Mr Hum
RESTRICTED
[DRAFT]
FROM:
PF Ricketts
DATE:
CC:
Hong Kong Department
2 July 1993
PS/PUS
Sir J Coles
Mr Muir
Hds of OED
MVD
NTCD
Consular Dept
Security Dept
PMD
TSD
RFD
HKD
406/2
02 JUL 1993
Information Dept
FED ISD(S) ISD (0) PUSD
CRD MRS
Joint Directorate Senior British
Commissioner, HK Mr Gunesekera,
British Council
Chief Clerk
PS/Mr Goodlad
HONG KONG: NEW CONSULATE GENERAL
Problem
1.
Should construction of the new Consulate General building in Hong Kong now go ahead on the basis of current plans?
Recommendation
2. That we should proceed with the present design. This was the conclusion of a meeting of the Steering Committee chaired by you on 2 July, which considered the options presented by the MRS, and concluded that the present design strikes the best balance in dealing with the staffing problems caused by