RESTRICTED
From:
MHR Bertram, OED
Date:
CC:
31 March 1993
PS/PUS
Sir J Coles
Mr Muir
Mr Alston
Mr Pugh, British Council Senior British Trade
Commissioner, Hong Kong
Heads:
HKD MVD
NTCD
Consular Dept
Security Dept
TSD
RFD
нко
HILD 406/2
Information Dept
RF
FED
23 APR 1993
INU:
Mr Hum
Chief Clerk
PS/Mr Goodlad
ISD(S) ISD(0) PUSD
CRD MRS
Joint Directorate
HONG KONG : NEW CONSULATE-GENERAL
Problem
1. Final Sketch Designs are near completion for the new building to house the Consulate-General, British Council and some staff flats after 1997. The estimated cost is about £29 million (at current costs). Should we proceed?
Recommendation
2.
I recommend that we should proceed with the project at the estimated cost of about £29m, and that the Treasury's approval now be sought. The Hong Kong Steering Committee and the Senior British Trade commissioner's Co-ordinating Committee concur.