Works not appearing in Estimates.-New Kowloon.

110

232. Traffic Arrangement at Tsim Sha Tsui.-Alterations to the traffic arrangements at Tsim Sha Tsui were commenced towards the end of the year. This work consisted of the demolition of and re-erection on other sites of the existing Motor car shelter, Ricksha shelter, Motor Cycle shelter and Latrine.

Contract was let to Messrs. Kin Lee & Co. in November and December and by the end of the year the greater part of the work was done.

Special Vote Expenditure

$11,060.00 $7,715.16

233. New Children's Playground, Kowloon.-This work was referred to in paragraph 177 of last year's Report.

A contract for the erection of the Shelter, Swings, etc. was let to Messrs. Kin Lee & Co. in July, the amount being $6,855.35.

The work was commenced immediately and was completed early in October. The turfing of the whole playground was then commenced by the Botanical and Forestry Department and was completed by the end of October.

Special Vote Expenditure

$12,700.00 $11,221.99

234. Tong Mi-Extension of Storm Water Drain from Old Taipo Road to Kowloon Tong Village area.—The work, referred to in paragraph 192 of last year's Report, could not be started during the year as the layout of blocks to east of Nathan Square was still in abeyance.

Special Vote Expenditure

Expenditure to 31.12.30

$7,000.00 Nil. $15,000.00 $7,891.29

Total Estimates

NEW KOWLOON.

Servants Quarters and

235. Field Cottage-Additional Servants Quarters and reconditioning of building as Headquarters of the Flying Club. The work consisted of the addition of three small rooms and a coal Store for each of three floors of the Servants Quarters and the general renovation of the Main Building.

The work, which was executed under the Maintenance of Buildings Contract, was commenced in February and completed in August.

Edit History

2026-05-11 13:30:54 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
Works not appearing in Estimates.-New Kowloon. 110 232. Traffic Arrangement at Tsim Sha Tsui.-Alterations to the traffic arrangements at Tsim Sha Tsui were commenced towards the end of the year. This work consisted of the demolition of and re-erection on other sites of the existing Motor car shelter, Ricksha shelter, Motor Cycle shelter and Latrine. Contract was let to Messrs. Kin Lee & Co. in November and December and by the end of the year the greater part of the work was done. Special Vote Expenditure $11,060.00 $7,715.16 233. New Children's Playground, Kowloon.-This work was referred to in paragraph 177 of last year's Report. A contract for the erection of the Shelter, Swings, etc. was let to Messrs. Kin Lee & Co. in July, the amount being $6,855.35. The work was commenced immediately and was completed early in October. The turfing of the whole playground was then commenced by the Botanical and Forestry Department and was completed by the end of October. Special Vote Expenditure $12,700.00 $11,221.99 234. Tong Mi-Extension of Storm Water Drain from Old Taipo Road to Kowloon Tong Village area.—The work, referred to in paragraph 192 of last year's Report, could not be started during the year as the layout of blocks to east of Nathan Square was still in abeyance. Special Vote Expenditure Expenditure to 31.12.30 $7,000.00 Nil. $15,000.00 $7,891.29 Total Estimates NEW KOWLOON. Servants Quarters and 235. Field Cottage-Additional Servants Quarters and reconditioning of building as Headquarters of the Flying Club. The work consisted of the addition of three small rooms and a coal Store for each of three floors of the Servants Quarters and the general renovation of the Main Building. The work, which was executed under the Maintenance of Buildings Contract, was commenced in February and completed in August.
Baseline (Original)
Works not appearing in Estimates.-New Kowloon. 110 232. Traffic Arrangement at Tsim Sha Tsui.-Alterations to the traffic arrangements at Tsim Sha Tsui were commenced towards the end of the year. This work consisted of the demolition of and re-erection on other sites of the existing Motor car shelter. Ricksha shelter, Motor Cycle shelter and Latrine. Contract were let to Messrs. Kin Lee & Co. in November and December and by the end of the year the greater part of the work was done. Special Vote Expenditure $11,060.00 $ 7,715.16 233. New Children's Playground, Kowloon.-This work was referred to in paragraph 177 of last year's Report. A contract for the erection of the Shelter, Swings, etc. was let to Messrs. Kin Lee & Co. in July the amount being $6,855.35. The work was commenced immediately and was completed early in October. The turfing of the whole playground was then commenced by the Botanical and Forestry Department and was completed by the end of October. Special Vote Expenditure $12,700.00 $11,221.99 234.Tong Mi-Extension of Storm Water Drain from Old Taipo Road to Kowloon Tong Village area.—The work, referred to in paragraph 192 of last year's Report, could not be started during the year as the layout of blocks to east of Nathan Square was still in abeyance. Special Vote Expenditure Expenditure to 31.12.30 $ 7,000.00 Nil. $15,000.00 $ 7,891.29 Total Estimates NEW KOWLOON. Servants Quarters and 235. Field Cottage-Additional -Additional Servants rèconditioning of building as Headquarters of the Flying Club. The work consisted of the addition of three small rooms and a coal Store or each of three floors of the Servants Quarters and the general renovation of the Main Building. The work, which was executed under the Maintenance of Buildings Contract, was commenced in February and completed in August.
2026-05-11 13:30:54 · Baseline
View content

Works not appearing in Estimates.-New Kowloon.

110

232. Traffic Arrangement at Tsim Sha Tsui.-Alterations to the traffic arrangements at Tsim Sha Tsui were commenced towards the end of the year. This work consisted of the demolition of and re-erection on other sites of the existing Motor car shelter. Ricksha shelter, Motor Cycle shelter and Latrine.

Contract were let to Messrs. Kin Lee & Co. in November and December and by the end of the year the greater part of the work was done.

Special Vote Expenditure

$11,060.00 $ 7,715.16

233. New Children's Playground, Kowloon.-This work was referred to in paragraph 177 of last year's Report.

A contract for the erection of the Shelter, Swings, etc. was let to Messrs. Kin Lee & Co. in July the amount being $6,855.35.

The work was commenced immediately and was completed early in October. The turfing of the whole playground was then commenced by the Botanical and Forestry Department and was completed by the end of October.

Special Vote Expenditure

$12,700.00 $11,221.99

234.Tong Mi-Extension of Storm Water Drain from Old Taipo Road to Kowloon Tong Village area.—The work, referred to in paragraph 192 of last year's Report, could not be started during the year as the layout of blocks to east of Nathan Square was still in abeyance.

Special Vote

Expenditure

Expenditure to 31.12.30

$ 7,000.00 Nil. $15,000.00 $ 7,891.29

Total Estimates

NEW KOWLOON.

Servants Quarters and

235. Field Cottage-Additional

-Additional Servants

rèconditioning of building as Headquarters of the Flying Club. The work consisted of the addition of three small rooms and a coal Store or each of three floors of the Servants Quarters and the general renovation of the Main Building.

The work, which was executed under the Maintenance of Buildings Contract, was commenced in February and completed in August.