1930 — Page 67

Public Works Department Annual Report 工務司署年報 All AI Reviewed

63

P.W.E. Hong Kong.

118. Training Nullahs.-The following are the most important nullah works carried out during the year:—

Locality. Description of work. Length trained (in feet). Re- marks. Repulse Bay Nullah training from Road to South of R.B.L. 177 to fore- shore at East of R.B.L. 159... 319' Com- pleted. Kennedy Town ... of I.L. 1082 West of Cad- ogan Street... 174' Nullah training from southern lot boundary of R.B.L. 200 to point near foreshore. 173' * Shaukiwan East... Wongueichong Parapet walling around exis- ting nullah at Shaukiwan East near Tram Terminus... 750′ "" Tai Hang Construction of wing walls at head of Village Road nullah, south of I. L. 2456 ... 27' "" Parapet walling on east side of Tai Hang nullah adjacent to I.L. 2477 418' Sookunpoo Parapet walling around Soo- kunpoo nullah from point opposite French Hospital to Causeway Bay 582' - "1 Stanley Peninsula. Channels below Septic Tanks serving St. Stephen's Col- lege Stanley Peninsula 458' Bowen Road Channel West of Military Hospital, Bowen Road 244' "" Macdonnell Road.. Channel in Botanical Garden opposite Macdonnell Road... 169' "" Pokfulam Improvements to Pokfulam nullah below No, 8 Bridge... A Estimates $25,000.00 Expenditure $15,962.70

Edit History

2026-05-11 13:04:56 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
63 P.W.E. Hong Kong. 118. Training Nullahs.-The following are the most important nullah works carried out during the year:— Locality. Description of work. Length trained (in feet). Re- marks. Repulse Bay Nullah training from Road to South of R.B.L. 177 to fore- shore at East of R.B.L. 159... 319' Com- pleted. Kennedy Town ... of I.L. 1082 West of Cad- ogan Street... 174' Nullah training from southern lot boundary of R.B.L. 200 to point near foreshore. 173' * Shaukiwan East... Wongueichong Parapet walling around exis- ting nullah at Shaukiwan East near Tram Terminus... 750′ "" Tai Hang Construction of wing walls at head of Village Road nullah, south of I. L. 2456 ... 27' "" Parapet walling on east side of Tai Hang nullah adjacent to I.L. 2477 418' Sookunpoo Parapet walling around Soo- kunpoo nullah from point opposite French Hospital to Causeway Bay 582' - "1 Stanley Peninsula. Channels below Septic Tanks serving St. Stephen's Col- lege Stanley Peninsula 458' Bowen Road Channel West of Military Hospital, Bowen Road 244' "" Macdonnell Road.. Channel in Botanical Garden opposite Macdonnell Road... 169' "" Pokfulam Improvements to Pokfulam nullah below No, 8 Bridge... A Estimates $25,000.00 Expenditure $15,962.70
Baseline (Original)
. 63 P.W.E. Hong Kong. 118. Training Nullahs.-The following are the most im- portant nullah works carried out during the year:— Locality. Description of work. Length trained (in feet). Re- marks. Repulse Bay Nullah training from Road to South of R.B.L. 177 to fore- shore at East of R.B.L. 159... 319' Com- pleted. Kennedy Town ... of I.L. 1082 West of Cad- ogan Street... 174' Nullah training from southern lot boundary of R.B.L. 200 to point near foreshore. Extension of nullah to south 173' * Shaukiwan East... Parapet walling around exis- Wongueichong Tai Hang Sookunpoo ting nullah at Shaukiwan East near Tram Terminus... Construction of wing walls at head of Village Road nullah, south of I. L. 2456 ... Parapet walling on east side of Tai Hang nullah adjacent to I.L. 2477 Parapet walling around Soo- kunpoo nullah from point opposite French Hospital to Causeway Bay Stanley Peninsula. Channels below Septic Tanks 750′ "" 27' "" 418' 582' - "1 serving St. Stephen's Col- lege Stanley Peninsula 458' Bowen Road Channel West of Military Hospital, Bowen Road 244' "" Macdonnell Road.. Channel in Botanical Garden Pokfulam opposite Macdonnell Road... 169' "" Improvements to Pokfulam nullah below No, 8 Bridge... A Estimates $25,000.00 Expenditure $15,962.70
2026-05-11 13:04:56 · Baseline
View content

.

63

P.W.E. Hong Kong.

118. Training Nullahs.-The following are the most im- portant nullah works carried out during the year:—

Locality.

Description of work.

Length trained (in feet).

Re- marks.

Repulse Bay

Nullah training from Road to South of R.B.L. 177 to fore- shore at East of R.B.L. 159...

319' Com-

pleted.

Kennedy Town

...

of I.L. 1082 West of Cad- ogan Street...

174'

Nullah training from southern lot boundary of R.B.L. 200 to point near foreshore.

Extension of nullah to south

173'

*

Shaukiwan East... Parapet walling around exis-

Wongueichong

Tai Hang

Sookunpoo

ting nullah at Shaukiwan East near Tram Terminus...

Construction of wing walls at head of Village Road nullah, south of I. L. 2456 ...

Parapet walling on east side of Tai Hang nullah adjacent to I.L. 2477

Parapet walling around Soo- kunpoo nullah from point opposite French Hospital to Causeway Bay

Stanley Peninsula. Channels below Septic Tanks

750′

""

27'

""

418'

582'

-

"1

serving St. Stephen's Col- lege Stanley Peninsula

458'

Bowen Road

Channel West of Military

Hospital, Bowen Road

244'

""

Macdonnell Road.. Channel in Botanical Garden

Pokfulam

opposite Macdonnell Road...

169'

""

Improvements to Pokfulam

nullah below No, 8 Bridge...

A

Estimates

$25,000.00

Expenditure

$15,962.70

Comments