1987 Ed.)
Air Pollution Control
[CAP. 311
33
6. The equipment and facilities to be provided for inspecting, sampling or measur-ing the emission of any air pollutant or any constituent thereof.
7. The maintenance and security of any equipment and facilities referred to in paragraph 6.
8. The provision to the Authority of samples, and of the results of the analysis of samples, of air pollutants or any material that may evolve air pollutants.
9. The keeping of records in relation to the matters mentioned in paragraphs 3 and 4.
10. The access of authorized officers to the equipment, facilities and records referred to in paragraphs 6 and 9.
11. Any matters relating to care and maintenance in relation to the provisions of paragraphs 3 and 4.
THIRD SCHEDULE
CHE
Item Specified Process Premises 1. Electricity Works Castle Peak “A” Power Station- Tap Shek Kok, New Territories (Tuen Mun Town Lot No. 220) 2. Electricity Works Castle Peak "B" Power Station- Tap Shek Kok, New Territories (Tuen Mun Town Lot No. 220) 3. Electricity Works Lamma Island Power Station-Po Lo Tsui, Lamma Island (Lot 1934 in Demarcation District No. 3) Picnic Bay, Lamma Island (Lot 64 in Demarcation District No. 6) 4. Cement Works Tap Shek Kok, New Territories (Tuen Mun Town Lot No. 201) 5. Cement Works Picnic Bay, Lamma Island (Quarry Allocation in Demarcation District No. 6) 6. Cement Works Tsing Yi Island (Tsing Yi Island Town Lot No. 75) 7. Chlorine Works Tsing Yi Island (Tsing Yi Island Town Lot No. 59) (Styrene Train No. 2) 8. Petrochemical Works 9. Gas Works Tai Po Area 26, New Territories (Tai Po Town Lot No. 46) (Amended, 23 of 1987, s. 17)[s. 20(2).]
FOURTH SCHEDULE
DETERMINATION OF COMPENSATION
(s. 26(2).]
1. A person who claims compensation under section 24 or 25 shall submit to the Authority particulars in writing of his claim.
2. (1) A claim under paragraph 1 shall be submitted-
(a) where a licence or exemption is cancelled, within 1 year after the can-cellation;
(b) where a licence or exemption is varied so as to impose additional obligations on either the licence holder or the owner of the premises used for the conduct of the specified process to which the exemption relates, as the case may be within 1 year after the completion of the works attributable solely to the requirement of the Authority.
1987 Ed.)
Air Pollution Control
[CAP. 311
33
6. The equipment and facilities to be provided for inspecting, sampling or measur-
ing the emission of any air pollutant or any constituent thereof.
7. The maintenance and security of any equipment and facilities referred to in
paragraph 6.
8. The provision to the Authority of samples, and of the results of the analysis of
samples, of air pollutants or any material that may evolve air pollutants.
9. The keeping of records in relation to the matters mentioned in paragraphs 3
and 4.
10. The access of authorized officers to the equipment, facilities and records referred
to in paragraphs 6 and 9.
11. Any matters relating to care and maintenance in relation to the provisions of
paragraphs 3 and 4.
THIRD SCHEDULE
CHE
Item
Specified Process
1.
Electricity Works
Premises
[s. 20(2).]
2.
3.
Electricity Works
Electricity Works
4.
Cement Works
5.
Cement Works
6.
Cement Works
7.
Chlorine Works
8.
Petrochemical Works
9.
Gas Works
Castle Peak “A” Power Station- Tap Shek Kok, New Territories (Tuen Mun Town Lot No. 220) Castle Peak "B" Power Station- Tap Shek Kok, New Territories (Tuen Mun Town Lot No. 220)
Lamma Island Power Station-Po Lo Tsui, Lamma Island (Lot 1934 in Demarcation District No. 3) Picnic Bay, Lamma Island (Lot 64 in Demarcation District No. 6) Tap Shek Kok, New Territories (Tuen Mun Town Lot No. 201) Picnic Bay, Lamma Island (Quarry Allocation in Demarcation District No. 6)
Tsing Yi Island (Tsing Yi Island Town Lot No. 75)
Tsing Yi Island (Tsing Yi Island Town Lot No. 59) (Styrene Train No. 2)
Tai Po Area 26, New Territories (Tai Po Town Lot No. 46) (Amended, 23 of 1987, s. 17)
FOURTH SCHEDULE
DETERMINATION OF COMPENSATION
(s. 26(2).]
1. A person who claims compensation under section 24 or 25 shall submit to the Authority particulars in writing of his claim.
2. (1) A claim under paragraph 1 shall be submitted-
(a) where a licence or exemption is cancelled, within 1 year after the can-
cellation;
(b) where a licence or exemption is varied so as to impose additional obligations on either the licence holder or the owner of the premises used for the conduct of the specified process to which the exemption relates, as the case may be within 1 year after the completion of the works attributable solely to the requirement of the Authority.
No comments yet.
Private notes are available after approval.