TABLE 79

BUILDING PROGRAMME 1979/80

BUILDING OR EXTENSIONS TO EXISTING BUILDINGS COMPLETED

GOVERNMENT

(1) Extension and Improvements to Panling Hospital Phase I

5-storey extension built to accommodate a casualty unit, a X-ray unit, a family health service centre and staff quarters. The project was completed in November 1979.

(2) Queen Mary Hospital, additional staff quarters Phase II

20-atorey block to provide 80 Type I & II units of married quarters for medical and clinical lecturers. Completed in March 1980.

2.

(3) Central Government Offices, Dental Clinic an extension to

provide 3 additional dental surgeries. Completed in December 1979.

(4) Sai Kung Dispensary, temporary reprovisioning of the general

out-patient department at two shop uni te in Sai Kung tow. Fitting out work completed in July 1979.

PROJECTS UNDER CONSTRUCTION

II.

A.

Government

A now mental

(1) Peychiatric Wing, Princess Margaret Hospital

hospital of 1336 bede, will include two ward blocke and a clinical and services block, Expected completion date 18 July 1980.

(2) Fanling Hospital, Extension and Improvements Phase II

includes alterations and additions to the existing hospital facilities and 46 additional beds. Expected completion date is December 1980.

(3) Dental Teaching Hospital. Expected completion date is

August 1980.

(4) Sha Tin General Clinic – includes Maternity Child Health

Centre, Pamily Health Service, Out-patient Department and Community Health Education Centre. Expected completion date is September 1980.

(5) Sha Tin Hospital and Polyclinic

A regional hospital of 1400 beds, with teaching facilities, Expected complation date is September 1982.

(6) Tuen Mun Polyclinic, Phase I includes Out-patient

Department, Maternity Child Health Centre, Family Health Centre, Chest Clinic, Dental Clinic and X-ray Department. Expected completion date is July 1981.

B.

TABLE 79 (Cont'd)

(7) Tean Yuk Hospital, Pre-natal Diagnostic Laboratory

expected completion date is July 1980.

(8) Air Conditioning for two Floors of Princess Margaret

Hospital.

(9) Central Laboratory for Urine Teats Fo Men Tin Hethadone

Clinic.

(10) Medical & Health Departmental Laundry at Pik Uk.

(11) Ngau Tau Kok Urban Clinic.

Government-assisted

(1) Kwong Wah Hospital New Wing An 11-storey clinical

pathology building with a mortuary, an X-ray department, occupational therapy, physiotherapy and medical social service, a 40-bed orthopaedic ward, laboratory facilities for various pathological services, Expected completion date is 1980/81.

(2) Dental Teaching beds, Tung Wah Hospital conversion and upgrading of existing facilities of some 220 beds at the Centenary Building of the Hospital for use as teaching beds. Expected completion date is 1980.

(3) Pok Oi Staff Quarters

1980.

expected completion date is late

(4) Yan Chai Hospital extensi on

date te 1980/81.

Stage II

expected completion

III. PROJECTS INCLUDED IN THE DEVELOPMENT PROGRAMME

A.

Government

(1) Kowloon East Polyclinic, Stage II.

(2) Standard Clinic and School Children's dental clinic at

Lam Tin/Lei Yue Mun.

(3) Pupil Nurses Training School and quarters for Enrolled

Orthotic Training Nurses, Registered Nurses, Frosthetic School/Medical Social Workers Training Centre at Kowloon Hospital.

(4) Urban Clinic at Lei Muk Shue.

(5) Standard Urban Clinic, Area 11A, Ha Kwai Chung.

(6) Queen Elizabeth Hospital Additional Staff Quarters.

(7) Queen Mary Hospital

Pacilities.

Improvements to Car Parking