21. BASIS OF COST ESTIMATES
1. Prices ruling at the date of the estimate
(for proposed VOP contracts)
2. Prices ruling at the date of the estimate (for proposed firm price contracts)
3. Contracted prices - VOP contracts
4. Contracted prices - firm price contracts
5. Index value
6. Index name
22. REASONS FOR CHANGE IN COST ESTIMATE
1. External factors
2. Estimating changes
3. Design development
4. Client changes
5. Ground conditions
6. Contractor claims
7. Inflation
8. Other (specify)
Total (as diference between totals of 20(A) and 20(B))
23. CASH FLOW
(A) This submission
Year
£
92/93
400,000
93/94 3,280,000
94/95 12,250,000
95/96 10,050,000
96/97
1,570,000
Total
£27,550,000
(A)- This submission
Tick
Base date
/
MARCH 1993
N/A
MARCH 1993
N/A
(B) - Previous approval
Tick
£
£
Base date
(B) - Previous approval
dated
Year
£
Total
£