4. Application for construction noise permit for percussive piling

An application under section 8(2) of the Ordinance for a construction noise permit for the purpose of carrying out percussive piling between the hours of 7 a.m. and 7 p.m. on any day, not being a general holiday, shall be-

(a) in Form 2 in the Schedule; and

(b) submitted to the Authority together with the fee prescribed in regulation 8 and not earlier than 9 months prior to the date specified in the application for the commencement of the percussive piling unless the Authority agrees to accept submission of the application at an earlier time.

5. Form of construction noise permit

A construction noise permit issued-

(a) in respect of an application referred to in regulation 3, shall be in Form 3 in the Schedule; and

(b) in respect of an application referred to in regulation 4, shall be in Form 4 in the Schedule.

6. Form of noise abatement notice

A noise abatement notice served under section 13(1) of the Ordinance shall be in Form 5 in the Schedule.

7. Form of notice cancelling a noise abatement notice or varying any requirement therein

A notice served under section 13(4) of the Ordinance-

(a) cancelling a noise abatement notice shall be in Form 6 in the Schedule;

(b) varying any requirement in a noise abatement notice shall be in Form 7 in the Schedule.

8. Fees payable on application for a construction noise permit

(1) The fee payable on application for a construction noise permit referred to in regulation 3 shall be $100.

(2) The fee payable on application for a construction noise permit referred to in regulation 4 shall be $100.

Edit History

2026-05-05 03:56:23 · NVIDIA / meta/llama-4-maverick-17b-128e-instruct
Live
View comparison
AI Proofread
1989 Ed.] Noise Control (General) Regulations (CAP. 400 A 3 [Subsidiary]) 4. Application for construction noise permit for percussive piling An application under section 8(2) of the Ordinance for a construction noise permit for the purpose of carrying out percussive piling between the hours of 7 a.m. and 7 p.m. on any day, not being a general holiday, shall be- (a) in Form 2 in the Schedule; and (b) submitted to the Authority together with the fee prescribed in regulation 8 and not earlier than 9 months prior to the date specified in the application for the commencement of the percussive piling unless the Authority agrees to accept submission of the application at an earlier time. 5. Form of construction noise permit A construction noise permit issued- (a) in respect of an application referred to in regulation 3, shall be in Form 3 in the Schedule; and (b) in respect of an application referred to in regulation 4, shall be in Form 4 in the Schedule. 6. Form of noise abatement notice A noise abatement notice served under section 13(1) of the Ordinance shall be in Form 5 in the Schedule. 7. Form of notice cancelling a noise abatement notice or varying any requirement therein A notice served under section 13(4) of the Ordinance- (a) cancelling a noise abatement notice shall be in Form 6 in the Schedule; (b) varying any requirement in a noise abatement notice shall be in Form 7 in the Schedule. 8. Fees payable on application for a construction noise permit (1) The fee payable on application for a construction noise permit referred to in regulation 3 shall be $100. (2) The fee payable on application for a construction noise permit referred to in regulation 4 shall be $100.
Baseline (Original)
1989 Ed.] Noise Control (General) Regulations (CAP. 400 A 3 [Subsidiary] 4. Application for construction noise permit for percussive piling An application under section 8(2) of the Ordinance for a construction noise permit for the purpose of carrying out percussive piling between the hours of 7 a.m. and 7 p.m. on any day, not being a general holiday, shall be- (a) in Form 2 in the Schedule; and 5. (b) submitted to the Authority together with the fee prescribed in regulation & not earlier than 9 months prior to the date specified in the application for the commencement of the percussive piling unless the Authority agrees to accept submission of the application at an earlier time. Form of construction noise permit A construction noise permit issued- (a) in respect of an application referred to in regulation 3, shall be in Form 3 in the Schedule; and (b) in respect of an application referred to in regulation 4, shall be in Form 4 in the Schedule. ; 6. Form of noise abatement notice A noise abatement notice served under section 13(1) of the Ordinance shall be in Form 5 in the Schedule. 7. Form of notice cancelling a noise abatement notice or varying any requirement therein A notice served under section 13(4) of the Ordinance- (a) cancelling a noise abatement notice shall be in Form 6 in the Schedule; (b) varying any requirement in a noise abatement notice shall be in Form 7 in the Schedule. 8. Fees payable on application for a construction noise permit (1) The fee payable on application for a construction noise permit referred to in regulation 3 shall be $100. (2) The fee payable on application for a construction noise permit referred to in regulation 4 shall be $100. Į
2026-05-05 03:56:23 · Baseline
View content

1989 Ed.]

Noise Control (General) Regulations

(CAP. 400

A 3

[Subsidiary]

4. Application for construction noise

permit for percussive piling

An application under section 8(2) of the Ordinance for a construction noise permit for the purpose of carrying out percussive piling between the hours of 7 a.m. and 7 p.m. on any day, not being a general holiday, shall be-

(a) in Form 2 in the Schedule; and

5.

(b) submitted to the Authority together with the fee prescribed in regulation & not earlier than 9 months prior to the date specified in the application for the commencement of the percussive piling unless the Authority agrees to accept submission of the application at an earlier time.

Form of construction noise permit

A construction noise permit issued-

(a) in respect of an application referred to in regulation 3, shall be in

Form 3 in the Schedule; and

(b) in respect of an application referred to in regulation 4, shall be in

Form 4 in the Schedule.

;

6.

Form of noise abatement notice

A noise abatement notice served under section 13(1) of the Ordinance shall be in Form 5 in the Schedule.

7.

Form of notice cancelling a noise abatement

notice or varying any requirement therein

A notice served under section 13(4) of the Ordinance-

(a) cancelling a noise abatement notice shall be in Form 6 in the

Schedule;

(b) varying any requirement in a noise abatement notice shall be in

Form 7 in the Schedule.

8.

Fees payable on application for

a construction noise permit

(1) The fee payable on application for a construction noise permit referred to in regulation 3 shall be $100.

(2) The fee payable on application for a construction noise permit referred to in regulation 4 shall be $100.