)—Conversion of Office into Lavatory and alterations to partitions in Broadcasting Studio.

Expenditure

$ 12,622.00

71. Maintenance of Roads and Bridges in City and Im- provements to Roads and Bridges in City. The surfaces of ap- proximately seventy-one miles of roads were maintained in a satisfactory condition. The asphaltum treatment of the carriage- ways was further extended.

72. The following figures show the extent of the operations carried out at the Government Quarry, Tsat Tsz Mui, during the year.

A total quantity of 14,290 cubic yards of various grades of stone were passed through crushers, of which 3,787 cubic yards were made into tar macadam, 1,490 cubic yards into sand-carpeting and 9,013 cubic yards were delivered to various works as the material came from crushers. 41,327 granolithic paving slabs were provided for use on footways, 181 reinforced concrete standards for railings, and 200 concrete pickets were made.

73. The following are particulars of the additional areas laid with improved surfacing during the year:

Tarring and sanding

21" granolithic paving slabs laid on footways Asphaltic sand-carpeting laid on 6" cement

concrete foundation

Expenditure

Square yards.

3,588

14,601

12,855

$79,884.99

74. Maintenance of Roads and Bridges Outside City and Improvements to Roads and Bridges Outside City. The road surfaces of approximately ninety miles of roads were maintained in a satisfactory condition.

75. The following are particulars of the improved surfacing introduced on a number of roads in addition to those mentioned in previous reports:-

Tarring and sanding...

21" granolithic paving slabs laid on footways

Expenditure

Square yards.

43,729

694

$79,860.76