1930 — Page 57

Public Works Department Annual Report 工務司署年報 All AI Reviewed

53

P.W.R. New Kowloon.

P. W. R. NEW KOWLOON.

81. Maintenance of Buildings.--Government Buildings were kept in a good state of repair.

Painting, colourwashing and repairs in accordance with the recurring programme were carried out to 3 buildings.

Major repairs included the following:-

Made good compound, etc., at Rennies Mills, Refitted windows, etc., at Lai Chi Kok Prison, Repairs to Boundary wall and fencing Lai Chi Kok Prison, Repairs to compounds at Sham Shui Po and Kowloon City Police Stations.

The electrical installations were maintained in good order.

Aerial cable in Lai Chi Kok Prison was rewired.

Estimates $8,000.00

Expenditure $6,392.03

82. Improvements to Buildings.-The principal improvements carried out under this heading were as follows:

Hanging rails and hooks at Kowloon City Market, Wire netting to cells at Sham Shui Po and Kowloon City Police Stations.

Estimates $2,000.00

Expenditure $934.46

83. Maintenance of Roads and Bridges. Improvements to Roads and Bridges.

Approximately 83 miles of roads.---The road surfaces were generally maintained in a satisfactory manner.

The following are particulars of the additional areas laid with improved surfacing during the year.

(1). Tarring and sanding Square yards. 56,000

(2). 21′′ granolithic paving slabs laid on footways 9,541

(3). New dry macadam surfacing 9,300

Estimates $32,000.00

Expenditure $31,623.97

Edit History

2026-05-11 12:52:31 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
53 P.W.R. New Kowloon. P. W. R. NEW KOWLOON. 81. Maintenance of Buildings.--Government Buildings were kept in a good state of repair. Painting, colourwashing and repairs in accordance with the recurring programme were carried out to 3 buildings. Major repairs included the following:- Made good compound, etc., at Rennies Mills, Refitted windows, etc., at Lai Chi Kok Prison, Repairs to Boundary wall and fencing Lai Chi Kok Prison, Repairs to compounds at Sham Shui Po and Kowloon City Police Stations. The electrical installations were maintained in good order. Aerial cable in Lai Chi Kok Prison was rewired. Estimates $8,000.00 Expenditure $6,392.03 82. Improvements to Buildings.-The principal improvements carried out under this heading were as follows: Hanging rails and hooks at Kowloon City Market, Wire netting to cells at Sham Shui Po and Kowloon City Police Stations. Estimates $2,000.00 Expenditure $934.46 83. Maintenance of Roads and Bridges. Improvements to Roads and Bridges. Approximately 83 miles of roads.---The road surfaces were generally maintained in a satisfactory manner. The following are particulars of the additional areas laid with improved surfacing during the year. (1). Tarring and sanding Square yards. 56,000 (2). 21′′ granolithic paving slabs laid on footways 9,541 (3). New dry macadam surfacing 9,300 Estimates $32,000.00 Expenditure $31,623.97
Baseline (Original)
53 P.W.R. New Kowloon. P. W. R. NEW KOWLOON. 81. Maintenance of Buildings.--Government Buildings were kept in a good state of repair. Painting, colourwashing and repairs in accordance with the recurring programme were carried out to 3 buildings. Major repairs included the following:- Made good compound, etc., at Rennies Mills, Refitted windows, etc., at Lai Chi Kok Prison, Repairs to Boundary wall and fencing Lai Chi Kok Prison, Repairs to compounds at Sham Shui Po and Kowloon City Police Stations. The electrical installations were maintained in good order. Aerial cable in Lai Chi Kok Prison was rewired. Estimates Expenditure $8,000.00 $6,392.03 82. Improvements to Buildings.-The principal improve- ments carried out under this heading were as follows: Hanging rails and hooks at Kowloon City Market, Wire netting to cells at Sham Shui Po and Kowloon City Police Stations. Estimates $2,000.00 Expenditure 83. Maintenance of Roads and Bridges. Improvements to Roads and Bridges. $ 934.46 Approximately 83 miles of roads.---The road surfaces were generally maintained in a satisfactory manner. The following are particulars of the additional areas laid with improved surfacing during the year. (1). Tarring and sanding Square yards. 56,000 (2). 21′′ granolithic paving slabs laid on footways 9,541 (3). New dry macadam surfacing 9,300 Estimates Expenditure $32,000.00 $31,623.97
2026-05-11 12:52:31 · Baseline
View content

53

P.W.R. New Kowloon.

P. W. R. NEW KOWLOON.

81. Maintenance of Buildings.--Government Buildings were kept in a good state of repair.

Painting, colourwashing and repairs in accordance with the recurring programme were carried out to 3 buildings.

Major repairs included the following:-

Made good compound, etc., at Rennies Mills, Refitted windows, etc., at Lai Chi Kok Prison, Repairs to Boundary wall and fencing Lai Chi Kok Prison, Repairs to compounds at Sham Shui Po and Kowloon City Police Stations.

The electrical installations were maintained in good order.

Aerial cable in Lai Chi Kok Prison was rewired.

Estimates

Expenditure

$8,000.00

$6,392.03

82. Improvements to Buildings.-The principal improve- ments carried out under this heading were as follows:

Hanging rails and hooks at Kowloon City Market, Wire netting to cells at Sham Shui Po and Kowloon City Police Stations.

Estimates

$2,000.00

Expenditure

83. Maintenance of Roads and Bridges.

Improvements to Roads and Bridges.

$ 934.46

Approximately

83 miles of roads.---The road surfaces were generally maintained

in a satisfactory manner.

The following are particulars of the additional areas laid with improved surfacing during the year.

(1). Tarring and sanding

Square yards.

56,000

(2). 21′′ granolithic paving slabs laid

on

footways

9,541

(3). New dry macadam surfacing

9,300

Estimates

Expenditure

$32,000.00

$31,623.97